The significance of control construction costs manages on entire

process

First, The necessary of control construction costs manages on entire process Talk about the management and the control on construction costs, that the field we are just accustomed to is thought of is a project advance in final account. Indeed , right away at present system and reality,what the job of that the management and the control on construction costs is advance in final account. Be that in advance, the people who work on final account according that already be ascertaied of the working drawing to calculate project amounts,apply a quota mechanically, the meter mechanically fetching cost, or designing that according to the drawing sheet and construction organization after construction is over as well as the scene construction visa takes notes weaves the final account being completed. This is necessary , useful no doubt. But we must see that when pre-final accounts personnel weave working drawing budget or the final account being completed, the construction plan and the

design paper already determined. But construction being to take according to picture as principle, so then in advance, job done by final account personnel is only the change secretly scheming against cost produced by design alteration and prevents upvaluation from calculating boldly. But suppose the project is unreasonable on economy, there is a fault in decision-making; suppose designing a scheme feasible or be not optimum on the technology; the final account personnel can do nothing for sb then in advance. Job of final account personnel does accounts in advance only under just saying system currently in effect, after the event , can only reflect already complete project amounts inactively , can only reflect design and be under construction passively. This evidently is single-faceted , insufficient , we must carry out the entire proceeding supervisory control on the construction costs of building a project.

Concrete conditions of union our country, cost of construction manages have problems as follows:

1、Be not enough to take investment decision into the stage of construction costs seriously charge indeed.

Investment decision is to produce the construction costs headstream, This one stage blow the expense at take up the total investment forehead about 0.5%~3%,but that can have an effect to raise the project benefit of investment. That the project carries out rational choice on construction is that resource carries out direct , the most important optimization deploy means on economy , project benefit of investment affects efficiency and beneficial result to entire national economy. The developed country charges attach importance to control on investment decision stage construction costs,and costs not stinting big capital of money making the studies on the stage of carrying out investment decision energetically, make relatively comparatively accurate construction costs , go along the control

For a long time, there is the grave phenomenon investing in swelling in engineering construction of our country,bring the limit for a project feeling longer and longer, construction costs is higher and higher. The cause of that is short of the effective basis of the building of earlier stage ascertaining construction costs, only basis the already completed according to the expert , decision-makers draw lessons to estimate the project construction costs. Because a lot of factor effects, the“three surpass " phenomenon very common, there are main cause as follows:

(1) personal factor brings about rough estimate lessening

(2) equipment composes in reply material price's not working out according to market quotations.

(3) construction units bring forward the too high for exceeding a design criterion 2、The design stage of construction costs is not under the control of strict

The design stage is the faucet in that project construction costs controls. After the investment decision is be made rationally , that is the process of plan the technology and organic together economly . Effective control the cost of construction requires strictly and all-round in the enginee designing . Engineering design of current our country also puts move bidding system , fair competition into practice , cost of construction looks on control engineering effective to design stage as one of the

standard choosing main part being hit by the bid unit , cost of construction carries out the administration controlling on the entire proceeding .Our country major part design that the unit carries out thorough analysis lack on construction project technology and economy , big multiple technologies make light of economy in design but at present , design that the personnel is responsible seemingly only to design project mass , are concerned with the construction costs height not very. Optimize a design plan to such an extent as having no way to pass, the first step designs , the rough estimate gets to the effect controlling general cost of construction's establishment. Mass and depth that engineering design pursues etc. is also insufficient , amounts project mistakes in amounts project detailed lists calculates , misses and not calculating, can't arouse increasing by estimating a project momentary, the mass making a tender work is difficult to ensure that , have no way to have an effect to control construction costs as

a result also.

3、Has not adopt the amounts project detailed list quoted price way being applied or used universally on the international all round

Adopt the amounts project detailed list quoted price way being put into use commonly on the international , is that our country construction costs system reforms and cause the inevitable trend reforming to bid system in invitation to bid tender.

One of important act carrying out project public bidding system being to build socialist market economy and to perfect construction market operating mechanism in construction field. After the construction project tender is carried out all round in our country, the effect is obvious in the respect of shortening the mass building a time limit for a project , ensuring a project , reducing construction costs , boycotting an unhealthy tendency. Have ensured the invitation to bid people and bidder's lawful rights and interests also effectively. With the socialist market economy uninterrupted growth,the original tender stage puts the budget quota valuation pattern into practice already doing not adapting , adopt the amounts project detailed list quoted price way being put into use commonly on the international to carry out a tender is an inevitable trend. Ministry of Construction has issued amounts project detailed list valuation method , amounts project detailed list valuation has been in construction project tender job , person has provided project quantity from invitation to bid according to national unification project amounts calculation regulation , quoted price, and classics have judged the reason bidder autonomously trying the at a low price middle bid construction costs valuation pattern.

That carrying out amounts project detailed list valuation method is one important measure of item of construction costs deepen the reform, is standard tender behavior effective measure. This method is beneficial to changing over taking that "amounts" ", "price" are "quota-consuming" as dominant static state managing a pattern , make project amounts in detailed list not enter competition, competition being confined to price only; Beneficial to rightness appraises enterprise strength; Project mass beneficial to ensuring that, reduces construction costs; May cut down the physical labour complicated and overloaded repeating the amounts calculating a project; Facilitate the tender quoted price job; Argue with the dispute back and forth in cutting down project settlement; Receive a track step by step with the convention "controlling

amounts , guiding price , competing for a fee's on" the international, deepen the reformation that project valuation manages mainly according to the marketplace changes development, taking one's place on the international market for our country contracts business creates condition.

4、The stage being under construction controls lack to construction costs

Want to have strict control design alteration too in the stage being under construction. Guard the pass though that working drawing appears in joint trial or are able to have all sorts of problems, but call for to design a branch in the process of construction hard to avoid is strict out of the construction works complexity, the situation changing after avoiding doing first, is also that the weight avoiding break a rough estimate , effective control engineering of construction costs cost of construction plays with a link. At the same time, the sharpening contract manages , ensures equality and mutual benefit issuing contract of method and contracting method.

5、The construction costs being completed settling a stage's controls a project inefficiently

That the final account being completed is that entire construction costs is under the control of the most important one is encircled by construction works. How the final account being completed can reflect actual entire project cost of construction honestly , have also reflected the ability issuing contract of method and contracting method to construction costs administration , have finished handling a project in time the final account being completed must collect , arrange settling a data , pursuing , designing the certificate material changing notice , various warning including that the project is completed and so on being completed. These data collecting must pay attention to whose validity with obtaining evidence, specimen seal impression having designing personnel's signature and being related to if the design alteration advice note must be made known to lower levels by plain design organ. Scene inspection and control visa must label seal and the ratification going on a punitive expedition to such that designing a personnel etc. having construction site person in charge of first party. Great majority our country construction projects are completed in the project being under construction when the final account, during the period of the final account being completed contracting method , are are under construction contracting method calculating commonly much in the book being completed winding up an account , are issue contract of haggie just inexhaustible in devices and schemes , are dispute over trifles phenomenon is grave , project settlement drags repeatedly , some confirmation having drug once and , greatly, affecting engineering construction project sigmatism and building construction costs.

A construction project includes the following procedure from brewing , planning , designing that to establishing completion and commissioning: Be that the project letter of advice stage , feasibility appraise the stage , design stage , the stage being under construction , acceptance check stage and the queen being completed estimate that.Correspondingly, the construction costs ascertaining that and the project construction phase job look at and appraise the stage adapting to , several being allotted in general for the following: The investment studying stage establishment in

the project letter of advice and feasibility is estimated, design stage establishment designs a rough estimate in the first step, budget designing that the stage weaves working drawing in working drawing, budget builds ampere of construction costs face to face with working drawing for basis tender project engineering contract, price is also that the form ascertains that with the business contract; Project amounts putting stage into practice being going to be completed according to contracting reality in project, takes contract price as basis , considers cost of construction rise aroused by inflation of prices at the same time , considers the project and cost being difficult to estimate that to designing middle but happening in putting stage reality into practice , the example is ascertained estimating price; All-in cost costing in the reality being completed checking and accepting a stage , assembling into engineering construction process middle all round, weaves the final account being completed , embodies the actual cost of construction that a construction project according to the facts.

"Four guess that two-valence "is interrelated , the former restricts the latter , the latter supplements the former.

What is called, build the construction costs administration and control, it is the occurrence contracting the stage and construction in the investment decision stage , design stage , construction project putting stage into practice with construction construction costs to control within the cost of construction quota O. K. , correcting the deviation happening at any time, to ensure that the project manages the target realization , get fairly good benefit of investment and social benefits in an attempt being able to use manpower and material resources, financial resources rationally in building a project one by one.

Second, the importance of the investment decision-making stage of project cost control

Construction projects in the investment decision-making stage, the project of the techno-economic decision-making, as well as the cost of construction projects completed and put into production after the project cost-effective, have a decisive impact on the construction project cost control is an important stage. Project cost management as a decision-making stage in the feasibility study report shall be prepared, and economic evaluation of the proposed project, select the technically feasible and economically the construction of example programs and to optimize the construction program on the basis of the preparation of high-quality items investment is estimated that the project construction so that the real control of the project has played the role of total investment.

The impact of the decision-making phase of the project cost are the main factors: a, the determine level of construction standards; b, the choice of built-up areas; c, building location (site) selection; d, project the economic scale; e, technology selection f, equipment selection .

Such as the choice of built-up areas, there is a basic principle, that is close to raw materials, fuel and consumer principles. This project completed and put into production, you can avoid the raw materials, fuels, and finished the long-haul transport, reduce costs, lower costs; transportation distance may be shortened to reduce the flow of time, speed up cash flow and is conducive to business. If the

project's economic size, economies of scale, product standard is a reasonable means of production volume, a number of products under certain conditions, was "increasing returns" of economic phenomena, that is, with the expansion of production volume, unit cost reduction, revenue increase.

Therefore, in order to phase in the investment decision-making control over project cost effective, we must do a good job in the following areas:

(1) the implementation of construction project legal person responsibility system, the construction project from planning to implementation of the whole process of the use of funds and repayment responsibilities to people and projects at the same time establish a system of matching corporate oversight mechanisms, by the competent authorities and supervision of the industry sector establishment of a monitoring group to oversee the use of project funds.

(2) to conduct market analysis and seeking truth from facts, to avoid the blindness of the project decision-making, reduce risk and lower investment, give full consideration to construction projects in the future competitiveness of the market so that more scientific book design and reliability

(3) Capital financial capital must be committed to a formal document, investment funds must be put in place the parties, there must be a funding document to ensure that projects are implemented on schedule after approval. Conditions of the loans should be carefully analyzed and compared to minimize the interest burden and repayment pressure.

(4) Strengthening of engineering geology, hydrogeology, as well as land, water, electricity, transport, environmental protection projects such as the work of the depth of the external conditions, so that there is sufficient basis to estimate the investment. At the same time, extensive research should be to compare similar projects, a serious functional analysis, comparison and choice of multi-program, a full-scale technical feasibility studies and economic evaluation, the finalization of technologically advanced, reliable, economical and rational project construction program in order to estimate more accurate and realistic estimate of the amount of investment in order to make the project cost from the start position in a more reasonable level.

Third, the design phase of the importance of project cost control

Make investment decisions in the project, the project cost control is the key to the design. Design is in the technical and economic implementation of the proposed project to conduct a comprehensive arrangement, is also planning the construction process. Technologically advanced, economical and rational design can reduce the project construction period, savings investment, to improve efficiency. According to expert analysis, design fee generally equal to the construction of the project life-cycle cost of less than 1%, which costs less than 1% of project cost accounts for the impact of degrees above 75%. Because of the general construction projects, selection of materials and equipment accounted for more than 50% of the cost of the project, and in the design phase of architectural forms, structural type, the selection of equipment and materials have been identified in the construction of post-implementation phase, the impact of the project cost a small (10 % or less). This shows that the design quality is crucial to the entire project

The same construction project, the same single unit of work can have different programs, which have different costs, it is therefore necessary to meet the function under the premise of doing a number of options, through technical comparison, economic analysis and efficiency evaluation, selection of technology selection into the application of economic and rational design, that is, the process of design optimization. Often used to optimize the design of the program, also known as the value of value engineering analysis, that is, as far as possible in meeting the functionality or improve the function of the premise, as far as possible to reduce costs.

Occurred in the cost of all parts of the application of value engineering, construction investment will require a lot of people, financial, and material, and thus the value of engineering construction works great. For a rather mature and effective management methods, value engineering in a number of works have been widely used in construction.

In the engineering design phase correctly handle the technical and economic relationship between the unity of opposites, we can control the key to investment, design and cost management must work closely with staff to make a lot of the technical and economic comparison, in the reduction and control of project efforts, engineering Cost management in the design process should be timely investment analysis on the comparison, the cost of information feedback and dynamic impact on the design, in order to ensure effective control over investment.

At the design stage to project cost control should focus on the following aspects.

(1) to promote the design and the design of the bidding campaign optimization design approach

The assessment team of experts using scientific methods, in accordance with applicable, economic, aesthetic principles, as well as technologically advanced, well-structured to meet the building energy saving and environmental requirements, a comprehensive assessment of the merits of design, selection of the best in determining the successful program. Estimates of selected investment program in general to be close to the scope of construction projects. The design of these two methods both contract design choice and competition, to ensure selection of the design of technologically advanced, innovative and unique, adaptable, and help control project cost. Design units should strive to improve their own quality, clever engineering design ideas, great care, in order to reduce the project cost more than their brains in order to improve design quality, and strive to put at the design stage in the approval of project cost control within the investment limits.

(2) actively pursuing the design limit

The so-called cap design, is in accordance with the approved design of the book and investment is estimated that in the guarantee under the premise of the functional requirements. Preliminary design and budget control, in accordance with the approved budget for the preliminary design and total control of the construction design. Through the ceiling design, every professional, every designer has a target investment limit. During the design process, designers should be more into the program to compare and optimize the design, Not only to ensure that technically advanced and reasonable design, innovative aesthetics, but also the investment limit is not exceeded

the target in order to put an end to the design of the project to raise the factor of safety and design standards, or only consider the feasibility of technical solutions, rather than the phenomenon of economic rationality to ensure effective cost control.

(3) the implementation of the design of reward and punishment system

In order to limit the design of the implementation into practice, the limit should be set up and sound system designed to reward and punishment. To limit the design is done well, cost savings and control of investment there is the effectiveness of the project legal person should be given appropriate incentives and design units. Design to limit the development of the internal design of assessment and incentive methods to limit attention to the design, made to save investment and effective cost control offices and the significant achievements of individuals, should be rewarding. Do not attach importance to limit the design, do not take measures to save the investment, resulting in more than a design limit investment offices and individuals should be given to economic penalties. Do reward and encourage designers to design deep potential economic importance to design the control of a reasonable project cost will be a major breakthrough.

Fourth、the cost control of the implementation phase of construction project

1, the bidding process stage

The implementation of construction project bidding is effective means of construction projects to control the implementation phase of the project cost. If we want To do a good job for bidding, the first we should make sure that qualification is clearance, and resolutely put an end to bribery, such as all the Phenomenon about destruction of all bidding discipline; Secondly, we should strengthen the bid management, to ensure the accuracy and confidentiality of bid preparation; Third, make sure the method of Evaluation and Calibration are Scientific .when select the successful projects as a standard we should concern about the reasonable, short period, reputable companies, construction considerations such as experience. when we evaluation, the first is technical standard assessment, the follow is business assessment,this can ensure open, fair and just.

2, the construction phase

In the construction phase construction ,the goles based on project budget or contract price of Civil works and installation works and project cost control of Civil works and installation works. At this stage the scope for savings has been small, but it is likely to lead to waste,this make us give them adequate attention for the control of project cost.

(1) strengthen the technical and economic comparison of construction program

Construction is an important work of the design of constructing orgnization. Reasonable constructing program can shorten the period of constructing, ensure the quality of the project and enhance economic efficiency. Comparing and analysing the constructing program from technical and economic view and comparing the three techno-economic index of the quality, duration and cost through qualitative analysis and quantitative analysis can take good use of manpower, material and financial resources, achieving better economic benefits. Consequently, good construction management is an important way of all-round cost management.

(2) a sound system design change Examination and approval system

If design subject need to be change, we should take action as far as possible in advance, because the sooner the change, the smaller loss; Second, before each design ofchanges we must analysis the quality of project and cost, and this should receive the consent of the original design. If it breakthrough the total project cost estimates after the change, this must be approved by the review of the relevant departments, we should prevent these things happened such as increasing design elements ,improving the design standards, increasing the project cost.

(3) check strictly with visa procedures of the project site we should Construct project management system , establish the specialized departments,and through the use of specialized management of professionals for the project, to avoid the phenomenon that project management staff just care visa only, take no concern about the economic accounts, resulting the serious consequences such as investment is out of control.

For Seriously changes of visa procedures we should make the building side, supervision side, the construction site together representatives signed a manner to ensure that the authenticity of the visa, the rationality of the economy of changes and to avoid the disputes caused by the phenomenon of fraud.

(4) do a good job in the completion of the audit settlement price

Clearing refers to the completion of construction enterprises in accordance with the terms of the contract completed by the contractor within the engineering, land quality experience, and in accordance with the contract, the construction units to carry out the final project settlement price. Completion of the project audited settlement is approved in accordance with the construction of the project cost. Therefore, the completion of settlement of the audit is a very important work, should focus on the following:

① check the accuracy of the project quantity.the check of project Quantity is the most important and most complicated, the most detailed work in process of the settle of completed project, this must be based on completion of the project plan, changed design and construction of the scene .it strictly in accordance with the provisions of the rules one by one in terms of project review to prevent the units of construction to increase the volume of inflated project cost in the settlement on completion of the project.

② examine whether the additional apply is right . check the sub-projects listed in the price in line with the fixed unit price, check whether the name, specification, measurement units and the content consistent with the units of the valuation table; for the unit price of conversion, the first step is to check if the conversion price was fixed allowed, followed check if the conversion price is correct.

③ check if the standards for the admission fee In line with the cost of the fixed and the cost of policies and regulations of the project during the construction.

Fifth, the thinking and outlook of project cost management system From a long time, we generally ignore the the project cost control of preparatory work for the construction phase, and control projects often focus on the cost of the construction phase - the budget review working drawings and reasonable settlement

price Civil project and installation project,little count, although there do , but, after all, is "never too late to mend", achieve very little.

In order to control construction costs effectively, it is necessary for us to shifted the focus of control to the early stages, the first thing we shoulf do is that to attach importance to this and strengthen the work of estimated investment of decision-making phase of the project. in an effort to increase the accuracy of control count of the investment feasibility study. to effectively play its the role of control the construction of the total project cost.

Secondly, we should know that the budget estimates must be clear not only to reflect the design, calculation of project cost, but also can affect the dynamic design, optimal design and play the role of control project cost, and promote the role of the rational use of construction funds.

At the same time,we should to take design estimates of invest estimates in the project cost, and working drawings budget, contract price, settlement price, the completion of final accounts (four counting the two prices) to implement the integrated management of change the situation of " the pipe section of the railway police," and this the needs of the industry by deepening structural reforms, through the operation of market price-setting mechanism, we can get a project cost management system with the formation of a unified, coordinated and orderly system, to achieve the goles of rational use of investment, to control costs effectively, achieve the best return on investment in the end, and to gradually establish a project cost management system .this system can adapt the socialist market economic system, and also adopt the situation that China's national conditions in line with international practice.

土木工程类专业英文文献及翻译

PA VEMENT PROBLEMS CAUSED BY COLLAPSIBLE SUBGRADES By Sandra L. Houston,1 Associate Member, ASCE (Reviewed by the Highway Division) ABSTRACT: Problem subgrade materials consisting of collapsible soils are com- mon in arid environments, which have climatic conditions and depositional and weathering processes favorable to their formation. Included herein is a discussion of predictive techniques that use commonly available laboratory equipment and testing methods for obtaining reliable estimates of the volume change for these problem soils. A method for predicting relevant stresses and corresponding collapse strains for typical pavement subgrades is presented. Relatively simple methods of evaluating potential volume change, based on results of familiar laboratory tests, are used. INTRODUCTION When a soil is given free access to water, it may decrease in volume, increase in volume, or do nothing. A soil that increases in volume is called a swelling or expansive soil, and a soil that decreases in volume is called a collapsible soil. The amount of volume change that occurs depends on the soil type and structure, the initial soil density, the imposed stress state, and the degree and extent of wetting. Subgrade materials comprised of soils that change volume upon wetting have caused distress to highways since the be- ginning of the professional practice and have cost many millions of dollars in roadway repairs. The prediction of the volume changes that may occur in the field is the first step in making an economic decision for dealing with these problem subgrade materials. Each project will have different design considerations, economic con- straints, and risk factors that will have to be taken into account. However, with a reliable method for making volume change predictions, the best design relative to the subgrade soils becomes a matter of economic comparison, and a much more rational design approach may be made. For example, typical techniques for dealing with expansive clays include: (1) In situ treatments with substances such as lime, cement, or fly-ash; (2) seepage barriers and/ or drainage systems; or (3) a computing of the serviceability loss and a mod- ification of the design to "accept" the anticipated expansion. In order to make the most economical decision, the amount of volume change (especially non- uniform volume change) must be accurately estimated, and the degree of road roughness evaluated from these data. Similarly, alternative design techniques are available for any roadway problem. The emphasis here will be placed on presenting economical and simple methods for: (1) Determining whether the subgrade materials are collapsible; and (2) estimating the amount of volume change that is likely to occur in the 'Asst. Prof., Ctr. for Advanced Res. in Transp., Arizona State Univ., Tempe, AZ 85287. Note. Discussion open until April 1, 1989. To extend the closing date one month,

中英文参考文献格式

中文参考文献格式 参考文献(即引文出处)的类型以单字母方式标识: M——专著,C——论文集,N——报纸文章,J——期刊文章,D——学位论文,R——报告,S——标准,P——专利;对于不属于上述的文献类型,采用字母“Z”标识。 参考文献一律置于文末。其格式为: (一)专著 示例 [1] 张志建.严复思想研究[M]. 桂林:广西师范大学出版社,1989. [2] 马克思恩格斯全集:第1卷[M]. 北京:人民出版社,1956. [3] [英]蔼理士.性心理学[M]. 潘光旦译注.北京:商务印书馆,1997. (二)论文集 示例 [1] 伍蠡甫.西方文论选[C]. 上海:上海译文出版社,1979. [2] 别林斯基.论俄国中篇小说和果戈里君的中篇小说[A]. 伍蠡甫.西方文论选:下册[C]. 上海:上海译文出版社,1979. 凡引专著的页码,加圆括号置于文中序号之后。 (三)报纸文章 示例 [1] 李大伦.经济全球化的重要性[N]. 光明日报,1998-12-27,(3) (四)期刊文章 示例 [1] 郭英德.元明文学史观散论[J]. 北京师范大学学报(社会科学版),1995(3). (五)学位论文 示例 [1] 刘伟.汉字不同视觉识别方式的理论和实证研究[D]. 北京:北京师范大学心理系,1998. (六)报告 示例 [1] 白秀水,刘敢,任保平. 西安金融、人才、技术三大要素市场培育与发展研究[R]. 西安:陕西师范大学西北经济发展研究中心,1998. (七)、对论文正文中某一特定内容的进一步解释或补充说明性的注释,置于本页地脚,前面用圈码标识。 参考文献的类型 根据GB3469-83《文献类型与文献载体代码》规定,以单字母标识: M——专著(含古籍中的史、志论著) C——论文集 N——报纸文章 J——期刊文章 D——学位论文 R——研究报告 S——标准 P——专利 A——专著、论文集中的析出文献 Z——其他未说明的文献类型 电子文献类型以双字母作为标识: DB——数据库 CP——计算机程序 EB——电子公告

土木工程岩土类毕业设计外文翻译

姓名: 学号: 10447425 X X 大学 毕业设计(论文)外文翻译 (2014届) 外文题目Developments in excavation bracing systems 译文题目开挖工程支撑体系的发展 外文出处Tunnelling and Underground Space Technology 31 (2012) 107–116 学生XXX 学院XXXX 专业班级XXXXX 校内指导教师XXX 专业技术职务XXXXX 校外指导老师专业技术职务 二○一三年十二月

开挖工程支撑体系的发展 1.引言 几乎所有土木工程建设项目(如建筑物,道路,隧道,桥梁,污水处理厂,管道,下水道)都涉及泥土挖掘的一些工程量。往往由于由相邻的结构,特性线,或使用权空间的限制,必须要一个土地固定系统,以允许土壤被挖掘到所需的深度。历史上,许多挖掘支撑系统已经开发出来。其中,现在比较常见的几种方法是:板桩,钻孔桩墙,泥浆墙。 土地固定系统的选择是由技术性能要求和施工可行性(例如手段,方法)决定的,包括执行的可靠性,而成本考虑了这些之后,其他问题也得到解决。通常环境后果(用于处理废泥浆和钻井液如监管要求)也非常被关注(邱阳、1998)。 土地固定系统通常是建设项目的较大的一个组成部分。如果不能按时完成项目,将极大地影响总成本。通常首先建造支撑,在许多情况下,临时支撑系统是用于支持在挖掘以允许进行不断施工,直到永久系统被构造。临时系统可以被去除或留在原处。 打桩时,因撞击或振动它们可能会被赶入到位。在一般情况下,振动是最昂贵的方法,但只适合于松散颗粒材料,土壤中具有较高电阻(例如,通过鹅卵石)的不能使用。采用打入桩系统通常是中间的成本和适合于软沉积物(包括粘性和非粘性),只要该矿床是免费的鹅卵石或更大的岩石。 通常,垂直元素(例如桩)的前安装挖掘工程和水平元件(如内部支撑或绑回)被安装为挖掘工程的进行下去,从而限制了跨距长度,以便减少在垂直开发弯矩元素。在填充情况下,桩可先设置,从在斜坡的底部其嵌入悬挑起来,安装作为填充进步水平元素(如搭背或土钉)。如果滞后是用来保持垂直元素之间的土壤中,它被安装为挖掘工程的进行下去,或之前以填补位置。 吉尔- 马丁等人(2010)提供了一个数值计算程序,以获取圆形桩承受轴向载荷和统一标志(如悬臂桩)的单轴弯矩的最佳纵筋。他们开发的两种优化流程:用一个或两个直径为纵向钢筋。优化增强模式允许大量减少的设计要求钢筋的用量,这些减少纵向钢筋可达到50%相对传统的,均匀分布的加固方案。 加固桩集中纵向钢筋最佳的位置在受拉区。除了节约钢筋,所述非对称加强钢筋图案提高抗弯刚度,通过增加转动惯量的转化部分的时刻。这种增加的刚性可能会在一段时间内增加的变形与蠕变相关的费用。评估相对于传统的非对称加强桩的优点,对称,钢筋桩被服务的条件下全面测试来完成的,这种试验是为了验证结构的可行性和取得的变形的原位测量。 基于现场试验中,用于优化的加强图案的优点浇铸钻出孔(CIDH)在巴塞罗那的

中英文论文参考文献标准格式 超详细

超详细中英文论文参考文献标准格式 1、参考文献和注释。按论文中所引用文献或注释编号的顺序列在论文正文之后,参考文献之前。图表或数据必须注明来源和出处。 (参考文献是期刊时,书写格式为: [编号]、作者、文章题目、期刊名(外文可缩写)、年份、卷号、期数、页码。参考文献是图书时,书写格式为: [编号]、作者、书名、出版单位、年份、版次、页码。) 2、附录。包括放在正文内过份冗长的公式推导,以备他人阅读方便所需的辅助性数学工具、重复性数据图表、论文使用的符号意义、单位缩写、程序全文及有关说明等。 参考文献(即引文出处)的类型以单字母方式标识,具体如下: [M]--专著,著作 [C]--论文集(一般指会议发表的论文续集,及一些专题论文集,如《***大学研究生学术论文集》[N]-- 报纸文章 [J]--期刊文章:发表在期刊上的论文,尽管有时我们看到的是从网上下载的(如知网),但它也是发表在期刊上的,你看到的电子期刊仅是其电子版 [D]--学位论文:不区分硕士还是博士论文 [R]--报告:一般在标题中会有"关于****的报告"字样 [S]-- 标准 [P]--专利 [A]--文章:很少用,主要是不属于以上类型的文章 [Z]--对于不属于上述的文献类型,可用字母"Z"标识,但这种情况非常少见 常用的电子文献及载体类型标识: [DB/OL] --联机网上数据(database online) [DB/MT] --磁带数据库(database on magnetic tape) [M/CD] --光盘图书(monograph on CDROM) [CP/DK] --磁盘软件(computer program on disk) [J/OL] --网上期刊(serial online) [EB/OL] --网上电子公告(electronic bulletin board online) 很显然,标识的就是该资源的英文缩写,/前面表示类型,/后面表示资源的载体,如OL表示在线资源 二、参考文献的格式及举例 1.期刊类 【格式】[序号]作者.篇名[J].刊名,出版年份,卷号(期号)起止页码. 【举例】 [1] 周融,任志国,杨尚雷,厉星星.对新形势下毕业设计管理工作的思考与实践[J].电气电子教学学报,2003(6):107-109. [2] 夏鲁惠.高等学校毕业设计(论文)教学情况调研报告[J].高等理科教育,2004(1):46-52. [3] Heider, E.R.& D.C.Oliver. The structure of color space in naming and memory of two languages [J]. Foreign Language Teaching and Research, 1999, (3): 62 67. 2.专著类

土木工程专业外文文献及翻译

( 二 〇 一 二 年 六 月 外文文献及翻译 题 目: About Buiding on the Structure Design 学生姓名: 学 院:土木工程学院 系 别:建筑工程系 专 业:土木工程(建筑工程方向) 班 级:土木08-4班 指导教师:

英文原文: Building construction concrete crack of prevention and processing Abstract The crack problem of concrete is a widespread existence but again difficult in solve of engineering actual problem, this text carried on a study analysis to a little bit familiar crack problem in the concrete engineering, and aim at concrete the circumstance put forward some prevention, processing measure. Keyword:Concrete crack prevention processing Foreword Concrete's ising 1 kind is anticipate by the freestone bone, cement, water and other mixture but formation of the in addition material of quality brittleness not and all material.Because the concrete construction transform with oneself, control etc. a series problem, harden model of in the concrete existence numerous tiny hole, spirit cave and tiny crack, is exactly because these beginning start blemish of existence just make the concrete present one some not and all the characteristic of quality.The tiny crack is a kind of harmless crack and accept concrete heavy, defend Shen and a little bit other use function not a creation to endanger.But after the concrete be subjected to lotus carry, difference in temperature etc. function, tiny crack would continuously of expand with connect, end formation we can see without the

中英文参考文献格式

中英文参考文献格式! (細節也很重要啊。。)来源:李菲玥的日志 规范的参考文献格式 一、参考文献的类型 参考文献(即引文出处)的类型以单字母方式标识,具体如下: M——专著C——论文集N——报纸文章J——期刊文章 D——学位论文R——报告S——标准P——专利 A——文章 对于不属于上述的文献类型,采用字母“Z”标识。 常用的电子文献及载体类型标识: [DB/OL]——联机网上数据(database online) [DB/MT]——磁带数据库(database on magnetic tape) [M/CD]——光盘图书(monograph on CD ROM) [CP/DK]——磁盘软件(computer program on disk) [J/OL]——网上期刊(serial online) [EB/OL]——网上电子公告(electronic bulletin board online) 对于英文参考文献,还应注意以下两点: ①作者姓名采用“姓在前名在后”原则,具体格式是:姓,名字的首字母. 如:Malcolm R ichard Cowley 应为:Cowley, M.R.,如果有两位作者,第一位作者方式不变,&之后第二位作者名字的首字母放在前面,姓放在后面,如:Frank Norris 与Irving Gordon应为:Norri s, F. & I.Gordon.; ②书名、报刊名使用斜体字,如:Mastering English Literature,English Weekly。二、参考文献的格式及举例 1.期刊类 【格式】[序号]作者.篇名[J].刊名,出版年份,卷号(期号):起止页码. 【举例】 [1] 周融,任志国,杨尚雷,厉星星.对新形势下毕业设计管理工作的思考与实践[J].电气电子教学学报,2003(6):107-109.

英语毕业论文引用和参考文献格式

英语毕业论文引用和参考文献格式 英语专业毕业论文引用和参考文献格式采用APA格式及规。 一、文中夹注格式 英语学位论文引用别人的观点、方法、言论必须注明出处,注明出处时使用括号夹注的方法(一般不使用脚注或者尾注),且一般应在正文后面的参考文献中列出。关于夹注,采用APA格式。 (一)引用整篇文献的观点 引用整篇文献(即全书或全文)观点时有两种情况: 1.作者的姓氏在正文中没有出现,如: Charlotte and Emily Bronte were polar opposites, not only in their personalities but in their sources of inspiration for writing (Taylor, 1990). 2. 作者的姓氏已在正文同一句中出现,如: Taylor claims that Charlotte and Emily Bronte were polar opposites, not only in their personalities but in their sources of inspiration for writing (1990). 3. 如果作者的姓氏和文献出版年份均已在正文同一句中出现,按APA的规不需使用括号夹注,如: In a 1990 article, Taylor claims that Charlotte and Emily Bronte were polar opposites, not only in their personalities but in their sources of inspiration for writing. 4. 在英文撰写的论文中引用中文著作或者期刊,括号夹注中只需用汉语拼音标明作者的姓氏,不得使用汉字,如:(Zhang, 2005) (二)引用文献中具体观点或文字 引用文献中某一具体观点或文字时必须注明该观点或者该段文字出现的页码出版年份,没有页码是文献引用不规的表现。 1.引用一位作者的文献 (1)引用容在一页,如: Emily Bronte “expressed increasing hostility for the world of human relationships, whether sexual or social” (Taylor, 1988:11). (2)引用容在多页上,如: Newmark (1988:39-40) notes three characteristically expressive text-types: (a) serious imaginative literature (e.g. lyrical poetry); (b) authoritative statements (political speeches and documents, statutes and legal documents, philosophical and academic works by acknowledged authorities); (c) autobiography, essays, personal correspondence (when these are personal effusions).

土木工程毕业设计外文翻译最终中英文

7 Rigid-Frame Structures A rigid-frame high-rise structure typically comprises parallel or orthogonally arranged bents consisting of columns and girders with moment resistant joints. Resistance to horizontal loading is provided by the bending resistance of the columns, girders, and joints. The continuity of the frame also contributes to resisting gravity loading, by reducing the moments in the girders. The advantages of a rigid frame are the simplicity and convenience of its rectangular form.Its unobstructed arrangement, clear of bracing members and structural walls, allows freedom internally for the layout and externally for the fenestration. Rig id frames are considered economical for buildings of up to' about 25 stories, above which their drift resistance is costly to control. If, however, a rigid frame is combined with shear walls or cores, the resulting structure is very much stiffer so that its height potential may extend up to 50 stories or more. A flat plate structure is very similar to a rigid frame, but with slabs replacing the girders As with a rigid frame, horizontal and vertical loadings are resisted in a flat plate structure by the flexural continuity between the vertical and horizontal components. As highly redundant structures, rigid frames are designed initially on the basis of approximate analyses, after which more rigorous analyses and checks can be made. The procedure may typically inc lude the following stages: 1. Estimation of gravity load forces in girders and columns by approximate method. 2. Preliminary estimate of member sizes based on gravity load forces with arbitrary increase in sizes to allow for horizontal loading. 3. Approximate allocation of horizontal loading to bents and preliminary analysis of member forces in bents. 4. Check on drift and adjustment of member sizes if necessary. 5. Check on strength of members for worst combination of gravity and horizontal loading, and adjustment of member sizes if necessary. 6. Computer analysis of total structure for more accurate check on member strengths and drift, with further adjustment of sizes where required. This stage may include the second-order P-Delta effects of gravity loading on the member forces and drift.. 7. Detailed design of members and connections.

英语优秀论文参考文献格式要求

英语优秀论文参考文献格式要求

————————————————————————————————作者:————————————————————————————————日期:

英语专业本科毕业论文 参考文献格式要求 I.文内引用 (一)直接引用 1.引用中的省略 原始资料的引用:在正文中直接引用时,应给出作者、年份,并用带括号的数字标出页码。若有任何资料省略,使用英文时,应用3个省略号在句中标出(…),中文用6个(……);若两句间的资料省略,英文应用4个省略号标出(‥‥),中文用6个(……)。若要在直接引用插入自己的解释,应使用方括号[ ]。若在资料中有什么错误拼写、错误语法或标点错误会使读者糊涂,应在引用后立即插入[sic],中文用[原文如此]。下面是一些示例: 例一:The DSM IV defines the disorder [dysthymic] as being in a chronically depressed mood that occurs for "most of the day more days than not for at least two years (Criterion A) .... In children, the mood may be irritable rather than depressed, and the required minimum duration is only one year" (APA, 1994, p. 345). 例二:Issac (1995) states that bipolar disorder "is not only uncommon but may be the most diagnostic entity in children and adolescents in similar settings .... and may be the most common diagnosis in adolescents who are court-remanded to such settings" (p.275). 2.大段落引用 当中文引用超过160字时,不使用引号,而使用“块”的形式(引用起于新的一行,首行缩进4个空格,两端对齐,之后每行都缩进)。 当英文引用超过40字时,不使用引号,而使用“块”的形式(引用起于新的一行,首行缩进5个空格,左对齐,之后每行都缩进)。 Elkind (1978) states:

英文引用及参考文献格式要求

英文引用及参考文献格式要求 一、参考文献的类型 参考文献(即引文出处)的类型以单字母方式标识,具体如下: M——专著C——论文集N——报纸文章 J——期刊文章D——学位论文R——报告 对于不属于上述的文献类型,采用字母“Z”标识。 对于英文参考文献,还应注意以下两点: ①作者姓名采用“姓在前名在后”原则,具体格式是:姓,名字的首字母.如:MalcolmRichardCowley应为:Cowley,M.R.,如果有两位作者,第一位作者方式不变,&之后第二位作者名字的首字母放在前面,姓放在后面,如:FrankNorris与IrvingGordon应为:Norris,F.&I.Gordon.; ②书名、报刊名使用斜体字,如:MasteringEnglishLiterature,EnglishWeekly。 二、参考文献的格式及举例 1.期刊类 【格式】[序号]作者.篇名[J].刊名,出版年份,卷号(期号):起止页码. 【举例】 [1]王海粟.浅议会计信息披露模式[J].财政研究,2004,21(1):56-58. [2]夏鲁惠.高等学校毕业论文教学情况调研报告[J].高等理科教育,2004(1):46-52. [3]Heider,E.R.&D.C.Oliver.Thestructureofcolorspaceinnamingandmemo ryoftwolanguages[J].ForeignLanguageTeachingandResearch,1999,(3):62–6 7. 2.专著类 【格式】[序号]作者.书名[M].出版地:出版社,出版年份:起止页码. 【举例】[4]葛家澍,林志军.现代西方财务会计理论[M].厦门:厦门大学出版社,2001:42. [5]Gill,R.MasteringEnglishLiterature[M].London:Macmillan,1985:42-45. 3.报纸类 【格式】[序号]作者.篇名[N].报纸名,出版日期(版次). 【举例】 [6]李大伦.经济全球化的重要性[N].光明日报,1998-12-27(3). [7]French,W.BetweenSilences:AVoicefromChina[N].AtlanticWeekly,198 715(33). 4.论文集 【格式】[序号]作者.篇名[C].出版地:出版者,出版年份:起始页码. 【举例】 [8]伍蠡甫.西方文论选[C].上海:上海译文出版社,1979:12-17. [9]Spivak,G.“CantheSubalternSpeak?”[A].InC.Nelson&L.Grossberg(e ds.).VictoryinLimbo:Imigism[C].Urbana:UniversityofIllinoisPress,1988, pp.271-313.

土木工程毕业设计中英文翻译

附录:中英文翻译 英文部分: LOADS Loads that act on structures are usually classified as dead loads or live loads are fixed in location and constant in magnitude throughout the life of the the self-weight of a structure is the most important part of the structure and the unit weight of the density varies from about 90 to 120 pcf (14 to 19 KN/m)for lightweight concrete,and is about 145 pcf (23 KN/m)for normal calculating the dead load of structural concrete,usually a 5 pcf (1 KN/m)increment is included with the weight of the concrete to account for the presence of the reinforcement. Live loads are loads such as occupancy,snow,wind,or traffic loads,or seismic may be either fully or partially in place,or not present at may also change in location. Althought it is the responsibility of the engineer to calculate dead loads,live loads are usually specified by local,regional,or national codes and sources are the publications of the American National Standards Institute,the American Association of State Highway and Transportation Officials and,for wind loads,the recommendations of the ASCE Task Committee on Wind Forces. Specified live the loads usually include some allowance for overload,and may include measures such as posting of maximum loads will not be is oftern important to distinguish between the

单片机-英文参考文献

Structure and function of the MCS-51series Structure and function of the MCS-51series one-chip computer MCS-51is a name of a piece of one-chip computer series which Intel Company produces.This company introduced8top-grade one-chip computers of MCS-51series in1980after introducing8one-chip computers of MCS-48series in1976.It belong to a lot of kinds this line of one-chip computer the chips have,such as8051,8031,8751, 80C51BH,80C31BH,etc.,their basic composition,basic performance and instruction system are all the same.8051daily representatives-51serial one-chip computers. An one-chip computer system is made up of several following parts:(1)One microprocessor of8(CPU).(2)At slice data memory RAM(128B/256B),it use not depositting not can reading/data that write,such as result not middle of operation, final result and data wanted to show,etc.(3)Procedure memory ROM/EPROM (4KB/8KB),is used to preserve the procedure,some initial data and form in slice. But does not take ROM/EPROM within some one-chip computers,such as8031, 8032,80C,etc..(4)Four8run side by side I/O interface P0four P3,each mouth can use as introduction,may use as exporting too.(5)Two timer/counter,each timer/ counter may set up and count in the way,used to count to the external incident,can set up into a timing way too,and can according to count or result of timing realize the control of the computer.(6)Five cut off cutting off the control system of the source. (7)One all duplexing serial I/O mouth of UART(universal asynchronous receiver/transmitter(UART)),is it realize one-chip computer or one-chip computer and serial communication of computer to use for.(8)Stretch oscillator and clock produce circuit,quartz crystal finely tune electric capacity need outer.Allow oscillation frequency as12megahertas now at most.Every the above-mentioned part was joined through the inside data bus.Among them,CPU is a core of the one-chip computer,it is the control of the computer and command centre,made up of such parts as arithmetic unit and controller,etc..The arithmetic unit can carry on8persons of arithmetic operation and unit ALU of logic operation while including one,the1 storing device temporarilies of8,storing device2temporarily,8's accumulation

土木工程专业设计外文翻译.doc

外文翻译 题目:高层建筑 学院土木建筑工程学院 专业土木工程(建筑工程方向)班级2006级3班 学号 姓名赖俊宇 指导教师梁新彩 二〇一〇年五月19日

Tall Buildings Although there have been many advancements in building construction technology in general, spectacular achievements have been made in the design and construction of ultrahigh-rise buildings. The early development of high-rise buildings began with structural steel framing. Reinforced concrete and stressed-skin tube systems have since been economically and competitively used in a number of structures for both residential and commercial purposes. The high-rise buildings ranging from 50 to 110 stories that are being built all over the United States are the result of innovations and development of new structural systems. Greater height entails increased column and beam sizes to make buildings more rigid so that under wind load they will not sway beyond an acceptable limit. Excessive lateral sway may cause serious recurring damage to partitions, ceilings, and other architectural details. In addition, excessive sway may cause discomfort to the occupants of the building because of their perception of such motion. Structural systems of reinforced concrete, as well as steel, take full advantage of the inherent potential stiffness of the total building and therefore do not require additional stiffening to limit the sway. In a steel structure, for example, the economy can be defined in terms of the total average quantity of steel per square foot of floor area of the building. Curve A in Fig. 1 represents the average unit weight of a conventional frame with increasing numbers of stories. Curve B represents the average steel weight if the frame is protected from all lateral loads. The gap between the upper boundary and the lower boundary represents the premium for height for the traditional column-and-beam frame; Structural engineers have developed structural systems with a view to eliminating this premium. Systems in steel. Tall buildings in steel developed as a result of several types of structural innovations. The innovations have been applied to the construction of both office and apartment buildings. Frames with rigid belt trusses. In order to tie the exterior columns of a frame structure to the interior vertical trusses, a system of rigid belt trusses at mid-height and at the top of the building may be used. A good example of this system is the First Wisconsin Bank Building (1974) in Milwaukee. Framed tube. The maximum efficiency of the total structure of a tall building, for both

相关主题
文本预览
相关文档 最新文档