、编制依据湖北省XX设计院提供的施工图纸《电力建设施工验收及技术规范》《地基与基础工程施工及验收规范》(GBJ202-83)《建筑地基处理技术规范》(GJ79-91)《混凝土结构工程施工规范》(GB50204-92)《砌体工程施工及验收规范》(GBJ50203-98)《地面与楼地面工程施工及验收规范》(GBJ209-83)《屋面工程施工及验收规范》(GBJ207-83)《建筑装饰工程施工及验收规范》(JGJ73-91)《采暖与卫生工程施工及验收规范》(GBJ242-82)《通风与空调施工及验收规范》(GBJ243-82)《建筑电气安装工程质量检验评定标准》(GBJ303-88)《建筑地面工程施工及验收规范》(GB50209-95)《工程测量规范及条文说明》(GB50026-93)《屋面工程技术规范》(GB50207-94)《钢筋焊接及验收规范》(JGJ18-84)《水泥混凝土路面施工及验收规范》(GBJ97-87)《建筑安装工程质量检验评定统一标准》(GBJ300-88)《建筑工程质量检验评定标准》(GBJ301-88)《预制混凝土构件质量检验评定标准》(GBJ32221-91)《建筑安装工程质量检验评定标准》(TJ305-75)《建筑采暖卫生与煤气工程质量检验评定标准》(GBJ302-88)《通风与空调工程质量检验评定标准》(GBJ304-88)《钢结构工程施工及验收规范》(GB50205-95)《钢结构工程质量评定标准》(GB50221-95)《火电施工质量评定标准》(土建篇)《施工现场临时用电安全技术》(JGJ46-88)《建筑机械使用安全技术规程》(JGJ33-86)《电力建设安全施工管理规定》某局及本公司的企业标准某局某公司颁发的《质量保证手册》、《程序文件》目录前言

第一章:------------------------------------------工程概况及特点

第二章:------------------------------------------施工现场组织机构第三章:----------------------------------------施工现场总平面布置第四章:--------------------------------------------------施工方案第五章:----------------------------------------工期及施工进度计划第六章:------------------------------------质量目标、质量保证体系

第七章:------------------------------------------- 施工安全保证

第八章:----------------------------------------环境保护及文明施工第九章:------------------------------------计划、统计和信息管理

前言

一、编制说明:

为了更好的完成XX机房配电系统改造工程,进一步提高施工队伍的技术素质和管理水平,深化全面质量管理工作。根据北京电力公司工程施工管理要求,编制本工程施工组织设计。

编制施工组织设计的指导思想是:树立安全生产意识、质量保证意识、文明施工意识及为客户服务意识,以科学的管理方法,行之有效的规章制度,调动施工人员的积极性,按期保质的完成施工任务,真正做到以施工人员的工作质量保工程质量,保施工安全。

该组织设计综合了技术素质管理,施工组织措施、安全生产措施、施工方案进度、文明施工公约等方面的内容。是指导施工的具体文件,施工人员应认真遵照执行,为实现工程安全可靠顺利完工目标共同努力。我公司将确保本站工程质量和工期并达标投产,工程质量水平符合并达到电力部颁

发《质量验评标准》中的“合格”级标准。

第一章工程概况及特点

1.1工程概况

本工程包括安装高压开关柜12面、安装高压母线桥1座、更换变压器5台,改造低压母线5段、更换低压开关柜13面、变电系统二次配线及系统调试、新装设备交接电气试验等内容。我公司针对本工程要求,制定了详细的施工方案与临时电源计划,采取完善的安全技术措施,保证在配电站设备进行拆旧换新施工过程中,电台运行所需电源及工程施工用电部分能正常用电。工程名称:XX机房配电系统改造工程

建设单位: XXX

工程地点:XXXXXXX

工程规模:314平方米

1.2编制依据:

①设计图纸

②现场勘察

③设计院提供的平面图纸

④GB50303-2002《建筑电气工程施工质量验收规范》

⑤《供电安全工作现场规程》

⑥ISO9001-2000版质量体系

1.3工程特点及预案:

本工程是在运行设备上改造施工,要保证运行设备的运行安全,施工难度大、责任大。为此我公司认真勘查现场,仔细研究图纸,制定详细完备的施工方案,保证工程施工中正常必要的用电要求。采取落实有效施工预案是保证工程“合格”前提必不可少条件。

1.4工程施工管理

本工程实行项目经理制,为更好地配合生产厂家和建设方的工作,本工程设置二级建造师1名, 工程项目部由公司质监部专职质检员配合质量管理部门严格按照ISO9000执行,做好质量检验及评价工作;施工中安排一名资料员管理所有设备与施工资料。

第二章施工现场组织机构

2.1 工程组织机构

为了本工程的顺利施工,做到安全生产,文明施工,质量合格,我施工单位特成立XX 机房配电系统改造工程项目部,实行项目经理负责制,建立工程现场管理机构体系。

2.2组织机构

成立项目部负责本工程项目的全部施工组织工作。

工程项目经理

(公司授权)

班组质量员

2.3 主要负责人简介

项目经理: 1人质量负责人:1人

安全负责人:1人施工管理负责人:1人

技术负责人: 1人资料员:1人

主要负责人介绍

质安部部长

①项目经理:二级建造师. 主要职责抓好施工前的各项前期准备工作,安排总体施工计划,拟定重大施工方案,协调内外关系,疏通影响施工的渠道,有效控制施工进度、质量、成本及安全。同时作为本工程安全、质量和施工组织的第一责任者,接受各级管理部门的监督和指导。

②总工程师:首席工程师,负责本工程技术工作。

③质安部部长:全面负责本工程现场保卫安全及施工质量。

④施工管理及技术负责人:主要职责审核、制订各阶段、各工序的施工方案,制定技术措施,组织技术培训和工程交底,监督检查现场施工技术措施的落实情况,解决施工中的技术问题。组织开展施工中的技术管理工作并向工程项目经理负责。

⑤专职质量员:主要职责编制本工程质量工作计划,进行各分项、分部工程的质量检验,搞好质量控制,组织质量验收和质量评定工作,并定期召开现场生产质量例会,及时解决施工中的质量问题。

⑥专职安全员:根据工程进展和现场实际情况制定重点安全管理工作计划并审核施工安全技术措施。检查施工中的安全规程及安全技术措施的落实情况,监督检查职工的安全工作状况,在现场进行安全把关,进行施工安全评定与考核工作,并定期召开现场安全例会,分析安全生产情况,消除事故隐患。定期检查现场消防器材完好状况,组织现场文明施工评比活动。

⑦资料管理员:负责现场工程技术资料及管理资料的收集和整理工作,

做好竣工资料归档备案工作。

⑧专职料具员:对该工程材料进行统计,按材料供应计划向现场提供施

工材料及工具,并做好材料保管和协助工程核算工作。

第三章施工现场总平面布置

3.1施工现场-设计院提供图纸

3.2项目部设置在现场临时区域内,施工人员休息区、施工设备材料存放区、施工现场临时电源、运输通道、消防设施、施工作业场地等由项目部和施工组织方项目部协调总体布置,现场的布置应整齐美观,保证必要的施工通道和施工人员作业时所需的工作环境。施工现场应按要求在适当位置布置一定数量的消防设备,同时设置必要的安全护栏和标志。及时清除施工废弃料和包装物,保证施工作业按计划顺利进行。

第四章施工方案

4.1施工工序准备

本工程施工程序为:开工前准备阶段→高压开关柜基础制作安装→新高压开关柜及高压母线桥安装→高压开关柜二次系统配线、调试→用户高压倒路→拆除1#、2#、3#变压器及低压开关柜→安装新变压器、低压开关柜及低压母线→新设备试验、调整→验收、发电→拆除4#、5#变压器及5#低压进线开关柜和联络柜→安装4#、5#新变压器、5#低压进线开关柜和联络柜与低压母线→新设备试验、调整→验收、发电、交接。

4.2施工方案:

一、高压柜安装部分:

1、运输:新高压开关柜由配电室北门运输,在车上会同厂家与甲方人员共同

进行设备开箱检验,做好开箱记录,由吊车从车上吊至液压叉车上,用液压叉车运至室内,沿途门框如有阻碍可以先卸下,高压柜安装好后再将门装上.

2、安装;先按柜体尺寸现场加工安装设备基础,注意预留高压电缆和二次控制电缆位置。基础制作安装完毕后高压开关柜就位、固定及母线安装。

3、二次系统:高压开关柜一次系统完毕后进行二次电缆布线、接线、传动。

4、交接试验:高压开关柜一、二次系统全部完工后,按规程标准进行设备交接试验。出具试验报告,并整理成册。

5、验收:设备安装、试验完毕后,报甲方进行工程验收,做好验收记录。对甲方验收中提出的问题,现场及时进行处理。

6、发电:甲方验收合格后,由甲方组织进行10KV设备停电倒路,所有进线及出线电缆,由旧设备上倒至新设备上。所有电缆倒路完毕后发电,由10KV 新设备带所有负荷。

二、1#、2#、3#变压器及低压开关柜部分

1、停电:拉开1#、2#、3#变压器所有低压出线开关,停掉所有负荷以后拉开1#、2#、3#变压器高压开关。

2、拆除:经验电、挂地线等措施后,拆除变压器高、低压侧铜排,拆除变压器固定螺栓。所有部分拆除完毕后,将变压器移出室外,由吊车运走。低压柜经验电后,拆除所有母线排及固定螺栓,所有出线电缆做好标记后拆除,电缆头做好防护,重要路负荷用临时电缆接至运行柜备用开关,低压柜柜体用液压叉车运至楼两侧吊装孔处,由吊车运至室外。

3、运输:在车上会同厂家与甲方人员共同进行设备开箱检验,做好开箱记录。变压器用吊车吊至变压器室外平台上,由人工移到变压器室内设计位置。低压柜由楼两侧吊装孔吊至二楼,用液压叉车运至低压开关室。

4、安装:变压器就位后进行固定,固定完毕后进行设备外壳与中性点接地部分的制作安装,测量低压出线母排尺寸,进行变压器交接试验,做好试验记录,变压器交接试验后安装低压出线母排及高压电缆连接。低压开关柜基础进行打磨清理后,低压开关柜就位、固定,低压母线排安装、坚固后进行低压开关柜绝缘摇测,做好记录。

5、验收:整理所有资料,报甲方进行设备验收,做好验收记录,对验收中甲方提出的问题,现场及时处理。

6、发电:甲方验收合格后,由甲方组织进行新设备发电,变压器空载运行24小时,空载进行时注意进行变压器监控。

7、恢复低压出线:变压器空载运行24小时后将所有出线电缆按标记对照图纸接至新低压开关柜上。

三、4#、5#变压器及低压开关柜部分:

1、停电:拉开4#、5#变压器所有低压出线开关,停掉所有负荷以后拉开4#、5#变压器高压开关。

2、拆除:经验电、挂地线等措施后,拆除变压器高、低压侧铜排(5#变压器属于增容,原低压出线母排全部更换),拆除变压器固定螺栓。所有部分拆除完毕后,将变压器移出室外,由吊车运走。低压柜经验电后,拆除低压进线柜与联络柜母排,拆除低压开关柜固定螺栓,低压柜柜体用液压叉车运至楼两侧吊装孔处,由吊车运至室外。

3、运输:在车上会同厂家与甲方人员共同进行设备开箱检验,做好开箱记录。变压器用吊车吊至变压器室外平台上,由人工移到变压器室内设计位置。

4、安装:变压器就位后进行固定,固定完毕后进行设备外壳与中性点接地部分的制作安装,测量低压出线母排尺寸,进行变压器交接试验,做好试验记

录,变压器交接试验后安装低压出线母排及高压电缆连接。低压开关柜基础进行打磨清理后,低压开关柜就位、固定,低压母线排安装、坚固后进行低压开关柜绝缘摇测,做好记录,。

5、验收:整理所有资料,报甲方进行设备验收,对验收中甲方提出的问题,

现场及时处理。

6、发电:甲方验收合格后,由甲方组织进行新设备发电,变压器空载运行24小时,空载进行时注意进行变压器监控。

四、工程交接:

所有改造工程全部完工,经甲方验收合格并发电后,整理工程所有资料,装订成册后移交甲方。

4.3.1新设备安装前要对运至现场的设备认真进行开箱检验和进货检验工作,并认真填写《设备开箱检验记录》、《设备附件检查记录》,如开箱时发现问题应同时填写《不合格品评审处置单》,在施工中发现厂家产品问题应填写《设备处缺记录》向技术质量及物资供应部门上报,以便尽早处理,防止因设备质量问题影响工程质量和施工进度。

4.3.2由项目部负责组织有关人员进行施工图的审核工作、施工组织设计的编写和上报工作、重大施工方案的制定工作,由项目部组织在整体施工前进行施工技术交底、施工中按分部工程进行技术交底、在关键工序开工前进行分项工程技术交底。

4.3.3由工程项目部执行本工程的《施工组织设计》及部颁有关规程和公司所制订的安装作业指导书的执行情况。

4.3.4正式施工前,研究有关运行单位的反事故措施,进一步增强安装设备运行的可靠性。

4.3.5在开工前,由工程项目部按照IS09002标准的培训程序对工程特殊工艺做好人员技术培训和技术交底工作。

4.3.6结合本工程的实际情况,在施工现场成立Q C活动小组,针对施工中遇到的技术问题进行技术质量攻关工作,不断提高施工班组队伍的素质水平,进一步保证本工程的施工质量。

4.3.7工程所用的材料质量必须达到国家有关标准、规程、规范、技术条件中规定的标准和设计要求,必须具备出厂合格证、材质证明或有关试验报告。

4.3.8材料按计划采购、供应、运输,并派专人负责检查其质量。

4.3.9当可直接清点数量和观察到外观的产品运至施工现场时,现场施工人员应验证产品的数量、规格、型号,保存随产品发来的有关资料,并填写相应的开箱检验记录和进货检验记录。

4.3.10施工现场的材料管理人员对到场的设备材料要认真进行开箱检验工作,发现问题及时处理并汇报。同时要及时清点入库,妥善保管。贵重设备材料要有防盗措施。现场材料管理员应按照设备材料供应计划进行发放领用,并定期向项目部提供核算信息。

4.3.11施工现场准备根据项目部、施工班组、施工场地和运输道路的情况,在开工前由项目部组织有关人员在对现场进行调查后,选择材料堆放场地,并清理场地内运输通道杂物。

4.3.12施工力量配置根据本工程的实际工期要求,以及工程总体施工方案、基本工程量和国家综合劳动定额,计划投入技术员6人,力工根据施工进度做相应调整,以满足工程需要。

4.3.13施工技术力量配备

①施工相关文件

②施工图纸

③设备安装、使用说明书

④〈〈供电安全工作现场规程〉〉

⑤〈〈电气装置安装工程验收规范〉〉

⑥〈〈电力设备交接和预防性试验规程〉〉

⑦各种安装、调试记录。

4.3.14施工机具准备

施工用车

4.4设备安装技术交底

㈠安装施工工艺及进场检查项目

设备基础施工→设备进场检验→新设备安装→新设备试验调整→新设备发电→送电试运行→验收、竣工。

1.电缆支架必须接地(PE)或接零(PEN)可靠;新敷设电缆有标识。

2.现场高压电缆做交流工频耐压试验,高压柜做交流耐压试验:交流38KV/1

分钟,变压器做交流耐压试验:交流30KV/1分钟,高压避雷器做泄露电流试验。

㈡质量标准

施工方应使用最新颁布执行的国家标准、行业标准和IEC标准。

4.6施工中注意质量问题

1.定期对施工人员进行质量教育,提高质量意识,确保质量标准,施工规范进行施工。

2.严格执行质量检查程序,每道工序必须先自检、后互检、再进行交接检、隐检等项工作。

3.实行定人、定位、定分工、定职责的方法,将质量管理工作分解到每个人、每个施工部位,以提高工程质量。

4.严格进货检验和试验工作程序,所有设备均进行考察,验证合格后方可订货。进场后要会同专业技术人员,质检、物资人员进行开箱检验,合格后进入安装。其他材料根据北京市有关规定进行检查验收,对有试验要求的进行试验检查,做好验证记录,合格后方可进入安装。

5.过程检验和试验是保证工程质量的重要环节,有关人员必须按施工方案的要求和基本程序进行检验和试验,未经检验和试验或检、试验不合格的过程,不得转序。

6.每天晚上进行一次例会,提出并解决施工中出现的质量问题。

7.落实现场质量奖罚制,做到奖优罚劣,提高工程质量。

4.7工程成本控制措施

1.工程成本控制措施

①优化施工组织结构,提高职工素质及业务水平,挖潜堵漏,增产节支。

②统一指挥,合理布局,周密安排,均衡施工。

③运用网络技术和计算机专用管理软件对施工进度实行循环动态管理,随着工程进度做到合理、及时调整施工进度计划,指导施工作业。

④人工、材料、机械实行定额管理,超罚节奖。人工根据工程量和工序的要求合理调整结构,施工人员持证上岗,资金实行计划管理、指标管理。

⑤技术、质量、安全措施具体,减少一般质量、安全事故,杜绝重大质量事故和安全事故的发生。

⑥开展质量竞赛活动,保证每道工序的施工质量,杜绝返工,减少修理,提高效益。

⑦开展技术革新,推广应用新技术、新工艺,向技术要质量、要安全、要效益。

第五章工期及施工进度计划

5.1施工工期

高压柜安装部分:

计划开工日期:年月日

计划竣工日期:年月日

总日历工期:约10日历天。

变压器、低压柜及母线桥部分:

计划开工日期:年月日

计划竣工日期:年月日

总日历工期:约20日历天。

5.2工期保证措施

①从项目经理到项目部的各级负责人,应认真执行工程计划管理工程,项目部应对计划图根据实际情况进行及时调整,对不能落实计划的因素认真分析,找出原因并制定具体对策,以保证综合进度如期实现。

②项目部根据设计图纸做出施工图预算,对各项费用进行分解,编制施工任务单,按分部工程下达给各施工班组进行承包,提高施工效率。

③严格执行各项质量规程,按照ISO—9002质量认证体系的具体要求开展

施工,认真执行“三检制”,杜绝施工现场的质量事故和返工现象,从而保证工程的按期达标投产。

④做好工程的前期准备工作,做到组织、技术、资金、材料、机械具供应“五落实”,从各方面保证工程的顺利进行。

⑤采取工序搭接施工,缩短工期,合理利用工作日。

⑥开展各种施工竞赛活动,推广新技术、新工艺,提高工作效率。

⑦发挥全体职工的主观能动性,力争提前完成施工任务,缩短实际工期,

为北京电网的安全可靠运行创造有利条件.

5.3材料供应管理

本工程材料的供应管理,包括采购,运输、半成品加工、保管、质量检查的控制等,按照我处《质量体系程序文件》中的《JDG/WJ-03-401物资管理制度》程序执行。工程开工前由项目部按施工进度安排制定工程原材料及器材的供应计划,工由项目审批后实施。施工过程中随施工进度及时调整供应计划,同时积极与施工组织方材料供应部门协作,做好材料供应工作,以满足施工要求。

5.4工程进度横量图

第六章质量目标、质量保证体系

质量保证体系及技术组织措施将执行我处根据ISO9002标准建立的,(质量保证手册)和质量体系程序文件),同时严格执行作业指导书及施工组织方工程师的有关质量要求文件.

6.1质量方针

现代化管理.程序化施工.创精品工程.保顾客满意.

6.2质量目标:

分项工程移交合格率:100%

工程验收发电优良率:100%

6.3质量保证体系:

质量管理组织机构:

班组质量员

6.4主要职责

项目经理:做为本工程的质量第一责任人,对本工程的质量工作负

责,并接受质量管理部门的监督、指导。

技术负责人:协助项目经理做好本工程的质量日常管理工作,负责解决本专业的技术质量问题。

专职质量员:负责施工现场的质量检验和监督工作,对项目部负责,协助项目经理做好工程的质量工作。

施工班组:必须严格按照技术质量规范和质量体系文件中的要求进行施工,不断提高施工工艺和及施工质量。

6.5质量管理措施

为确保变配电室设备安装工程质量目标的实现,确保实现工程处“百

分之百达标投产发电”的目标,根据本工程特点,制定以下质量管理措施。

6.5.1准备阶段的质量把关

①由公司有关领导及各职能处室对本工程施工组织设计进行审批,通过后下达给项目部。

②坚持两级技术交底制度,在工程开工前,由工程处组织项目部有关管理人员,听取设计人员针对本工程的设计交底,由设计人员解答设计问题。工程开工前,由项目部对全体施工人员进行技术交底,对该工程设计意图及施工技术要求、质量标准、施工方案等进行详细说明。

③由项目部根据施工图纸及工程材料预算组织有关人员,全面落实本工程的材料、设备,由各专业施工人员、材料管理员组织清点,核对规格并进行外观检验。

④工程开工前由工程部组织有关工程技术人员对土建工程进行检验,对发现的质量问题及时汇报,并与施工组织方联系协商解决,对于隐蔽工程,要求土建单位提供施工记录。

6.5.2施工阶段的质量管理

①落实施工人员质量责任制,严格执行主设备挂牌制,保证施工质量。由项目部组织开展质量竞赛活动,增强职工的质量意识,及时消除各种质量缺陷。

②分部工程施工前,项目部组织施工班组进行分部技术交底并安排时间学习有关的规程、规范和作业指导书。

③对本工程初次采用的设备,设备安装前由项目部工程技术员对施工人员进行技术培训。

④设备安装前要对运至现场的设备认真进行开箱检验和进货检验工作,并认真填写《设备开箱检验记录》、《设备附件检查记录》,如开箱时发现问题应同时填写《不合格品评审处置单》,在施工中发现厂家产品

问题应填写《设备处缺记录》向技术质量及物资供应部门上报,以便尽早处理,防止因设备质量问题影响工程质量和施工进度。

⑤设备到现场后,项目部负责收集所带的各种技术资料、厂家说明书和产品合格证,对其进行整理汇集并妥善保管。配备的专用工具、操作器械、备品备件由专业施工负责入收集保管,并作详细记录,以备竣工时移交验收单位。

⑥施工过程中严格按照设计图进行施工,发现设计图纸、技术说明书有问题时,及时向项目部反映,由项目部与设计协商解决。设计变更、工程洽商由工程技术员统一管理,并做记录,在竣工图中如实反映工程变动。

⑦加强工序检验,坚持质量的三级检查制度:即施工班组检验百分之百,项目部检验百分之五十,施工处检验百分之二十。做到:自检不合格不移交;专检不合格不进入下道工序。在一道工序中,施工人员除应在工作完毕后进行检验外,还应在工序进行中根据设置的检验点做好施工记录,相衔接的两道工序,下道工序的施工人员施工前必须对上道工序施工质量进行检查。施工人员工作时要互相协调,互相帮助,保证本工序的施工质量。

⑧施工人员在各个分项工程完成后应认真填写施工记录。为了保证施工质量,项目部每周组织一次现场施工质量检查,现场质量管理小组每天进行各专业施工质量的监督检查。

⑨为了防止错用材料、设备影响施工质量,项目部对施工所用材料、设备重新进行核对、计算,并标注在施工图纸上。材料管理员可以按照施工图纸进行领料、发料,施工中如发现问题应及时上报项目部,以便其重新调整施工方案,确保施工质量。

⑩施工记录的填写必须真实、准确、及时。各分项工程完工报质量验收时,必须提交施工记录。

6.5.3竣工阶段的质量保证

6.3.3.1各分项(分部)工程完工后,施工记录上交项目部,由其组织内部质量验收,合格后报公司质安部,由公司组织竣工验收工作。

6.3.3.2各种施工资料、厂家技术文件、备品备件、专用工具应完好齐全(移交资料详见“施工班组在施工质量工作中竣工资料管理规定<试行>”)。工程验收前项目部向运行单位办理移交手续。

6.3.3.3各种竣工资料的填写要符合国家计量标准的要求和IS09002质量认证体系的要求。

6.3.3.4设备验收阶段,项目部要抽调专人配合试验、验收等工作,发现问题及时反映、及时处理。

6.3.3.5根据施工班组上报完工的情况,项目部按分项分部工程完成进度情况对工程质量进行评价:全部施工完成后,对整体工程进行综合评价,并据此计算工程质量优良率、合格率。

6.5.4质量管理检验的标准

本工程执行下列质量规程文件和质量认证体系程序文件中的下列有关程序:

1、《电气装置安装工程接地装置施工及验收规范》

2、《电气装置安装工程电缆线路施工及验收规范》

3、《电气装置安装工程电气设备交接试验标准》

4、电力部颁发的电力建设工程施工技术管理制度

5、华北电管局反事故措施

6、《送变电工程质量监督站质量监督检查典型大纲》

7、《质量保证手册》

8、《质量体系程序文件》

9、设计图纸、设计变更

10、电缆厂家须提供国家电线电缆检测中心或国家电网公司电力设备质量检

验测试中心的鉴定报告.

第七章施工安全保证7.1安全管理目标:

7.1.1安全方针:安全第一,预防为主

7.1.2安全管理目标:

①重伤以上人身事故0次;

②重大火灾事故0次;

③千元以上设备事故0次;

④重大交通事故0次;

⑤轻伤事故0次。

7.1.3 人身重伤及以上、群伤事故零次

7.1.4 输变电运行设备事故零次

7.1.5 重大施工机械、设备损坏事故零次

7.1.6 重大交通事故零次

7.1.7 火灾事故零次

7.1.8两低:

①人身轻伤负伤率低于2%

②大幅度降低施工组织方责任行车交通事故

7.1.9 一减少:

①减少施工现场的习惯性违章现象

7.1.10五加强:

①加强对习惯性违章的考核力度

②加强临时工的安全管理

③加强施工现场安技措施的落实

④加强交通安全管理

⑤加强对工地现场及库房的治安防范三提高:

⑥提高班组安全管理水平

⑦提高对事故预测预控能力

⑧提高安全员安全意识和素质

7.2安全保证管理机构:

2.1职责:

项目部:负责现场安全工作的管理组织。

质安组:传达上级指示、文件、电传等有关安全的各种通报,监督检查现场安全工作,组织安规考试等。

班组负责人(班长):负责班组施工、安全、协助项目经理做好各项工作。

安全负责人:负责对施工人员进行安全教育、安全规程培训及现场安全监察工作。

班组安全员:监督工作票执行情况,纠正现场各种违章及不安全现象,对现场防火工作及工作人员情绪随时观察检查,有问题及时上报。

7.3安全管理制度及办法:

35KV降压变电站设计

[目录] 前言 第一篇任务书 一、设计要求 二、原始资料 三、设计任务 四、设计成果 第二篇说明书 第一章概述 第二章主接线设计方案 第三章主变台数和容量的选择 第四章所变的选择和所用电的设计 第五章短路电流计算 第六章导体及电气设备的选择. 第三篇计算书 一、主变容量的计算 二、短路电流计算 参考资料

第一篇任务书 一、设计要求 1、建立工程设计的正确观点,掌握电力系统设计基本原则和方法。 2、培养独立思考、解决问题的能力。 3、学习使用工程设计手册和其他参考书的能力,学习撰写工程设计说明书。 二、原始资料 1、某国营企业为保证供电需求,要求设计一座35KV降压变电所,以10KV电缆给各车间供电,一次设计并建成。 2、距本变电所6Km处有一系统变电所,由该变电所用35KV双回路架空线路向待定设计的变电所供电,在最大运行方式下,待设计的变电所高压母线上的短路功率为1000MVA 。 3、待设计的变电所10KV无电源,考虑以后装设的组电容器,提高功率因素,故要求预留两个间隔。 4、本变电所10KV母线到各个车间均用电缆供电,其中一车间和二车间为一类负荷,其余为二类负荷,Tmax=4000h ,各馈线负荷如表1—1

5、所用电的主要负荷见表1—2

6、环境条件 1)当地最热月平均最高温度29.9°c,极端最低温度-5.9°c,最热月地面0.8m 处土壤平均26.7°c ,电缆出线净距100mm。 2)当地海拔高度507.4m。雷暴日数36.9日/年:无空气污染,变电所地处在 P≤500m·Ω的黄土上。 三、设计任务 1、设计本变电所的主电路,论证设计方案是最佳方案,选址主变压器的容量和台数。 2、设计本变电所的自用电路,选择自用变压器的容量和台数。 3、计算短路电流。 4、选择导体及电气设备。 四、设计成果 1、设计说明书和计算书各一份 2、主电路和所用电路图各一份 第二篇说明书 第一章概述 一、设计依据 根据设计任务书给出的条件。 二、设计原则

35KV某变电站综合自动化改造工程施工组织设计

35kV金熊变电站综合自动化改造工程施工设计方案

说明 一、本施工方案一式六份,分别送潜江供电公司生技部、安监部、调度、输变电工区,另一份放在施工现场,一份本单位存档。 二、施工方案经过上级审批通过后,必须严格按计划执行,各类施工必须按计划时间开工及在计划工期内完成。 三、施工方案中的各类施工,如涉及到需要办理停电第一种工作票时必须按规定报票。 四、较大型的施工项目,如需有关部门人员到施工现场的,应事先告知。 五、在施工过程中如需申请中间验收的应及时通知相关部门人员组织中间验收,并妥善保管中间验收结论。 六、工程完工后申请竣工验收,经验收合格后,办理竣工报告及移交相关资料等。

编制/日期:审核/日期:会审/日期:

批准/日期: 1 概况:为了进一步保护证电网的安全运行,提高供电可靠性,根据上级的工作安排,我们对35kV金熊变电站进行综自改造。具体内容为: 1.1 新增屏位基础及屏底电缆沟施工,室外电缆沟改造。 1.2 后台安装调试。 1.3 更换35KV主变保护测控屏、公用柜屏、直流屏、交流屏。1.4 新增35KV线路保护测控屏、远动屏、不间断电源柜。 1.5 更换10KV所属馈线保护装置8套及CT 9组,更换10VPT。

1.6 更换室外端子箱为不锈钢端子箱,新增检修端子箱。 1.7 更换相应的二次电缆。 1.8 室外电缆沟改造。 1.9更换站变为S11-100/35型。 1.10执行反措:屏柜接地铜排环状连接接地、CT二次N级在端子箱接地、PT二次N级引至保护屏接地、等等。 为了安全、优质、按时地完成此项工程,特编制本方案。 2组织措施: 2.1 工作负责人:xxx。 负责该项工程施工的组织、协调,根据工程进度调整工作计划和组织验收施工质量,保证工程进度和工程质量。督促全体工作人员认真执行安全措施,确保安全生产。 2.2 现场负责人:别必举。 负责该项工程施工的组织、协调。工作负责人不在现场的时候,履行工作负责人职责。 2.3 现场安全负责人:王卫华。 职责:督促全体施工人员认真贯彻执行国家颁布的安全法规,及企业制定的安全规章制度;深入现场每道工序,掌握安全重点部位的情况,检查各种防护措施,纠正违章指挥,违章作业,并建立违章作业登记;参加项目经理组织的定期安全检查,查出的问题要督促在限期内整改完成;发现危险及危害职工生命安全的重大安全隐患,有权力制止作业,并组织施工人员撤离危险区域;负责检查现场所做的安全措施是否符合实际,并做好危险点的分析与控制。 2.4 一次工作负责人:田刚。

电气工程35KV变电所电气施工方案

目录 一、工程概况及施工前准备 1、工程概况 (2) 2、施工前准备 (2) 二、设备材料验收 (2) 三、电气施工方法 (一)低压配电室电气设备安装调试………………………………3-10 (二)配电室高、低压受送电………………………………………10-12 (三)防爆区电气动力施工…………………………………………12-19 (四)防爆区电气照明施工…………………………………………19-20 (五)防爆区防雷拉地施工…………………………………………20-21 四、人员组织机构…………………………………………………………21-22 五、安全技术措施…………………………………………………………22-23

六、安全保证体系 (23) 七、质量保证体系 (23) 八、执行的技术标准及规范………………………………………………23-24 一、工程概况及施工前准备 1、工程概况 本工程为阿克苏华锦化肥有限责任公司年产30万吨合成氨及52万吨尿素项目。本方案为35Kv变电所电气施工方案,主要施工内容包括35KV高压配电室、6KV中压配电室、35/6KV变压器室及6KV电力电容器室的设备安装、调试。 在35KV变电所安装有两台16000KVA 35/6KV油浸式有载调压电力变压器,8面35KV高压柜,30面6KV中压金属封闭中置移开式开关柜,一套微机保护系统。 本总变电站两路35KV进线引自库车东城变电站35KV不同母线段,进站后组成单母线分段接线方式。6KV侧,主变压器进线两回路,汽轮发电机电源一回路,接线形式为采用单母线分三段形式。发电机组电源经电缆送至6KV 母线。正常生产时,由发电机组电源和一路变压器电源供给全厂负荷用电,当发电机出现故障退出运行时,则全厂负荷完全由系统供给。

35kV变电站电气设计

摘要 变电站是改变电压的场所。为了把发电厂发出来的电能输送到较远的地方,必须把电压升高,变为高压电,到用户附近再按需要把电压降低,这种升降电压的工作靠变电站来完成。变电站的主要设备是开关和变压器。按规模大小不同,称为变电所、配电室等。 随着现代工业的不断发展,人们对电力供应的要求越来越高,特别是供电的安全性、可靠性和稳定性。然而电网的安全性、可靠性和稳定性往往取决于变电站的设计和配置。出于对这几方面的综合考虑,本论文设计了一个35kV的降压变电站。 本次设计首先对负荷进行了分析与计算,根据负荷的大小选取主变压器型号,然后根据主接线的经济可靠、运行灵活的要求,为各电压等级选择接线方式,在技术和经济方面进行比较,灵活选取最优的接线方式。设计中还进行了短路电流的计算与高压设备的选择与校验,如高压断路器、高压隔离开关、高压熔断器、电压互感器、电流互感器等。此外设计还进行了防雷保护的计算与整定来保障整个系统的安全运行。 关键词:35kV变电站,变压器,防雷保护

Abstract The substation is a place to change voltage. In order to make the electric energy transport from the power plants to distant places, the voltage must be taken rise to become high voltage, and then according to the users’demand, the voltage should be reduced correspondingly. Above the work is completed by the substation .The main equipments of substation are switchgears and transformers. According to the different scale of the substation, the place is called power substation or power distribution room,etc.. With the development of modern industry, the demand of power supply is increasingly become higher and higher, especially the power supply safety, reliability and stability. However, the security, reliability and stability of power system are often depends on the substation’s design and configuration. By considering the several aspects, this thesis de- signed a 35kV step-down substation. First, this design has carried on the analysis and calculation of the load, according to the size of the load select the main transformer model, then according to the main-wiring’s requirements of economical, reliable, and flexible to select the connection mode for different voltage level. Compare in the aspects of technology and economy, select the optimal way of wiring flexibly. The design also carried out the calculation of short-circuit current as well as the selection and checking of the high pressure equipment, such as high-voltage circuit breaker, high-voltage isolator, high-voltage fuse, voltage transformer, current transformer, etc.. In addition, this paper also including the design and setting calculation of lightning protection to guarantee the security of the whole system. Key Words:35kV substation,transformer,lightning protection

35KV变电站土建方案

五、施工方案 组织机构图 1、主变压器基础 一侧预埋4根DN40镀锌钢管,一侧预埋2根DN50镀锌钢管。一端与基础顶平齐,另一端埋至就近电缆沟。基础尺寸 2.675*2.675,基础埋深为1.65M。基础混凝土采用C30,;垫层混凝土采用C15。钢材采用Q235B,焊条采用E43。钢筋采用HPB235级,基础钢筋保护层厚度40MM。油池混凝土地坪以0.5%坡度坡向集水井,最薄处不小于100MM。油池内

干铺卵石,粒径为50-80MM,铺设厚度不小于250MM。所有埋管管底标高度0.8M,伸入电缆沟时管口应高于沟底100MM。所有埋件焊缝均为满焊,焊缝高度为8MM。所有埋管弯曲半径不小于10倍管径。 励磁支架及基础 基础垫层采用C10混凝土,杯基采用C20混凝土,二次灌浆采用C25细石砼。电杆外形长度3500MM,地面以上2500MM。 防火墙施工:做100厚C10砼垫层,每隔200MM,横竖交错搭接直径为8和10的配筋。墙体与构造柱连接处砌成马牙槎,同时与墙体埋设钢筋拉结在一起。构造柱混凝土为C25砼,先砌墙后浇注。墙体0.000以下采用强度等级MU10机红砖,M10水泥砂浆砌筑。0.000以上采用强度等级MU10机红砖,M10混合砂浆砌筑。地面高度4500MM,最后压顶梁。 2、地基处理 各建构筑物基础基本以泥岩为持力层,基底与泥岩层间如有空隙采用毛石混凝土回填。 照明:全站照明采用正常照明和事故照明两种方式。 生产综合楼内正常电源电压采用交流380V,动力和照明系统共用的方式,由楼内主控室的交流屏供电。35KV配电室,10KV配电室、主控室、电容器室及接地变室设事故照明,事故照明电源电压采用直流220V,正常时由交流屏供电,当工作照明电源故障时,蓄电池直流系统应自动投入,由直流屏供电。楼内事故照明灯由事故照明箱集中控制,就地不设事故照明开关。 2.11 通风方案及设备选型 根据《35~110kV变电所设计规范》(GB 50059-1992)的规定,配电装置室等房间内每小时通风换气次数不应低于6次。接地变配电装置室需通风,通风采用自然进风、机械排风的方式,按照换气次数不小于

35kv变电所电气预防性试验安全技术措施

35KV变电所电气预防性试验 安全技术措施 一、概况: 根据《煤矿安全规程》第490、491条的规定及《煤矿电气试验规程》的要求,每年春季需要对矿井主要供电设备和电缆做预防性试验,以确保供电安全。按照集团公司电气试验室的统一要求,计划规定于2012年月日至日,对35KV变电所供电设备及电缆线路做预防性电气试验。本次试验工作由集团公司电气试验室负责,综合工区积极配合试验。为确保本次工作的安全顺利进行,特制定本措施。 二、施工组织: 1、试验负责人:集团公司电气试验室 2、配合施工负责人:徐贵远 安全负责人: 3、工区现场人员:徐贵远 4、配合试验人员: 三、试验准备工作 1、所有参加试验人员必须提前到施工试验现场,熟悉本变电所供电运行方式及现场试验环境,并学习本措施签字后方可参加施工。 2、试验前,由工区负责人将高压柜检查一遍,确保各

柜断路器分合动作准确无误,指示准确,并将各柜的完好整定值与实际整定值校对一遍,确保整定无误。 3、由集团公司实验室负责试验的安排工作,工区负责开关柜的停送电,电气工作票的签发及执行工作。试验前,将所用的两票全部准备好。 4、按照集团电气试验室负责人的要求,将试验用仪器全部接通电源。 四、35KV变电所正常运转状态为张株I回路为主运行回路,张株II回路为热备用回路。 (一)张株II 回路35KV电气设备预防性试验步骤: 1、牢阅电气工作票,填写倒闸操作票 2、穿戴绝缘用具并带验电笔 3、核对断路器,隔离开关运行状态 4、监护人唱票,操作人复诵。 5、停2#主变6KV出线盘602真空断路器及上下隔离开关6022、6023。 6、停2#主变35KV302断路器3002隔离开关;2#变压器停运,停II路电压互感器3004隔离开关。 7、对2#主变6KV出线盘6023验电,放电,挂三相短路接地线,挂停电牌。 8、停6kv联络开关柜,停6KVII段的所有开关柜断路器与上下隔离开关614、6006、606、608、604、612、610、

35kv变电所主要施工方案

35kv变电所主要施工方案

目录 工程概况 (2) 编制说明和依据 (2) 施工方法及技术要求 (2) 配电装置施工 (3) 电缆桥架施工 (5) 电缆敷设 (5) 电缆接线 (6) 试验项目标准 (7)

35kv变电所主要施工方案 工程概况 35kv变电所是江西星火有机硅厂25kt/a离子膜烧碱技改工程的主要施工内容,该变电所投运后,原35/10kv变电所的供配电设施拆除,保留35kv电源为降压站的备用电源。本工程所需的35kv电源将由110kv降压站提供。(110kv降压站已于2002年10月开始建设,下在建设中。)新建的35kv开关所,用于旧隔膜碱及新建离子膜碱的整流装置供电,在原户外35kv开关设备场地新建烧碱低压变电所,用于整个烧碱街区的低压供电。 编制说明和依据 因投标资料提供的设备不完整、不全面,其中对35kv开关所综合自动化系统无任何资料,现参考投标文件25kt/a离子膜烧碱技改工程量清单,根据以往类似工程的施工经验,现编制本方案,仅供参考,待设计图纸和详细设计资料齐全,依具体工程特点再对方案加以详细补充。 供电系统:35kv开关所主接线单母分段,两路进线电源引自厂内110kv降压站;35kv 配电设备采用35kv成套开关柜,与预留的滤波装置布置在一个建筑物内;35kv断路器采用SF6断路器;35kv开关柜控制及保护采用微机监控保护综合模块;35kv开关所为无人值班,断路器的操作及控制在整流控制中心实施,整流控制中心布置在烧碱低变电所上面。 编制依据如下: (1)《电气装置安装工程高压电器施工及验收规范》(GBJ147-90)。 (2)《电气装置安装工程高压电器施工及验收规范》(GBJ147-90)。 (3)《电气装置安装工程高压电器施工及验收规范》(GBJ147-90)。 (4)《电气装置安装工程高压电器施工及验收规范》(GBJ147-90)。 施工方法及技术要求 主变压器就位在变压器基础验收移交后,对周边施工场地进行平整和夯实。根据变压器的外形尺寸,预先制作好变压器拖运架。变压器在现场卸车时要有防止倾倒措施,一般倾角不得小于规定的角度,要严禁冲击和严重振动等情况。现场卸车地点应土质坚

35kV箱式变电站设计(样本)

目录 摘要 (Ⅰ) Abstract (Ⅱ) 第1章绪论 (1) 1.1 供配电技术的发展 (1) 1.2箱式变电站的类型、结构与技术特点 (1) 1.2.1 箱式变电站的类型 (1) 1.2.2 箱式变电站的结构 (1) 1.2.3 箱式变电站的技术特点 (2) 1.2.4 箱式变电站与常规变电站的对比分析 (3) 1.3 箱式变电站的技术要求与设计规范 (5) 1.3.1 额定值 (5) 1.3.2 设计和结构 (6) 1.3.3 使用条件 (7) 1.3.4 箱体要求 (8) 1.3.5箱式变电站内部电器设备 (8) 1.4 本课题的主要任务 (8) 第2章35kV箱式变电站总体结构设计 (9) 2.1 电气主接线的确定 (9) 2.1.1 主接线的基本形式 (9) 2.1.2 箱式变电站对主接线的基本要求 (9) 2.1.3 主接线的比较与选择 (10) 2.1.4 高压接线方式 (11) 2.2 箱式变电站箱体的确定 (11) 2.2.1 箱体的结构的确定 (11) 2..2.2 合理配置 (11) 2.3 变压器 (12) 2.3.1 变压器容量、接线组别的确定 (12) 2.3.2 变压器的散热处理 (13) 2.3.3 用负荷开关—熔断器组合电器保护变压器 (13)

2.4 箱式变电站总体布置 (14) 第3章35kV箱式变电站一次系统设计及设备选型 (15) 3.1 主电路设计 (15) 3.1.1 概述 (15) 3.1.2 一次系统设计原则 (15) 3.1.3 一次系统设计 (15) 3.2 设备选型 (16) 3.2.1 箱式变电站设备选型应注意的方面 (16) 3.2.2 设备选型的基本原理 (17) 3.2.3 高低压电器设备选择的要求 (18) 3.2.4 断路器的选型 (19) 3.2.5 熔断器的选型 (19) 3.2.6 互感器的选型 (21) 3.2.7 隔离开关的选型 (22) 3.2.8 开关柜的选型 (22) 第4章35kV箱式变电站二次系统设计 (23) 4.1 电气二次系统设计 (23) 4.1.1 二次系统定义及分类 (23) 4.1.2 电气测量仪表 (23) 4.1.3 二次系统设计 (23) 4.2 二次系统总体方案 (24) 4.3 断路器控制与信号回路 (25) 4.3.1 概述 (25) 4.3.2 控制回路设计 (26) 4.3.3 信号回路设计 (26) 4.4 电气测量与信号系统 (26) 第5章箱式变电站智能监控功能设计 (28) 5.1 箱式变电站的监控内容 (28) 5.1.1 电量监测与保护 (28) 5.1.2 防凝露保护 (28) 5.1.3 变压器室温度保护 (28)

35KV变电站毕业设计(完整版)

35kV 变电站设计原始数据 本次设计的变电站为一座35kV降压变电站,以10kV给各农网供电,距离本变电站15km和10km 处各有一个系统变电所,由这两个变电所用35kV双回架空线路向待设计的变电站供电,在最大运 行方式下,待设计的变电站高压母线上的短路功率为1500MVA。 本变电站有8回10kV架空出线,每回架空线路的最大输送功率为1800kVA其中#1出线和#2 出线为I类负荷,其余为U类负荷及川类负荷,Tmax=4000h,cos? =0.85。 环境条件:年最高温度42 C ;年最低温度-5 C;年平均气温25 T ;海拔高度150m 土质为粘土;雷暴日数为30 日/ 年。

35KV变电站设计 、变电站负荷的计算及无功功率的补偿 1. 负荷计算的意义和目的 所谓负荷计算,其实就是计算在正常时通过设备和导线的最大电流,有了这 个才可以知道选择多大截面的导线、设备。负荷计算是首要考虑的。要考虑很多因素才能计算出较为准确的数值。如果计算结果偏大,就会将大量的有色金属浪费,增加制作的成本。如果计算结果偏小,就会使导线和设备运行的时候过载,影响设备的寿命,耗电也增大,会直接影响供电系统的稳定运行。 2. 无功补偿的计算、设备选择 2.1无功补偿的意义和计算 电磁感应引用在许多的用电设备中。在能量转换的过程中产生交变磁场,每个周期内释放、吸收的功率相等,这就是无功功率。在电力系统中无功功率和有功功率都要平衡。有功功率、无功功率、视在功率之间相互关联。 S ,卩厂Q2 S——视在功率,kVA P――有功功率,kW Q 无功功率,kvar 由上述可知,有功功率稳定的情况下,功率因数cos ?越小则需要的无功功 率越大。如果无功功率不通过电容器提供则必须从该传输系统提供,以满足电力 线和变压器的容量需要增加的电力需求。这不仅增加了投资的供给,降低了设备的利用率也将增加线路损耗。为此对电力的国家规定:无功功率平衡要到位,用户应该提高用电功率因数的自然,设计和安装无功补偿设备,及时投入与它的负载和电压的基础上变更或切断,避免无功倒送回来。还为用户提供了功率因数应符合相应的标准,不然,电力部门可能会拒绝提供电力。所以无功功率要提高功率因素,在节约能源和提高质量具有非常重要的意义。无功补偿指的是:设备具有容性负载功率和情感力量负荷,并加入在同一电路,能量的两个负载之间的相互交换。 无功补偿装置被广泛采用在并联电容器中。这种方法容易安装并且施工周期短,成本低易操作维护。 2.2提高功率因数 P——有功功率 S1――补偿前的视在功率 S2补偿后的视在功率 Q1补偿前的无功功率 Q2补偿后的无功功率 ? 1――补偿前的功率因数角

35KV变电所施工组织设计

35KV变电所电气工程施工组织设计 1.工程概况 35KV变电所是科苑集团高新技术产业区内的唯一一座35KV变电所,两台主变压器容量为 3150KVA,35KV和10KV主结线均采用单母线分段方案。35KV变电所电源采用双回路进线,主 供线引自城东变35KV专用线路,备用线引自贝斯特轻化厂与科苑集团间的35KV联络线,并采用 冷备用运行方式。 变电所布置采用全屋内式,配电室为二层半结构,上层为35KV开关室及控制室,底层为 10KV开关室及电容器室,中间为电缆夹层。变电所内共有电气设备55台,内部电缆3.2km。 2.主要实物工程量 名称型号规格 数量 电力变压器 SZ9-3150/35 2台 35KV开关柜 KYN10-40.5 11台 10KV开关柜 GZS1-10 16台 电容器柜 GR-1 4台 控制,保护,计量屏 GK-1 11台 直流电源屏 DUN186-48/20,100AH 2台 所用电屏 GCS 2台 母线桥 (厂家配套) 4套 照明配电箱 DCX(R) 2台 事故照明配电箱 XLS-40(改) 1台 照明灯具 87套 照明配管 PVC 770m 管内穿线 2620m

接地极 L50*50*5 15根 避雷带 -12*4 120m 避雷引下线 -12*4 190m 接地线 -25*4 280m 电缆 3.2km 3.施工依据 1)施工图00113DS-5和枝术签证。 2)现行的国家标准------电气装置安装工程施工及验收规范: 高压电器施工及验收规范 GBJ147-90 电力变压器,油浸电抗器,互感器施工及验收规范 GBJ148-90 母线装置施工及验收规范 GBJ149-90 电气设备交接试验标准 GB50150-91 电缆线路施工及验收规范 GB50168-92 接地装置施工及验收规范 GB50169-92 盘柜及二次回路结线施工及验收规范 GB50171- 92 蓄电池施工及验收规范 GB50172-92 电力变流设备施工及验收规范 GB50255-96 1KV及以下配线工程施工及验收规范 GB50258- 96 电气照明装置施工及验收规范 GB50259-96 4.施工方法 4.1设备安装 设备基础槽钢在制作前应调直,焊接应牢固。安装后基础槽钢的不直度、水平度、位置误

35kv变电站设计

项目设计报告 项目名称:35KV电源进线的总降变配电设计专业:电气自动化技术 班级: 姓名: 学号: 指导老师: 2016年7月13日

目录 前言 (2) 一:原始资料分析 (3) 1.1负荷资料 (3) 1.2各车间和生活变电所的地理位置图 (3) 1.3电源资料 (4) 1.4气象及水文地质资料 (4) 二、负荷计算 (4) 2.1负荷计算所需公式、材料依据 (4) 2.2 各车间的计算负荷 (4) 2.3总降的负荷计算 (5) 2.4 导线选择 (7) 2.5所选变压器型号表 (8) 三、主接线方案的选定 (8) 四、短路电流的计算 (9) 4.1计算方法的选择 (9) 4.2标幺值计算 (10) 五、电气设备的选择和校验 (14) 5.1高压设备选择和校验的项目 (14) 5.2 高压设备的选择及其校验 (14) 5.3 10KV一次设备选择 (15) 六、二次保护 (15) 6.1 二次保护原理图及其展开图 (15) 6.2 二次保护的整定及其灵敏度校验 (17) 七、变电所选址及防雷保护 (18) 7.1 变电所选址 (18) 7.2 防雷保护资料分析 (20)

7.3避雷针的选择 (20) 7.5对雷电侵入波过电压的保护 (20) 前言 随着人们生活质量的日益提高,用电水平的不断上升,对电能质量的要求也日益增长。而在工厂、企业中,通过对配电系统的建立,就可以对自身整体的电能使用情况和设备运行状态做到全面了解和控制,对今后生产的调整进行有效的电力匹配,减少和杜绝电力运行中的安全隐患,提高设备运行效率,提供基础的数据依据,使整个工厂电力系统更经济、安全、可控。 供电技术是分配和合理使用电能的重要环节,本着对供电的四点要求 即:安全,应按照规范能充分保证人身和设备的安全;优质,能保证供电电压和频率满足用户需求;灵活,能满足供电系统的各种运行方式,有改扩建的可能性;经济,尽量使主接线简单、投资少、节约电能和有色金属消耗量。我们在掌握理论知识的基础上,来设计该工厂分级供电的系统设计和规划。 在设计过程中,参照工厂的原始设备资料进行负荷计算,由此得出的结果来选择确定车间的负荷级别,然后根据车间负荷及负荷级别来确定变压器台数和变压器容量,由此选择主接线方案。再通过短路电流的计算来选择高低压电器设备和电力导线等。考虑并设计防雷和接地装置。

35KV降压变电所设计方案

35KV降压变电所设计方案 第一篇任务书 一、设计要求 1、建立工程设计的正确观点,掌握电力系统设计基本原则和方法。 2、培养独立思考、解决问题的能力。 3、学习使用工程设计手册和其他参考书的能力,学习撰写工程设计说明书。 二、原始资料 1、某国营企业为保证供电需求,要求设计一座35KV降压变电所,以10KV电缆给各车间供电,一次设计并建成。 2、距本变电所6Km处有一系统变电所,由该变电所用35KV双回路架空线路向待定设计的变电所供电,在最大运行方式下,待设计的变电所高压母线上的短路功率为1000MVA 。 3、待设计的变电所10KV无电源,考虑以后装设的组电容器,提高功率因素,故要求预留两个间隔。 4、本变电所10KV母线到各个车间均用电缆供电,其中一车间和二车间为一类负荷,其余为二类负荷,Tmax=4000h ,各馈线负荷如表1—1 序号车间名称计算用有功功率 (kw) 计算用无功功率 (kvar) 1 一车间 1046 471

2 二车间 735 487 3 机械车间 808 572 4 装配车间 1000 491 5 锻工车间 920 276 6 高压站 1350 297 7 高压泵房 737 496 8 其他 931 675 5、所用电的主要负荷见表1—2 序号车间名称额定容 量(KW) 功率因 素 (cos ) 安 装 台 数 工 作 台 数 备注 1 主充电机20 0.88 1 1 周期性负 荷 2 浮充电机 4.5 0.85 1 1 经常性负 荷 3 蓄电池室通 风2.7 0.88 1 1 经常性负 荷 4 室装配装置 通风110.79 2 2 周期性负 荷 5 交流焊机10.5 0.5 1 1 周期性负 荷

煤矿地面35kV变电站的设计毕业设计(论文)

摘要 本设计初步设计了煤矿地面35kV变电站的设计。其设计过程主要包括负荷计算、主接线设计、短路计算、电气设备选择、继电保护方案、变电所的防雷保护与接地等。通过对煤矿35KV变电站做负荷统计,用需用系数法进行负荷计算,根据负荷计算的结果确定出该站主变压器的台数、容量及型号。用标幺值法对供电系统进行了短路电流计算,为电气设备的选择及校验提供了数据。根据煤矿供电系统的特点,制定了矿井变电所的主结线方式、运行方式、继电保护方案。其中35KV 侧为全桥接线,6KV主接线为单母分段。两台主变压器采用分列运行方式。并根据电流整定值以及相关数据的校验,选择了断路器、隔离开关、继电器、变压器等电气设备。 关键字:负荷计算; 变电站; 继电保护;运行方式

目录 摘要 (1) ABSTRACT .............................. 错误!未定义书签。 1 概述 (1) 1.1 设计依据 (1) 1.2 设计目的及范围 (1) 1.3 矿井基础资料 (1) 2 负荷计算 (4) 2.1 负荷计算的目的 (4) 2.2 负荷计算方法 (4) 2.3 负荷计算过程 (5) 2.3.1 各用电设备组负荷计算 (5) 2.3.2 低压变压器的选择与损耗计算 (8) 2.3.3 6kV母线侧补偿前总计算负荷 (11) 2.3.4 无功补偿计算及电容器柜选择 (11) 2.3.5 补偿后6kV母线侧总计算负荷及功率因数校验 . 12 3 变电所主变压器选择 (13) 3.1 变压器的选取原则 (13) 3.2 变压器选择计算 (13) 3.3 变压器损耗计算 (14) 3.4 35kV侧全矿负荷计算及功率因数校验 (15) 3.5 变压器经济运行方案的确定 (15) 4 电气主接线设计 (16) 4.1 对主接线的基本要求 (16) 4.2 本所电气主接线方案的确定 (16) 4.2.1 确定矿井35kV进线回路 (16) 4.2.2 35kV、6kV主接线的确定 (17) 4.2.3下井电缆回数的确定 (17) 4.2.4 负荷分配 (18) 5 短路电流计算 (20) 5.1 短路电流计算的目的 (20) 5.2 短路电流计算中应计算的数值 (20) 5.3 三相短路电流计算计算的步骤 (20) 5.4短路电流计算过程 (21) 5.5短路参数汇总表 (30) 5.6 负荷电流统计表 (32) 6 高压电气设备的选择 (33)

35KV变电站施工方案

XXX工程 变电站施工方案 2015年3月

批准审核编制

目录 编制依据及说明 6 工程概况程特点 6 工期和质量目标 8 第一部分 35KV变电站 ⒈工作概况及施工内容 8 ⒉工期安排和保证措施 9 ⒊工期质量指标 12 ⒋质量保证措施 12 ⒌设备安装及调试工序 14 ⒌1高压变压器安装、调试 14 ⒌2高压电气设备安装、调试 19 6.自检与专检 23 7.高压盘柜安装 24 7.1盘柜安装工艺流程 24 7.2盘柜安装主要技术要求 25 8. 系统受电 25

第二部分附属设施电气/仪表及全站电缆敷设工程 ⒈工程概况 26 ⒉工作内容 26 3.盘、箱柜安装 26 4.电缆支架制作 31 5.电缆支架安装 31 6.电气配管 31 ⒎电缆敷设及接线 33 8.照明系统安装 37 ⒐接地系统安装 38 ⒑防火工程 40 11.供配电调试 41 12.保护继电器单体试验 42 13.低压配电盘调试 43 14.低压试送电检查 43 15.受电运行 43 16.电气传动部分调试 44 17.硬件检查测试 45 18.应用软件调试 46 19.综自设备调试 46 工期及施工进度安排 49 21.安全措施 49

22.质量管理措施 51 23.质量程序及检验项目 52 24.安全目标、安全保证体系及材料组织措施 53 25.重点专业的安全控制措施 55 26.环境保护及文明施工 56 27.文明施工目标及实施方案 57 28.文明施工考核、管理办法 58 附表:浚县光明35KV变电站电气安装人员安排

编制依据及说明 根据浚县供电公司《浚县35KV光明站输变电安装工程招标文件》的要求和工程设计图纸。 编制依据 (1)鹤壁黎源电工有限公司根据《浚县35KV光明站输变电安装施工合同》。 (2)浚县光明35KV输变电工程设计图纸。 (3)建筑工业部颁布的现行工程建设施工标准、规程、规范和验评标准。 (4)《电气装臵安装工程质量检验及评定规程》(DL/T 5161.1~17-2002) (5)原电力工业部《施工组织设计导则》 (6)原电力工业部《电力建设施工及验收技术规范》(电气篇) (7)原电力工业部《电力建设安全施工管理规定》 (8)《工程建设标准强制性条文》(2006版)(电力工程部分)(建设部建标【2006】102号) 工程概况 浚县光明站35KV输变电工程(电气部分)由:35kV变电站接地网敷设、全站电缆敷设、站内电气工程几部分组成。

35kV降压变电站电气部分设计毕业设计

35kV降压变电站电气部分设计毕业设计 目录 摘要................................................. ABSTRACT .............................................. 目录 ................................................ 毕业设计任务书......................................... 前言 .............................................. 一毕业设计概述 (1) 1.1毕业设计题目 (1) 1.2毕业设计目的 (1) 1.3毕业设计内容 (1) 二 35KV降压变电站设计 (2) 2.1设计原则及特点 (2) 2.2设计原则 (2) 2.3设计特点 (2) 2.3设计说明 (2) 三主变压器的选择 (3)

3.1主变压器容量、台数、型号选择 (3) 3.2站用变压器选择 (4) 3.3低损耗配电变压器的结构 (5) 3.4低损耗配电变压器的特点 (6) 3.5油浸式变压器防火安全措施 (6) 四变电站电气主接线设计 (8) 4.1电气主接线的基本要求和原则 (8) 4.2电气主接线设计程序 (9) 4.3电气主接线设计 (11) 五短路电流计算 (15) 5.1短路概述 (15) 5.2造成短路原因 (15) 5.3短路危害 (15) 5.4短路计算 (16) 六电气设备的选择 (22) 6.1电气设备及分类 (22) 6.2电气设备的选择 (23) 七防雷保护设计 (32) 7.1雷电过电压 (32) 7.2雷电的危害 (32) 7.3防雷保护装置 (32)

35KV变电所设计配置方案

广州华立科技职业学院 毕业设计(论文) 中文题目: 35KV变电所设计配置方案 英文题目:35KV substation design configuration program 学生姓名: 学号: 专业: 指导老师姓名: 论文提交时间:

内容摘要 变电所即改变电压的场所。是介于发电与用电的环节,对于电力系统的稳定性、安全性和效率有着极为重要的作用。35kV相比于110kV以及220kV来说,35kV属于小型容量的变电所。这种小型的变电所在诸如北上广深等用电量大、经济发达的一线城市已不再进行建设,但在二、三、四线城市以及农村等依旧仍将长期存在。本文依据总体情况,就县、乡(镇)以及农村35kV提出合理的设计解决方案以及适用范围。 关键字:小型化 35kV变电所设计方案

ABSTRACT The place where the voltage changes. Is between the power generation and electricity links, for the stability of the power system, safety and efficiency has a very important role. 35kV compared to 110kV and 220kV, 35kV is a small capacity of the substation. This small substation, such as Beijing , Shanghai, Guangzhou and Shenzhen and other large electricity consumption, economically developed first-tier cities are no longer construction, but in the second, third and fourth tier cities and rural areas will still exist for a long time. Based on the general situation, this paper puts forward reasonable design solution and scope of application to county, township (town) and rural 35kV. Keywords: miniaturization 35kV substation design

35kV变电站典型方案设计技术原则

35kV变电站典型方案设计编制原则 1 总则 1.1 本原则基于以下基本原则 1.1.2变电站全部按无人值班变电站设计,设备选型原则是高可靠性、高技术含量、少维护或免维护、无油化、小型化。根据电网现状及规划,变电站主接线力求简单、可靠。 1.1.2主接线及设备选型应满足遥控实现运行方式改变和电能质量调整的需要,减少运行人员的现场操作。 1.1.3在主接线、设备选型及平面布置上,应考虑电网现状及规划,城市中心区、城区及城郊等不同地域的负荷密度和性质,变电站在电网中的重要性及投资效益等因素,通过经济技术分析,选取优化方案。 1.1.4 变电站主变压器一般为2或3台,在负荷密度较大且重要的地区,宜采用3台,并应满足当一台停运(故障)时,其余主变容量应不小于60%的全部负荷。 1.1.5 短路电流的确定,按可能发生最大短路电流的正常接线方式确定,不考虑切换过程中并列运行方式。变电站在允许电压波动范围内,主变压器低压侧最大短路电流应控制在:10kV不大于16kA,否则应采取降低短路电流的措施。 1.1.6变电站宜采用电气闭锁或机械闭锁,实现完善的五防闭锁功能。条件允许时也可采用微机五防闭锁。 1.1.7 变电站应设置防火、防盗设施。 1.1.8变电站应合理控制工程造价,尽量减少占地面积,弱化室内装饰,外装饰应与当地环境相协调。 2 主接线 2.1当35kV进线两回,且两台主变时,宜采用内桥接线。35kV线路有转供负荷,且进线三回及以上时,宜采用单母线分段接线。当3台主变压器时,宜采用扩大内桥接线或线变组接线方式。 2.2 当主变压器为两台时,10kV侧宜采用单母线分段接线。当主变压器为三台时,10kV宜采用单母线四分段接线方式。 3 设备选型 3.1 主变压器 3.1.1主变压器应采用低损耗、低噪音产品。低损耗指标参照10型标准;低噪音指标:控制在60dB 以下。 3.1.2 市区变压器宜选用自冷有载调压型,郊区宜选用风冷型。 3.1.3 变压器与GIS不宜采用油气联接方式。 3.1.4 主变压器容量及组别 3.1. 4.1主变压器容量 一般宜选用20MVA;高负荷密度地区可选31.5MVA。 3.1. 4.2 电压及组别 35±3×2.5%/10.5kV YN,d11 3 .2 其它主要设备选型 3.2.1 户外设备应加强外绝缘,选取防污型产品,泄露比距按污秽等级确定,最低不得小于2.5cm/ kV。 3.2.2 35kV配电装置可选用金属铠装可移开式或固定式开关柜、敞开式组合电器、敞开式断路器,断路器选用SF6或真空型,操作机构优先选用弹簧机构。 3.2.3户外35kV隔离开关宜选用高可靠一体化产品。主刀采用电动机构,地刀采用手动机构,瓷柱采用高强瓷,抗弯强度不小于8kN。 3.2.4户外35kV电流互感器城区变电站一般选用干式或SF6型,郊区一般选用油浸式;电压互感器宜选用电容式。 3.2.5避雷器:应采用硅橡胶或高瓷质外绝缘的氧化锌产品。 3.2.6 10kV开关柜选用金属铠装可移开式;断路器选用真空或SF6型。 3.2.7 开关柜应具备完善的五防闭锁功能。 4 配电装置型式 4.1 配电装置型式的选择应考虑所在地区的地理位置及环境条件。市区内优先选用占地少的户内配电装置型式,郊区可采用敞开式设备户外布置。 4.2根据《工业企业厂界噪声标准》(GB12348-90)和《城市区域环境噪声标准》(GB3096-93),变电站的运行噪音应低于表1的水平。