一、工程概况

本工程为新建城市道路,道路起于会展路,终点至石门路,长518米,宽14米。其中石园路连接隧道长度269.597米,净宽8.2米。道路等级为城市支路,设计速度为20公里/小时。

机动车道沥青面层结构:8cm粗粒式沥青砼AC-25C,4cm细粒式沥青砼AR-AC13。

编写依据:

1、施工合同、监理合同;

2、施工图及相关勘测、设计、变更文件;

3、经各方确认的会议纪要和其他书面记录、函件、传真、数据电文等;

4、《城镇道路工程施工及质量验收规》CJJ1—2008;

5、《沥青路面施工及验收规》标准号:GB50092-96

6、《建设工程监理规》GB50319—2013;

7、《公路沥青路面施工技术规》标准号:JTG F40-2004

8、《公路改性沥青路面施工技术规》(JTJ036-98)

9、监理规划;

10、国家及省市现行的工程建设强制标准及其他相关的法律法规;

11、经过批准的施工组织设计、(专项)施工方案。

二、施工阶段监控要点

1. 路床

(1)路床不得有翻浆、弹簧、起皮、波浪、积水等现象。

(2) 路床用20吨压路机碾压后,至表面无明显轮迹为止。

(3) 石质路床必须嵌缝紧密,不得有坑槽和松石。

(4) 路床的质量控制目标如下表

路床控制目标值

2.级配碎石垫层

(1)级配碎石压碎值不大于30%,材料针片状颗粒含量不大于20%,不应含有风化石、山皮、泥土块、有机等有害物质。

(2)级配碎石需用机械拌合摊铺和碾压,施工配料必须准确,摊铺或拌合必须均匀,并应严格掌握厚度。

(3)在最佳含水量时,用20T以上压路机进行碾压,压实度不得小于96%,压实后应无明显轮迹及推移等现象。

(4)垫层铺筑后应严格限制车辆通行,保护期不受破坏。

3.水泥稳定碎石层

(1)恢复道路中线,直线段每10米设一桩,弯道每5米设一桩,并在路肩外设置指示桩,并在指示桩上标出高程线和把松铺线和压实后的设计标高定在边桩上,签返《施工放线报验单》。

(2)水泥稳定级配碎石需用机械拌和摊铺和碾压。

(3)检查施工单位水泥稳定碎石层配料是否准确,含水量、水泥用量是否符合要求。

(4)水泥稳定碎石基层中所用的水泥掺量为5.5%(4.5%),32.5级普通水泥,硅酸盐水泥均可使用,初凝时间在3小时以上终凝时间在6小时以上,基层压实工作必须在水泥终凝前完成。

(5)水泥稳定碎石基层,碎石最大粒径不应超过5cm,碾压应均匀、密实,用20吨以上压路机碾压压实厚度不超过20cm,应分层铺筑,每层压实厚度不小于10cm,压实遍数不小于6~8遍,至表面无明显轮迹为止。

(6)施工时,最低气温要求5℃以上,压实后必须保湿养生。

(7)水泥稳定碎石基层的施工质量,应符合下表:

4.横向接缝处理

当混合料摊铺结束时,人工将未端混合料弄整齐,紧靠混合料放置两条方木,方木高度与混合料压实厚度相同。在方木的另一侧用碎石回填约3米长,其高度高出方木几厘米,压实时,压路机后轮应超过混合料。第二天接着铺时,取出方木,清除碎石,使横缝垂直对接,

不允许斜接。

5. 养生

在水泥稳定层经压实和压实度检验后,应立即并加强养护,经常保持水泥稳定层表面湿润,养护期不宜小于7天。控制车辆通行,不使基层出现车槽。基层如有损坏应在浇注砼板前采用相同材料修补压实,严禁用松散粒料填补。

6、质量通病的防治:

6.1 水泥稳定层

6.1.1 混合料离析

6.1.1.1 现象:混合料粗细不均,局部骨料或细料比较集中。混合料离析会造成平整度不好和结构强度不均匀等危害。

6.1.1.2 产生原因

a、混合料拌合时含水率控制不好,过干或过湿;

b、混合料搅拌时间不足,粗细料未完全充分拌合均匀;

c、混合料直接用铲车翻拌,拌和质量难保证;

d、混合料未按规定配合比进行拌和或砂石料级配不好。

6.1.1.3 防治对策

a、出厂前发现骨料离析,应采用铲车翻堆混合料拌均后出厂;

b、混合料由于集料级配不好或配合比控制不当而造成离析,则应通过增加细料或粒料进行复拌,以消除离析现象;

c、进入施工现场的混合料发现有离析现象时应在现场路床外拌匀后再摊铺,或者退料。

6.1.2 施工接缝不顺

6.1.2.1 现象:基层表面拼缝不顺直,或在拼缝处有明显高低不平。

6.1.2.2 产生原因

a、先铺的混合料压至边端时,由于推挤的原因,造成“低头”现象,而在拼缝时未作翻松,直接加新料,由于压缩系数不同,使该处升高。

b、先铺的边端部份碾压时未压,后摊铺时部份接下去摊铺,虽松方标高一致,但先铺部份含水量较低,压缩性较小,碾压后形成高带。

c、摊铺机摊铺时,纵向拼缝未搭接好,先铺段边缘的成型密实度较低,后铺段搭接时抛高又未控制好,碾压后形成接缝不顺直,或高或低。

6.1.2.3 防治对策

a、精心组织施工,尽可能地减少施工段和纵向拼缝;

b、在分段碾压时,拼缝一端应预留一部份不压(3—5m)以防止推挤,影响压实,同时又利于拼接;

c、摊铺前,应将拼缝处已压实端先翻松(长度0.5—1m)至松铺厚度,连同未压部份及新铺材料一起整平碾压,使之成为一体;

d、人工摊铺时,尽可能整个路幅摊铺,以消除纵向拼缝。

6.1.3 施工平整度不好

6.1.3.1 现象:压实后表面平整度不好,不符合质量验评标准。

6.1.3.2 产生原因

a、人工摊铺时没有按方格网控制平整度,机铺时不能均匀行驶、连续供料,停机点往往成为不平点;

b、混合料由几家单位供应,故级配区别较大,影响摊铺系数和压实系数,混合料的含水率不均匀,混合料离析,粗细不匀,均对平整度产生不良影响;

c、下卧层不平,混合料摊铺时虽表面平整,但压缩量不均匀,产生高低不平。

6.1.3.3 防治措施

a、非机铺时,在基层两侧及中间设立标高控制桩,纵向每5米设一断面,形成网格;

b、机铺时要保证连续供料,匀速摊铺。用铲车、推土机摊铺时其行驶路线应均匀,不应随意加铺混合料,以防松紧不一;

c、同一产家的料铺在同一段,不要混杂,不同厂家的料摊铺系数应由厂家确定,混合料配合比应确定;

d、下卧层的平整度应达到验收要求;

e、摊铺好以后,应进行摊铺层平整度修整,然后进行碾压。

6.1.4 压实度不足

6.1.4.1 现象:压实度不合格或合格率偏低,开挖样洞可看到骨料松散,不密实。

7.1.4.2 产生原因

a、碾压时,压路机吨位与碾压遍数不够;

船闸房建及室外附属工程安全监理实施细则

富春江船闸扩建改造工程船闸房建及室外附属工程 安全监理实施细贝y 项目监理机构(章): ___________________ 专业监理工程师: _______________________ 总监理工程师: _________________________ 日期:________________________ 内容提要:

专业工程特点 监理工作流程 监理工作要点监理工作方法及措施 一、工程概况 1、项目名称:富春江船闸扩建改造工程船闸房建及室外附属工程施工监理 2、项目地点:上游锚泊服务区及远方调度站管理用房(包括管理用房、传达室)位于浙江省建德市三都镇宋村山村;船闸运行管理和水上交通安全监管用房、船闸现场调度管理用房(包括管理用房、配电房、传达室)和上、下闸首启闭机房(包括上闸首启闭机房、下闸首左侧启闭机房、下闸首右侧启闭机房)位于浙江省桐庐县城南街道湾里村。 3、项目概况: a. 富春江船闸扩建改造工程是在原有船闸下紧接新建船闸一座 W级标准船闸(兼顾1000吨级船舶的过闸要求),船闸尺度为300 米X 23米X 4.5米(闸室长X宽X门槛水深),船闸总长364m。建设上下游引航道,上游引航道长569 米,宽50 米;下游引航道长1047 米,宽90 米。配建船闸配套及附属工程。 b. 原有船闸作为上游引航渠道,并对其进行加固改造。 c. 建设上下游锚泊服务区及远方调度站,助航安全保障设施及其他配套设施等。

项目规模:上游锚泊服务区及远方调度站管理用房(包括管理用房、传达室、室外道路和绿化、水、电)、船闸运行管理和水上交通安全监管用房(包括安全监管用房、室外道路和绿化、水、电)、船闸现场调度管理用房(包括管理用房、配电房、传达室、室外道路和绿化、水、电)和上、下闸首启闭机房(包括上闸首启闭机房、下闸首左侧启闭机房、下闸首右侧启闭机房),总建筑面积8184.9 〃,室外道路面积10290 〃,绿化面积19676讥 建设单位:富春江船闸扩建改造工程建设指挥部 施工单位:浙江奔腾建设工程有限公司 设计单位:浙江省交通规划设计研究院 监理单位:浙江泰宁建设工程咨询有限公司 二、安全监理目标安全管理规定,实现安全施工为三“零”事故(人身重伤害事故为零,设备交通事故为零,火灾爆炸事故为零)。坚决执行以人为本,关爱生命。 遵循国家和浙江地区法律、法规,实现治安管理零事件。 三、安全监理的依据: 1、《建设工程安全生产管理条例》、《建筑工程安全生产监督管理工作导则》和国家、地方有关安全生产、劳动保护、环境保护、消防等法律法规及方针、政策。 2、国家、地方有关建设工程安全生产标准规范及规范性文件。

(桩基工程)监理实施细则

目录 专业工程概况与特点——P1 监理工作的流程——P1 监理工作的控制要点及目标值——P4 (一)、工程质量控制 1、目标 2、控制点设置和控制手段 3、工序质量控制监理要点 4、常见质量问题的预控工作 5、本工程重点部位监理 6、安全生产监理 (二)、工程进度控制 (三)、工程投资控制 监理工作方法与措施——P9

一、本专业工程的概况与特点 本工程地处由于楼层高,工程量大,因此在桩基工程中要认真监理,为了确保工程质量,现制定桩基监理细则。 二、监理工作的流程 施工阶段监理工作流程如下: 1、灌注桩

、 合格 不合格 2、深层搅拌桩 入岩桩 测入岩界面 测入岩深度 钢筋笼验收 下笼旁站 下导管 砼浇注旁站 测砼坍落度,做试块旁站 砼灌注旁站 测孔深 护筒埋设验收 整改 桩就位验收 开钻 非入岩桩 一清后测沉渣 二清测沉渣及泥浆比重

预搅过程监督 提升喷浆搅拌过程的监督制浆的监控 质量验收 三、监理工作的控制要点及目标值 (一)、工程质量控制 1、目标: ①、质量主控项目和一般项目全部达质量验收标准。 ②、承载力达到设计和规范要求。 2、控制点设置和控制手段 控制点目标值控制手段 原材料、外加剂按规范规定审核质保书、见证取样送检桩径±50㎜尺量钻头桩位GB50202-2002表5.1.4 测量护筒、开挖后量桩中心孔深+300㎜测钻杆,用测绳测量钢筋笼主筋间距±10㎜尺量钢筋笼箍筋间距±20㎜尺量沉渣厚度承重桩≤50㎜抗拨桩≤100mm沉渣仪或测绳测量钢筋笼长度+100㎜尺量砼强度设计要求旁站监制试块、取芯送检砼充盈度>1 实测浇灌量、计算桩顶标高+30㎜、-50㎜仪器测量 控制点目标值控制手段 水泥、外掺剂设计要求查合格证、取样送检水泥用量设计要求查看流量计机头提速≤0.5m/min测单位时间上升距离控制点目标值控制手段 桩底标高±200㎜测机头深度

公路工程改造监理实施细则

第一章总则 1.1 工程概况 ######东起江苏省丰县,西至菏泽市东明县,是省际交通的重要通道。大田集至定陶段是丰东线菏泽境内的一部分,现为二级公路,该路段修建时间较早,路面窄且病害严重,已无法满足快速增长的交通运输需求,成为制约丰东线菏泽境内通行的交通瓶颈。因此,该项目改建势在必行,通过加宽路面,改善通行条件,将更好地促进社会经济和交通运输事业的发展,是适应交通量快速增长,完善公路交通网络布局的一项重要工程。 本项目采用二级公路标准,设计速度80km/h,第二驻地办承担第三、四、六合同段的监理任务。其中第三合同段包含K111+850.9~K132+372.5段内的临时工程、路面工程、绿化工程,一般路段路基宽度采用15.0m,路面宽度采用13.5m,定陶县黄店段及德商高速分离立交处路基宽度采用23.5m,路面宽度采用22m,定陶县东王店路基宽度采用16.5m,路面宽度采用15m,定陶城区段路基宽度采用19.5m,路面宽度采用18m;第四合同段包含K144+937.2~K150+668.4段内的临时工程、路面工程,路基宽度采用23.5m,路面宽度采用22.0m;第六合同段为全线交通工程,包含标志、标线、轮廓标、道口标柱和示警桩。 三合同段路面结构层类型为:加宽及新建路面表面层采用细粒式改性沥青混凝土(AC-10),下面层采用中粒式沥青混凝土(AC-16),基层采用水泥稳定碎石,底基层采用二灰土;补强路段基层采用水泥稳定碎石;罩面路段面层采用细粒式改性沥青混凝土(AC-10)。 四合同段路面结构层类型为:加宽及新建路面面层采用中粒式改性沥青混凝土(AC-16),基层采用大粒径透水性沥青混合料(LSPM-25)和水泥稳定碎石,底基层采用二灰土;补强部分面层采用采用中粒式改性沥青混凝土(AC-16

市政道路工程监理实施细则DOC

一、工程概况: 本次工程是对重庆市江北区四条路城市对外连接道路进行路面及其附属设施改造,四条路分别为大川水岸、重庆市救助站对外连接道、鸿恩雅苑对外连接道、长新路。 二、编制依据: 1.《市政道路工程质量检验评定标准》CJJ1-90; 2.《水泥混凝土路面施工及验收规范》GBJ97-87; 3.《公路路面基层施工技术规范》JTJ034-2000; 4.《公路沥青路面施工技术规范》JTJ032-94; 5.《公路工程质量检验评定标准》JTJ071-98; 6.《建设工程监理规范》GB50319-2000; 7.本工程《建设监理规划》; 8.本工程《施工组织设计》; 9.本工程设计图纸及有关技术文件等。 三、主要监理内容 1.道路工程:原混凝土路面、基层拆除,原人行道砖、路缘石、路边石的拆除,土石方挖运、土石方回填、回填碾压、余方弃置、安砌预制混凝土路缘石及路边石、水泥稳定级配碎石基层、混凝土基层、改性沥青混凝土面层、人行道透水砖及盲道砖铺设、交通标示线。 2.挡护工程:土石方开挖,土石方回填,重力式挡墙。 3.管道工程:挖沟槽土石方,土方回填,聚乙烯(HDPE)双壁波纹雨、污水管,混凝土检查井,d300国标II级钢筋混凝土管满包,雨水口。 4.电气工程:强电管沟,强电检查井,电力电缆,路灯,路灯手孔井,接地装置,配电箱等。

五、监理控制要点 1. 准备工作控制要点 熟悉合同文件、设计文件及有关技术资料,组织或协助业主组织图纸会审和设计技术交底; 2. 审查承包人的施工组织设计,提出审查意见,审核、检查进度计划及质量目标控制计划,签返《施工组织设计(方案)报审表》; 3. 审查承包人现场项目管理机构的质量管理体系、技术管理体系和质量保证体系,审核其组织机构、管理制度、人员的资格证和上岗证是否能确保工程项目的施工质量; 4. 检查施工机具进场情况,审查施工机具性能和数量是否满足施工要求,签返《进场设备报验单》; 5. 审查承包人报送的《分包单位资格报审表》和分包单位有关资质资料,符合有关规定后,签返《分包单位资格报审表》; 6. 复核承包人报送的测量放线控制成果,检查控制桩的保护措施,审查专职测量人员的资格及设备检定情况,符合要求后签返《施工测量放线报验单》; 7. 核查承包人各类材料的进场数量、质量(含质保书)及检测报告,签返《工程材料/构配件/设备报审表》; 8. 检查承包人施工准备情况,批复《工程开工报审表》。 六、控制目标 1. 路基工程 1.1 土石方工程: (一)基本要求: 1)清除地表腐植土0.3米并压实,当松土厚度超过0.3米时,应翻挖土后再回

交通设施工程监理细则

监理实施细则 工程名称明珠湾大桥工程 项目总监 铁科院(北京)工程咨询有限公司 广州市诚铁监理咨询有限公司 明珠湾大桥监理联合体总监理工程师办公室 2015年5月

交通设施工程施工监理细则 为加强道路交通设施工程施工管理,提高技术水平,确保工程质量,安全、节约材料,提高经济效益,特制定本施工细则。 1.适用范围 适用于明珠湾大桥工程交通设施工程及城市主干道的公路道路交通设施工程施工。 1、引用文件 (1)、《道路交通标志和标线》国标GB5768—1999;JT/280;GN47—1989;GN48—1989 (2)、广州市地名委员会《中英双语标志和通名译写规范》(3)、《中华人民共和国道路交通安全法》 (4)、《道路交通信号灯》国标GBI4887—2003 (5)、《市政道路工程质量检验评定标准》GJJ1—90 2.道路交通设施工程施工控制 2.1事前控制 (1)、掌握道路沿线的现场地形,地貌、建筑物的实际情况。 (2)、组织人员绘审及熟悉设计图纸。 (3)、审视施工单位的施工组织设计及施工方案。 (4)、校核临时水准点,道路轴线控制桩,高程桩。 (5)、对施工单位的资质、施工管理人员及技术人员的资格,特

殊技术工程上岗证进行审核。 (6)、审定材料和水泥来源、标号、质量、数量及供应计划、材料进场堆放。 2.2事中控制 交通设施工程施工过程中,监理工程师应到现场巡视,并按道路交通设施施工工序分别抽检旁站检验,施工单位在施工的每道工序自检合格后填写“工程报验单”报项目监理部,经监理工程师检查认定和按有关规定做试验合格后,方可进入下一道工序施工。 2.2.1设计目标的主要控点: 一、道路标准路段双向8车道,车道宽度3.5米。 二、标志的支撑方式: 1、悬臂式标志杆(L杆);L杆采用八角型钢管制作,是标牌和信 号灯的支持构件。 2、单立杆主要支持小型标志,因支持牌面大小的不同,单立杆有所 区别,支持1.5平方米以上的单立杆采用直径89mm钢管制作,支持1.5平方米以下的单立杆采用直径76 mm钢管制作. 三、材料的防锈处理:各类交通设施标志的杆件、螺母均应进行热镀锌处理,立杆、杆件等的钻孔、冲孔和车间焊接,应在钢材进行表面防腐处理之前完成。热镀锌干燥后,杆件再喷涂银色的环氧富锌漆3度。为防盗需要螺栓安装完毕应点焊。 四、信号灯:交叉口信号灯按车道功能设置,每组信号灯为红、黄、绿(箭头)三色灯具,附于车道下游的悬臂式或立柱式灯杆上(所有

公路涵洞工程监理实施细则范本

为使本建设项目监理工作制度化、标准化、规范化、程序化,进一步提高工程监管水平,提高投资效益,依据项目施工、监理合同及有关规范、规定特制定本细则,与其它管理办法互为补充,望各参建单位遵照执行。 一、工程概况 二、编制依据 1、监理规划 2、部颁《公路路基施工技术规范》(JTG F10—2006) 3、部颁《公路路面基层施工技术细则》(JTG/T F20—2015) 4、部颁《公路水泥混凝土路面施工技术细则》(JTG/T F30-2014) 5、部颁《公路沥青路面施工技术规范》(JTG F40-2004) 6、部颁《公路工程质量检验评定标准》(JTJ F80/1—2004) 三、路基施工监理控制要点 (一)、路基施工准备阶段的监理 1、测量工作监理要点: (1)、监理工程师向承包人书面提供原始基准点、基准线和基准高程的方位及数据。 (2)、施工单位必须根据设计资料认真搞好导线复测工作,复测采用全站仪或其它满足测量精度的仪器,复测导线时必须和相邻施工段的导线闭合,测量精度应满足规范要求. (3)、原有导线点不能满足施工要求时,应进行加密,保证在道路施工中,相邻导线点间能相互通视。对有碍施工的导线点,施工前应加以固定,固定方法可采用交点法或其它方法. (4)、路基开工前应全面恢复中线并固定路线主要控制桩,如交点、转点、圆曲线及缓和曲线的起讫点等。所有中线桩及主要控制桩必须采用坐标法恢复。 (5)、纵断高程测量要求至少每20米测一点,数据必须闭合,记录清楚完整,无涂改。应整理绘制复测后的纵断面图,并计算填挖高度. (6)、横断面测量要求至少每20米测一横断面,地形变化特殊地段应加测断面,地貌特征做好记录和说明,驻地办抽检频率不少于设计断面的30%同时根据需要增加频率.

危险性较大的分部分项工程监理实施细则

B13市开发区三岔河综合整治工程及附属道路工程 监理实施细则 (危险性较大的分部分项工程) 容提要: 专业工程特点 监理工作流程 监理工作控制目标及控制要点 监理工作方法及措施 项目监理机构(章): 专业监理工程师: 总监理工程师: 日期: 市政设计研究院监理分公司

危险性较大的分部分项工程 监理实施细则 一、编制依据: 1.《中华人民国建筑法》; 2.《中华人民全生产法》; 3.《建设工程安全生产管理条例》; 4.《建设工程质量管理条例》; 5.《危险性较大的分部分项工程安全管理办法》建质【2009】87号文; 《关于印发〈建设工程高大模板支撑系统施工安全监督管理导则〉的通知》建质【2009】6. 254号文; 7.《关于进一步加强建设工程危险性较大分部分项工程安全管理的通知》吴住建规【2010】14号文; 8.国家及省市有关质量、安全管理的法律、法规及规程。 二、细则编制的目的: 为了加强对危险性较大的分部分项工程安全管理,明确安全专项施工方案编制容,规专家论证程序,确保安全专项施工方案实施,积极防和遏制建筑施工生产安全事故的发生。 三、本细则实施的围: 危险性较大的分部分项工程是指建筑工程在施工过程中存在的、可能导致作业人员群死群伤或造成重大不良社会影响的分部分项工程。 针对本工程的特点、周边环境和施工工艺等,其危险性较大的分部分项工程是:1.基坑支护工程、土方开挖工程。

2.模板工程及支撑体系 3.塔吊、货梯、升降机等垂直运输设备,各类桩机,卸料平台。 4.脚手架工程:悬挑脚手架工程; 5. 施工用电 必须经专家论证的危险性较大的分部分项工程是: 基坑支护工程:本工程开挖深度超过4m 四、危险性较大的分部分项工程监理管理制度: 1.监理部严格按照建质【2009】87号文《危险性较大的分部分项工程安全管理办法》实施监理; 2.危险性较大的分部分项工程监理实行总监负责制,总监全权负责危险性较大的分部分项工程的监督管理工作; 3.针对危险性较大的分部分项工程,施工单位必须编制专项方案,企业技术负责人审批后,上报监理单位审核;超过一定规模的危险性较大的分部分项工程,必须按程序由企业相关部门审核、专家进行论证,企业技术负责人审批后、上报监理单位审核,建设单位负责人签字后,方可组织实施; 4.超过一定规模的危险性较大的分部分项工程,需要进行监测监控的,建议委托第三方实施; 5.项目监理部应编制危险性较大的分部分项工程监理实施细则, 6.施工单位在专项方案实施前,由编制人员或项目的技术负责人向现场管理人员和作业人员进行安全技术交底,监理实施见证; 7.施工单位应上报应急预案,监理单位进行见证,并督促施工单位对应急演习预案进行完善和改进;

交通安全设施监理细则

连云港新海至徐圩港区公路建设项目工程 交通安全设施 监理实施细则 编制: 审核: 批准: 江苏东南交通工程咨询监理有限公司 连云港新海至徐圩港区公路建设项目XX-JL总监办 2014年1月1日

目录 一、工程概况 (1) 二、监理工作依据 (2) 三、监理质量控制原则 (2) 四、质量目标分解 (2) 五、施工难点及监理要点 (2) 六、预控要点 (11) 七、适用规范 (12)

连云港新海至徐圩港区公路建设项目工程 交通安全设施监理实施细则 一、工程概况 本项目起点连云港市云台农场,终点为海堤公路,全长约26km。设计为一级公路标准。设计速度为100km/h。 根据道路规划调整,标准路段采用双向4车道。设计内容有:交通标志、交通标线、护栏、防眩设施、轮廓标及里程碑等。 (一)交通标志 标志类型:本项目交通标志主要包括警告、禁令、指示、指路等。 标志结构:全线交通标志主要设计为单柱式标志、单悬臂式标志、双悬臂式及附着式,具体形式主要根据道路条件和交通标志类型选择确定。 标志设计原则:交通标志的设置尽可能不偏设、不漏设、不多设,严禁错设。标志位置恰当,信息简洁、明确。 标志板材料:所有标志板面均采用铝合金板、合成树脂类材料,版面面积大于10平方米的标志,底板厚δ=3mm外,,版面面积小于10平方米的标志,底板厚δ=2mm。 标志反光材料:根据有关规定,并结合不同位置标志视认性的差异,本设计中的所有标志均采用二级反光膜。 标志版面颜色:指路标志版面颜色均为蓝底白图案,告示标志:一般为白底、黑字、黑图案、黑边框。警告、禁令、辅助标志及百米桩、公路界碑等按相关规范执行。 标志版面尺寸设计原则: 指路标志尺寸为*;单立柱标志尺寸为*,*等。 (二)交通标线 (1)标线材料采用热熔型加玻璃珠2号涂料。使具有良好的耐磨性、可见性、防滑性、干燥性、无毒性。标线设置情况: (2)道路交通标线的色度应符合GB/T16311的规定; (3)路面标线的技术要求应符合JT/T280、GN47、GN48的要求; (4)地面标线施工前必须加划底漆(下粘剂),标线涂层厚度±,材料用量按4kg/㎡控制。标线表面撒玻璃珠,应分布均匀,含量~㎡。 (5)减速振动标线颜色为白色,其基础部分厚度为2mm,凸起部分厚度为5±1mm,

公路工程监理使用表格word版本

公路工程监理使用表格

目录 1、总体施工组织设计报审表················································A-10 2、分项(分部、单位)工程开工申请批复单··································A-11 3、施工放样报验单························································A-12 4、原材料报验单··························································A-13 5、分项工程施工主要人员报验单············································A-14 6、进场设备报验单························································A-15 7、施工方案及主要工艺报审表··············································A-16 8、专项安全、文明(环保)施工方案报批单··································A-17 9、检验申请批复单························································A-18 10、工序检查报验单·······················································A-19 11、下承层检验申请批复单·················································A-20 12、混凝土浇筑申请报告单·················································A-21 13、施工单位月工作计划报告单·············································A-22 14、施工单位每周工作计划·················································A-23 15、监理巡视记录························································A-24 16、监理旁站记录·························································A-25 17、监理日志·····························································A-26 18、监理日巡视、旁站、抽捡安排表·········································A-27 19、工地会议记要·························································A-28 20、监理指令·····························································A-29 21、工程暂时停工指令·····················································A-30 22、复工申请·····························································A-31 23、复工指令·····························································A-32 24、施工日志·····························································A-33 25、工程质量(安全)事故处理报告单·······································A-34 26、中间交工证书·························································A-35 27、公路工程(施工段)交工验收证书··································A-36 28、工程缺陷责任期终止证书···············································A-37

监理实施细则(绿色建筑分部工程))

B13 工程 监理实施细则 (绿色建筑分部工程) 内容提要: 绿色建筑分部工程概况 本工程特点、难点 监理工作依据 监理组织机构 监理工作流程 监理工作控制要点及目标值 监理工作方法及措施 工程监理机构(章): 专业监理工程师: 总监理工程师: 日期: 镇江市住房和城乡建设局监制 二〇一六年三月

绿色建筑分部工程监理实施细则 1 绿色建筑分部工程概况 1.1 工程概况:本工程为公司开发建设的住宅工程,分为地下车库及住宅,总建筑面积约为273714.41平方米,建筑层数为:地下两层或三层、地上三十三层或三十四层的高层住宅建筑,与地下车库相连。本工程因地处中国南方地区,属夏热冬冷地区。 1.2 本工程绿色建筑分部工程概况 表1.1

2 本工程绿色建筑分部工程的特点、难点 2.1本工程绿色建筑分部工程设计、施工特点、难点:屋面和墙体保温材料的施工及塑钢窗高透光塑钢中空玻璃5+6A+5+6A+5或内置遮阳一体化5+19Ar+5施工。 2.2本工程绿色建筑分部工程监理质量控制的重点:屋面和墙体保温材料的施工及塑钢窗高透光塑钢中空玻璃5+6A+5+6A+5或内置遮阳一体化5+19Ar+5施工。 3 绿色建筑分部工程监理工作依据 3.1 绿色建筑设计方案审查表、经审查合格的设计文件。 3.2 本工程施工合同、协议等资料。 3.3 本工程《监理规划》。 3.4 经批准的工程施工组织设计、专项施工方案。 3.5 本工程适用的绿色建筑分部工程相关现行法律法规、技术标准规范及图集。 绿色建筑分部工程相关现行法律法规、技术标准规范及图集一览表 表3.1

3.6 其他依据:国家、省、市现行的法律法规、相关标准和规定。 4 项目监理部组织机构 4.1项目监理部组织机构框图(示意,框图中可添加人员姓名) 图4.1项目监理部组织机构框图 5 绿色建筑分部工程监理工作流程(用框图表示) 5.1绿色建筑分部工程施工阶段监理程序:

交通标志工程监理细则资料讲解

交通标志工程监理细 则

B13 ××××××工程 监理实施细则 (交通标志工程) 内容提要: 专业工程特点 监理工作流程 监理工作控制目标及控制要点 监理工作方法及措施 项目监理机构(章): 专业监理工程师: 总监理工程师: 日期: 江苏省建设厅监制

目录 第一章总则 (2) 第二章交通标志工程监理 (2) 一、一般规定 (2) 二、进场材料检查 (3) 三、开工报告 (3) 四、施工监理 (3) 五、备注 (7) 六、相关监理程序说明 (7) 交通标志工程监理细则

第一章总则 目的:为了加强高速公路建设项目的交通工程质量管理,合理控制工期和工程费用,使施工监理工作法制化、标准化、规范化、程序化,特制定本细则。 依据:依据交通部颁发“公路工程施工监理规范”及相关高速公路蒙蚌段工程合同文件制定。 施工监理原则:监理单位和监理人员应按照“严格监理、热情服务、秉公办事、一丝不苟”的原则认真贯彻有关监理的各项方针、政策、法规。认真做好施工监理工作。 适用范围:高速公路××段交通工程建设项目 备注:本项监理办法有关条款如与业主合同条款有异,以业主合同条款为准。 第二章交通标志工程监理 一、一般规定 以二公里划分为分部工程,分项工程中又分为放线定位、基坑开挖、基础混凝土浇注、支柱安装、交通标志安装等工序。每道工序施工完毕,经自检合格后,再报监理人员检验,上道工序未经监理人员检验认可,不许进入下道工序的施工。 本工程适用标准: GB 1720漆膜附着力测定法 GB 2423.17 盐雾试验方法 GB 2893 安全色 GB 3190 铝及铝合金加工产品的化学成份 GB 3194 铝及铝合金板材的尺寸及允许偏差 GB 3199 铝及铝合金加工产品的包装、标志、运输、贮存 GB 3681 塑料自然气候暴露试验方法 GB 3880 铝及铝合金轧制板材 GB 3978 标准照明体及照明观测条件 GB 3979 物体色的测量方法 GB 5237 铝合金建筑型材 GB 5768 道路交通标志和标线 GB 8416 视觉信号表面色

道路工程监理实施细则范文

市长寿区2014年农村公路路面改造工程 监理实施细则 (道路工程) 容提要: 专业工程特点 监理工作流程 监理工作控制目标及控制要点 监理工作方法及措施 项目监理机构(章): 专业监理工程师: 总监理工程师: 日期:

道路工程监理实施细则 1. 本细则编写依椐 1.1本项目工程已批准的监理规划。 1.2路达工程勘察设计咨询的一阶段施工设计图纸 1.3规、规程: 1.3.1《建设工程监理规》GB50319--2000 1.3.2《建筑工程施工质量验收统一标准》 1.3.3工程建设标准强制性条文 1.3.4各分部工程质量验收规如:(根据工程项目具体情况增加删减) 《工程建设强制性标准条文》房屋建设部分 《建筑地基基础工程施工质量验收规》GB50202-2002 《混凝土结构工程施工质量验收规》GB50204-2002 《建筑工程施工质量验收统一标准》GB50300-2001 《建筑工程质量检验评定标准》GB50301-2002 《公路路基设计规》JTG D30—2004 1.4 ******工程施工组织设计 ******工程委托监理合同 ******工程建筑工程施工合同 ******工程招投标文件 2. 专业工程特点

2.1 ******工程,位于****省******市****,总面积约****平方米,地上**层,地下**层,主要由*****组成。地下是***,地上主要是***,建筑高度是米,结构形式为**,基础形式为****。耐火等级是***,抗震设防烈度是****。 2.2 该工程建设单位是***,施工单位是***,设计单位是***(简单描述) 3.监理工作的流程如下: 4. 监理目标值

项目工程监理实施细则最全

. . 工程监理实施细则 XXX监理有限责任公司 XXXX工程监理部

目录 测量工程监理实施细则 (1) 基坑施工监理实施细则 (7) 大体积混凝土底板的监理实施细则 (18) 地下防水工程的监理实施细则 (32) 混凝土工程监理实施细则 (43) 模板工程监理实施细则 (48) 钢筋工程监理实施细则 (53) 钢结构工程监理实施细则 (58) 加气混凝土砌块墙体监理实施细则 (70) 屋面工程监理实施细则 (73) 门窗工程监理实施细则 (77) 装饰工程监理实施细则 (83) 冬季施工实施细则 (89) 旁站监理案 (93) 电气专业监理实施细则 (103) 水暖专业监理实施细则 (109) 电梯工程监理实施细则 (116) 通风工程监理实施细则 (121) 智能建筑工程监理实施细则 (125)

测量工程监理实施细则 工业与民用建筑的测量容主要包括:建筑物的定位、轴线放样、标高复核、建筑物总高测量、建筑物的垂直度测量、建筑物沉降观测。 一、测量前准备 ⒈测量前应对采用的测量仪器(水准仪、红外线测量仪等)进行校正和定期精度认定,以减少仪器的测量误差。 ⒉校核测量配套工具,如标尺刻线、丈量长度所用钢卷尺的精度。 ⒊准备好不同测量容所用的测量记录表。 ⒋检查判明测量用的原始点是否已破坏。 ⒌测量前应确定测量案,由于测量案关系到测量精度,因此,测量案应由技术负责人审核确认,其次,测量人员应有职责分工。 二、工程测量 ⒈建筑物的定位测量 ⑴建筑物定位测量前,应由建设项目法人提供规划测量部门测量并确认的建筑物角标的坐标,(包括书面通知和现场坐标移交)角标一般为三点以上,其中两点作为定位测量用,其余点作为校核用。 ⑵所提供的角标,施工单位应妥善保护,当角标位于建筑

交通工程监理实施细则2

交通工程监理实施细则 一、概述 合肥市望江西路(天智路~西客站西)工程起点位于天智路,终点位于西客站西。本交通工程附属设施涉及范围为:天智路~怀宁路段,线路设计起点位于天智路,起点桩号:K0-100,线路由西向东,终点位于怀宁路,终点桩号:K1+340,全长约为1400米。道路等级为城市主干道,设计速度为60km∕h。 二、编制依据 1、监理规划 2、设计图纸及有关规定 3、《城镇道路工程施工及质量验收规范》CJJ1-2008 4、《建设工程监理规范》GB50319-2000 5、《公路工程质量检验评定标准》JTG F80/1-2004 6、《公路交通标志和标线设置规范》JTG D82-2009 7、《道路交通信号灯设置与安装规范》GB 14886-2006 8、《合肥市智能交通管理技术规范》 三、工序部位工程质量控制签证流程图

四、开工前准备阶段监理 1、审查承包人编制的施工组织设计。施工组织设计文件一经监理工程师批准即作为以后施工应遵照的纲领性技术文件,成为施工承包合同文件的一部分,不得任意更改。监理工程师对承包人组织设计的审核着重抓以下几个方面: (1)交通施工技术措施要具有针对性,冬、雨季等特殊条件下施工必须有可靠的技术措施。 (2)应根据现场实际情况确定科学、可行的施工方案。 (3)施工机械设备的选择、配备和组合,除应考虑施工机械的技术性能、工作效率,还应保障施工进度、质量。 (4)承包人必须建立完善的质量保证体系,制定切实可行的质量保证组织、技术、经济、合同措施,建立健全质量管理组织机构,认真落实、履行“企业自检”。 (5)承包人必须根据工程特点制定切实可行的安全生产、文明施工措施。 2、审查承包人质量保证体系是否健全,人员是否到位。监理工程师将依照招投标文件对

市政道路及配套工程监理实施细则监理大纲范本

XXXXXX工程 监理实施细则 编制: 审批: 有限公司 XX年X月

目录 一、工程概况-----------------------------------------------------2 二、编制依据-----------------------------------------------------2 三、监理工作目标值-----------------------------------------------3 四、道路工程质量监理工作流程-------------------------------------3 五、道路工程测量放样质量监理-------------------------------------5 六、路基工程质量监理---------------------------------------------7 七、道路基层质量监理---------------------------------------------16 八、道路面层质量监理---------------------------------------------17 九、人行道工程质量监理-------------------------------------------23 十、附属构筑物质量监理-------------------------------------------23

一、工程概况 本项目位于。两条路均为城市支路,设计速度为30km/h。 主要参建单位: 建设单位: 设计单位: 监理单位: 施工单位: 本工程主要包括: 含道路标线、导向箭头、地面文字标记、标志杆基础。 二、编制依据 1、工程施工合同文件、设计图纸及招标文件等资料。 2、《城市道路工程设计规范》(CJJ37-2012); 3、《城市道路交叉口规划规范》(GB 50647-2011); 4、《城市道路交叉口设计规程》(CJJ 152-2010); 5、《城市道路路线设计规范》(CJJ 193-2012); 6、《无障碍设计规范》(GB 50763-2012)。 7、《城市道路路基设计规范》(CJJ 194-2013); 8、《建筑地基处理技术规范》(JGJ 79-2012); 9、《城镇道路路面设计规范》(CJJ169-2012); 10、《公路沥青路面设计规范》(JTG D50-2006); 11、《城镇道路工程施工与质量验收规范》( CJJ 1-2008); 12、《公路水泥混凝土路面设计规范》(JTG D40-2011)。 13、其它有关的国家及地方强制性规范和标准 14、经批准的监理规划 15、《建筑工程施工技术资料编制指南》; 16、《省建筑工程竣工验收技术资料统一用表》; 17《建筑施工安全管理资料统一用表》 18、行业主管部门现行有关建设工程管理的文件规定;

住宅小区附属工程市政工程监理实施细则

住宅小区附属工程市政工程监理实施细则 市政工程监理实施细则 宁波宁大工程建设监理有限公司 2010年11月 一、工程概况: 本工程为昌平区回龙观镇居住及公共设施项目市政工程,本项目位于昌平区回龙观镇朱辛庄西二路东侧,朱辛庄中路南侧、朱辛庄东路西侧、北京农学院北路北侧。此次施工的范畴为一期开发的A区和B区内的市政配套设施,包括雨污水、中水、给水、消防、热力及园区道路工程施工。

工程总造价975(万元)。工程工期要求:2010年10月5日园区地下管线完工,2010年11月15日道路工程施工完成,工程打算开工日期2010年0 8月01日,打算完工日期2010年11月15日,总工期107日历天,工程质量要求:合格。 参建单位: 建设单位:北京科技园建设(集团)有限公司 设计单位:北京新纪元建筑工程设计有限公司(室外综合) 北京兴天华市政工程设计有限责任公司(雨污水) 监理单位:北京帕克国际工程咨询有限公司 施工单位:北京市常青市政工程有限公司 二、编制依据: (一)《中关村甲3号项目监理规划》 (二)国家及北京市颁发的有关建筑施工的有关法律法规: 1.《给水排水管道工程施工验收规范》GBJ050268-2008 2.《高密度聚乙烯排水管道工程施工与验收技术规程》DBJ01-94-200 5 3.《城镇道路工程施工质量检验标准》DBJ01-11-2004 4.《排水管渠工程施工技术规程》DBJ01-13-2004 5.《市政基础设施工程质量检验与验收》DBJ01-90-2004 6.《北京市给水排水管道工程施工技术规程》DBJ01-47-2000 7.《北京市都市道路工程施工技术规范》DBJ01-84-2004 8.《公路路面基层施工技术规范》JTGF40-2004 9.《公路路面基层施工技术规范》JTJ034-2000 10.《沥青路面施工及验收规范》GB50092-96 三、施工预备时期的质量操纵 1、熟悉设计文件、施工操作规程、质量验评标准、有关合同及协议。 2、参加图纸会审、设计技术交底会。 3、审查承包单位报送的施工组织设计及重点部位、关键工序的施工工艺和

公路工程监理实施细则

泸县X005 福永路石岗场至新桥段改造工程 施 工 监 理 实 施 细 则 编制人: 审批人: 四川省兴旺建设工程项目管理有限公司 二○一五年七月

目录 1、封面 2、项目概述 3、监理范围 4、监理依据 5、监理目标 6、监理工作原则 7、监理组织机构及部门职责范围 8、主要监理人员岗位职责 9、监理工作内容 10、附则 11、组织机构图 12、监理程序框图 13、测量放样实施细则 14、路基工程施工监理实施细则 15、结构物回填监理实施细则 16、钢筋工程监理实施细则 17、混凝土工程监理实施细则 18、钢筋混凝土工程监理实施细则

一、项目概述 一、概述 1、任务依据 根据泸县福集镇、喻寺镇政府与四川兴旺建设工程项目管理有限公司签订的监理合同,组建监理机构,对泸县X005福永路石岗场至新桥改造工程,实施施工阶段监理工作。 2、设计标准 本路段设计标准为三级公路。 (1)计算行车速度:30km/h; (2)路基宽度7.5米、路面宽6.5米,两车路肩宽各0.5米,路面铺设水泥砼。 (3)设计荷载: 路面:标准轴载BZZ-100; 桥涵:计算荷载汽车-20级、验算荷载挂车-100; (4)设计洪水频率: 小桥、涵洞及小型构造物1/50; 二、路线及工程概况 县道福永路石岗场至新桥段三级公路改造工程,路线起点K0+000位于福永路K2+047,终点K9+889.544。 二、监理范围 项目监理为施工阶段的全过程的全面监理,包含施工准备阶段监理、施工阶段监理、交工及缺陷责任期阶段监理。 监理工作范围为泸县X005福永路石岗场至新桥改造工程一个施工合同段,起讫桩号为K52+802.3至K67+791.61,全长14.943公里。监理工作包括路基、路面、桥涵、路线交叉交通工程及沿线设施、环境保护等工程。 三、监理依据 3.1国家、交通部、福建省颁发的法律、法规和《公路工程施工监理规

路面及附属工程监理实施细则

路面及附属工程监理实施细则 一、工程概况 本工程为新建城市道路,道路起于会展路,终点至石门路,长518米,宽14米。其中石园路连接隧道长度269.597米,净宽8.2米。道路等级为城市支路,设计速度为20公里/小时。 机动车道沥青面层结构:8cm粗粒式沥青砼AC-25C,4cm细粒式沥青砼AR-AC13。 编写依据: 1、施工合同、监理合同; 2、施工图及相关勘测、设计、变更文件; 3、经各方确认的会议纪要和其他书面记录、函件、传真、数据电文等; 4、《城镇道路工程施工及质量验收规》CJJ1—2008; 5、《沥青路面施工及验收规》标准号:GB50092-96 6、《建设工程监理规》GB50319—2013; 7、《公路沥青路面施工技术规》标准号:JTG F40-2004 8、《公路改性沥青路面施工技术规》(JTJ036-98) 9、监理规划; 10、国家及省市现行的工程建设强制标准及其他相关的法律法规; 11、经过批准的施工组织设计、(专项)施工方案。

二、施工阶段监控要点 1. 路床 (1)路床不得有翻浆、弹簧、起皮、波浪、积水等现象。 (2) 路床用20吨压路机碾压后,至表面无明显轮迹为止。 (3) 石质路床必须嵌缝紧密,不得有坑槽和松石。 (4) 路床的质量控制目标如下表 路床控制目标值

2.级配碎石垫层 (1)级配碎石压碎值不大于30%,材料针片状颗粒含量不大于20%,不应含有风化石、山皮、泥土块、有机等有害物质。 (2)级配碎石需用机械拌合摊铺和碾压,施工配料必须准确,摊铺或拌合必须均匀,并应严格掌握厚度。 (3)在最佳含水量时,用20T以上压路机进行碾压,压实度不得小于96%,压实后应无明显轮迹及推移等现象。 (4)垫层铺筑后应严格限制车辆通行,保护期不受破坏。 3.水泥稳定碎石层 (1)恢复道路中线,直线段每10米设一桩,弯道每5米设一桩,并在路肩外设置指示桩,并在指示桩上标出高程线和把松铺线和压实后的设计标高定在边桩上,签返《施工放线报验单》。 (2)水泥稳定级配碎石需用机械拌和摊铺和碾压。 (3)检查施工单位水泥稳定碎石层配料是否准确,含水量、水泥用量是否符合要求。 (4)水泥稳定碎石基层中所用的水泥掺量为5.5%(4.5%),32.5级普通水泥,硅酸盐水泥均可使用,初凝时间在3小时以上终凝时间在6小时以上,基层压实工作必须在水泥终凝前完成。 (5)水泥稳定碎石基层,碎石最大粒径不应超过5cm,碾压应均匀、密实,用20吨以上压路机碾压压实厚度不超过20cm,应分层铺筑,每层压实厚度不小于10cm,压实遍数不小于6~8遍,至表面无明显轮迹为止。

交通标志工程监理实施细则

个人资料整理仅限学习使用 第一章总则目的:为了加强高速公路建设工程的交通工程质量管理,合理控制工期和工程费用,使施工监理工作法制化、标准化、规范化、程序化,特制定本细则。依据:依据交通部颁发“公路工程施工监理规范”及相关高速公路蒙蚌段工程合同文件制定。施工监理原则:监理单位和监理人员应按照“严格监理、热情服务、秉公办事、一丝不苟”的原则认真贯彻有关监理的各项方针、政策、法规。认真做好施工监理工作。适用范围:高速公路蒙蚌段交通工程建设工程备注:本项监理办法有关条款如与业主合同条款有异,以业主合同条款为准。第二章交通标志工程监理交通标志及基础工程监理一、一般规定以二公里划分为分部工程,分项工程中又分为放线定位、基坑开挖、基础混凝土浇注、支柱安装、交通标志安装等工序。每道工序施工完毕,经自检合格后,再报监理人员检验,上道工序未经监理人员检验认可,不许进入下道工序的施工。本工程适用标准GB 1720漆膜附着力测定法GB 2423.17 盐雾实验方法GB 2893 安全色GB 3190 铝及铝合金加工产品的化学成份GB 3194 铝及铝合金板材的尺寸及允许偏差GB 3199 铝及铝合金加工产品的包装、标志、运输、贮存GB 3681 塑料自然气候暴露实验方法GB 3880 铝及铝合金轧制板材GB 3978 标准照明体及照明观测条件GB 3979 物体色的测量方法GB 5237 铝合金建筑型材GB 5768 道路交通标志和标线GB 8416 视觉信号表面色GB 9344 塑料氙灯光源暴露实验方法以及涉及上述内容的更新标准。二、进场材料检查1. 提供和使用的材料,必须符合图纸要求和有关规定。2. 除非图纸规定或监理工程师有指示,否则底座混凝土标号应不低于25号。支柱或其部件应为热镀锌钢材;立柱、横梁、法兰盘的镀锌量不低于GB5768--1999规定的600g/m2要求,紧固件不低于350g/m2。承包人在订货前应将样品及测试资料提交监理工程师批准。3. 材料进场后,由监理、安装单位共同交验,现场主要依据合同文件和相关技术规范对到场材料进行外观质量、结构尺寸、防腐层质量、材质证明文件、出厂标志和数量检查。检验时填写《进场材料检验单》。4. 原材料进场后,监理人员应对进场的各种原材料进行检查:<1)检查水泥标号、出厂日期及合格证等,工程施工中不得使用过期的水泥。<2)工程用砂和石料应符合图纸和技术规范的规定。三、开工报告分部工程开工报告应说明工程名称、位置桩号、开工条件、施工人员和机械配备情况、施工方案、工艺流程图、质保体系并明确相关负责人、安全生产及环保措施、工期安排、明确工地工程负责人,同时提交水泥混凝土配合比报告、水泥混凝土抗压实验记录、砂石实验报告等实验记录,将其报总监审批。四、施工监理1、材料的组织生产工程所用材料严格按技术规范和设计图纸的要求采购、加工、制作、运输和安装,运抵现场的工程材料报请监理工程师检验合格后,方准使用,所用材料均附有出厂合格证及相关检验证明文件。只有通过监理工程师验收的材料承包人才能用于本工程;承包人用于本工程的材料,也必须随时随地接受工程师的抽样复查。所用材料的验收性实验,都必须在工程师同意的实验室并在工程师在场的情况下进行,还应提交实验报告两份。材料的实验费用,均不单独支付。所有运至工地的外购材料,必须有出厂证明书<标有厂名、材料名称、规格和数量、出厂日期和批号,实验报告和订货单副本)报工程师审查,若无上述文件或文件内容不全或文件内容与实物不符或有虚假伪造,则工程师都有权拒用。2、交通标志基础施工(1>施工前,必须依据设计图纸和现场交底的控制桩点进行标志位置的复测,并按施工需要放线要避开可能造成视线阻碍的构造物、高压线等,注意控制基础标高。浇筑混凝土基础应按图纸要求立模<业主制定厂家生产的整体钢模制作),配筋,回填土应分层夯实再做平台,监理旁站回填过程。<2)钢筋排列的形状及各部件尺寸应符合图纸要求,钢筋纵横交叉处应采用直径为1.2mm或1.0mm的铁丝绑扎牢固,不滑动,不遗漏。板与混凝土的接触面应平整,边缘整齐拼缝紧密牢固。预留孔洞位置准确,尺寸符合图纸要求。<3)法兰盘的安放位置应符合图纸要求。浇筑砼的强度应符合设计要求。浇灌混凝土时必须进行振捣,无论采用人工或机械振捣都应按层依次进行,捣固应密实,不得出现跑模,漏浆等现象。