风电塔筒施工组织方案

风电塔筒施工组织方案
风电塔筒施工组织方案

风电场塔筒制作防腐

绍兴县防腐保温工程公司

二〇一四年十月二十八日

目录

1 综述.......................................................... .... ........... ................ ....................

2 涂层质量检查.................................................. ........ ... ............. ...................

2.1腐蚀环境及保护期............................................ ........ ......... ....... ................

2.2涂层质量检查................................................. ........ .... ............ ...................

3 表面准备..................................................... ........ ................ .................... ...

3.1准备工艺........................................... ........ ..........

...... .............................. ...

3.2准备步骤、打砂清理和粗糙度要求.............................. ................... ..........

3.3涂装施工要求................................................. ............. ...... ................... .....

4 防腐涂料配套组合方案......................................... ................... . ..................

4.1塔筒筒体和门防腐涂料配套组合方案............................ ................... .........

4.2塔筒基础段防腐方案.......................................... ................... ................... ...

4.3塔筒附件防腐方案........................................... ................... ................... .......

4.4防腐质量检测................................................ .... .......... ......... ................... ......

施工技术方案

1 综述

1.1 本技术条件规定了//MW 风力发电机组塔筒和基础环防腐的技术要求,包括表面防腐材料的选择、表面处理、涂覆施工程序和涂层质量的检查。

1.2 按照国家相关标准规定,涂装前施工企业应对涂装材料的品名、种类和规定的技术指标进行检验和复验;合格方可用于产品涂装。

1.3如果业主方希望做本技术条件外的任何改变,他必须在执行前以书面形式向承包方说明。由业主方全权负责评定此类请求;业主方批准后要书面通知承包方(传真或者PDF文件)。

1.4 如果要更改部件,部件的部分,涂装材料或者涂装设计,必须在第一批施工前将更改的相关文件提供给业主批准。施工单位只有在收到业主的书面批准更改后才可以进行上述更改。

1.5 承包方应按照业主要求完成涂装工作。并向业主提供相关的技术资料,验收资料等相关资料(如工作函和工作施工范围内容,施工计划)等等详细内容资料。

1.6 每个零部件技术条件中都有与本技术条件的有关章节相关联的技术要求。没有涂覆的区域和其它特殊部位的技术要求应按照零部件和附图中的技术要求执行。

1.7 必须按本技术条件规定的涂层系统施工;如果需要选用不同的涂层系

统,那么必须选择与它们相当或者更高级别的涂层系统。

1.8 如果本技术条件中仅仅个别条款在其它协议中有不同的规定,那么其它条款不受限制仍然适用。如果在技术要求中、数据清单中或者本技术条件中有矛盾的要求时,那么应该按最严格的要求执行。

2 涂层质量检查

2.1 腐蚀环境及保护期

考虑到风机裸露于强烈阵风、湍流风、高温、低温、瞬时冲击载荷大等恶劣环境条件下工作,同时还要考虑内陆地区风沙及沿海地区潮湿、盐蚀等自然条件的影响;环境温度范围:-40℃~50℃;工作环境温度:-30℃~40℃;相对湿度≤95%;海拔≤2200m。考虑到上述腐蚀环境的实际情况,根据ISO 12 944-2 的要求,内陆地区塔筒的外表面属于腐蚀性类别C3,内表面属于腐蚀性类别C2;沿海地区塔筒的外表面属于腐蚀性类别C5M 或C5I,内表面属于腐蚀性类别C4。根据ISO 12 944-1 的要求塔筒的防腐保护等级为“长期”防腐寿命设计须大于 15 年,20 年内腐蚀深度不超过0.5mm。

2.2 涂层质量检查

2.2.1 总则

1)涂层质量的检查必须符合ISO 12 944-7 的要求,并且符合塔筒附件、基础环涂层厚度的规定。

2)涂层厚度均匀,不能有明显高低不平和迭起的状况,更不允许有流挂现象,涂层表面不能有漏涂、针孔、结皮、气泡等缺陷,颜色一致、平整光亮;并符合规定的色调,施工单位对涂层表面质量进行检查记录。

3)涂装施工方必须严格按照涂料供货厂家提供的技术参数表的要求进行涂装施工。

4)原则上按照涂料制造厂的产品技术参数表要求进行控制。任何与其要求

的偏差要事先获得油漆供货厂家的书面批准,并且使用的油漆要得到用户的许可。在涂装工作完成后,交货前必须将涂层质量检查记录文件提交给用户。

2.2.2 承包方资格及对承包方要求

1)进行涂装施工的承包方必须是从事涂装工作的专业公司。

2)承包方必须具有充足的专业技术人员和专业施工人员以及涂装施工必备的专用装备,能够确保可靠地完成规定的工作,确保每个工艺步骤都能达到防腐要求的涂装质量。

3)如果承包方想采用不同于本规范的方法来完成涂覆工作,必须得到客户的书面同意。

4)涂装施工工艺应当由专业技术人员编制,涂装质量由质量检验人员监督和检查,并采用适当的设备进行检查测试。

5)承包方应根据相关资料制定符合国家现行法规的健康、安全和环保的工艺措施,确保施工安全。

2.2.3 油漆材料

1)油漆制造厂必须是一家有资格的专业公司。

2)油漆材料由油漆制造厂供货时必须提交产品合格证、产品技术说明书和材料安全参数表。

3)必要时应在用户、涂装承包方和油漆供货方三方在场时,共同见证取样,并送有资质的涂料检测单位进行油漆技术参数指标的抽检或复验。

4)承包方负责满足涂料产品技术参数表中关于存储、处理和干燥(固化)的要求。

这些要求包括检查包装标签的详细内容和正确记录所有工艺步骤。

2.2.4监督和检查工作

1)根据ISO 12944-7的要求,涂装承包方必须一直由专业的有资格的人员监

督和检

查打砂清理和涂漆工作。他们必须使用必要的合适的设备。

2)必须进行以下检查:

a.检查干漆膜厚度(磁感应法)。一点的读数应当是距其26mm范围内其他三点的平均值。膜厚的分布根据90-10原则测量,即所测干膜点数的90% 应当等于或大于规定膜厚,剩余的10%的点数的膜厚应不低于规定膜厚的90%。施工中,应该按照GB/T 13452.2标准,每3平方米进行一次测量,并做涂层施工质量检查记录,每台塔筒涂装完毕后以报告形式提交给用户。

b.根据GB/T9286要求,进行附着力试验。在0-5的比例上合格等级为“0”或者“1” 。每种类型的表面都必须在试件上进行试验。这些试件必须打砂清理并且和部件一起涂漆。样本的一侧应该用外部油漆系统来上漆,另一侧应该用内部油漆系统来上漆。

c.视觉检查。内容包括颜色和光泽,涂层表面不能有漏涂、针孔、结皮、流挂、气孔,剥落,裂纹等缺陷。

以上检查记录须用涂层质量检查报告的形式提交给用户。

2.2.5 控制表面

a.为了确定施涂方法和工作质量标准,随时评定涂层质量和涂漆效率,必须按照ISO12 944-7和 ISO 12 944-8的要求对控制表面进行涂漆。按照订单规范制作的第一个完整涂漆部件作为控制表面。必须按照ISO 12944-7的要求准备其他所需的控制表面。

b.在首件控制表面上开始涂装之前,涂装承包方必须及时邀请用户和油漆系统供货厂家见证涂装过程。即使用户不参加,也必须和涂层系统供货厂家一起对控制表面涂漆。

3 表面准备

根据ISO 12 944-4规范的规定对塔筒体涂装部件的表面进行准备。在开始涂装工作之前,塔筒体涂装表面必须达到要求的粗糙度和清洁度,并在表面冲砂除锈后立即涂第一层油漆。

3.1 准备工艺

3.1.1对风机塔筒的棱角边先用砂轮机打磨至R1~2mm;焊缝表面除去飞溅、焊渣必须在打砂清理之前完成。

3.1.2塔筒表面在预处理前,应用清洁剂除去表面油脂、盐份等有害物质。

3.2 准备步骤、打砂清理和粗糙度要求

3.2.1 非机加工面喷涂前采用喷砂除锈,基体表面粗糙应达到Rz40~80μm,并保证致密度和均匀度。喷砂用压缩空气必须干燥;砂料必须有棱角、清洁、干燥,特别是应无油污、可溶性盐类,喷砂防锈表面应达到GB8923 之3.2.3 项的Sa2.5 级要求。对于个别部位喷砂达不到要求的要求时,应采用电动工具机械打磨除锈,达到GB8923 之3.3.3项的St3 级要求。喷砂所用的磨料应符合YB/T5149、GB6485 的标准规定。建议使用钢砂、钢丸。金属砂最好是棱角砂与钢丸混合使用,混合比例为30%,70%,棱角砂的规格为G25、G40,钢丸的规格为S330,可以用非金属磨料,但不准用海砂,建议使用铜矿砂或金刚砂。粒度为:16-30 目,磨料硬度必须在40-50Rc 之间。

3.2.2 喷(抛)射清理使用的磨粒大小应与适用的涂层系统的要求相一致;即表面轮廓高度(锚纹轮廓),表面轮廓将根据ISO 8503 标准分级。

3.2.3 完成打砂清理后,必须除去所有的打砂残留物并从打砂表面上彻底清除灰尘。

3.2.4 已喷砂的表面在涂覆前,不允许与污染物接触;经预处理的表面应即时进行底漆

涂装,若间隔时间超过3h,对预处理表面应进行妥善保护。由于发生故障喷

砂后停留时间过长或其他原因致使基体表面明显变质时,应再次进行打砂处理。根据表面预处理等级的规定,所有的零部件必须用薄缘的磨粒进行喷(抛)射处理。喷(抛)射清理使用的磨粒应该是干的、清洁的、不含污染物,不然这将会对涂层的性能产生负面影响。

3.3 涂装施工要求

3.3.1实施正确的涂装方法是获得良好涂层的关键之一。在涂装施工之前,必须根据涂装物件、设计要求、涂料种类、设备条件和施工环境等做出最佳选择。

3.3.2涂装施工时应遵循涂料作业的相关规定,无合格证书或质保书的涂料不能施工,未经入库复验合格的涂料不能施工,在混合搅拌或稀释过程中发现涂料有分层、沉淀等现象时不能施工。

3.3.3喷砂后尽快喷漆,其间隔时间愈短愈好,在干燥的晴朗天气,间隔时间不能超过12h;在相对湿度≤85%的天气应在4h内完成;若存在轻微盐雾气氛,间隔时间不能超过2h;聚氨酯面漆只能在相对湿度低于80%时涂覆。3.3.4 在喷涂过程中应注意防尘、防污染等,常温型涂料施工环境温度范围为5℃—40℃,相对湿度≤80%;当湿度超过85%或钢板温度低于露点3℃时不能进行喷漆施工;当环境温度为-10℃~5℃时,施工必须使用冬用型涂料,施工工艺及要求必须按涂料厂家提供的施工说明进行;当环境温度低于

-10℃时,不允许施工。施工单位应对施工环境进行监测和记录。

3.3.5 防腐过程中,机加工表面和螺纹表面应涂可清洗的防锈油并采取措施进行可靠保护以防止油漆和其他污染物玷污。

3.3.6 防腐涂装中,补涂质量是直接影响其防腐寿命的重要因素。因此,施工单位必须加强对补涂施工的工艺控制。

5 表面处理要求

5.1 为了保证涂层系统发挥最佳性能,钢结构表面在喷射清理前,须先进行结构处理,按ISO 8501-3:2001 进行。锐边和切割边缘打磨到R≥2mm,气孔要进行补焊,咬边要进行打磨,焊缝光顺没有焊渣、飞溅等。结构处理前对焊缝进行预喷砂有助于更好地发现缺陷。

5.2 喷射清理前,所有油脂,或因探伤拍片留下的润湿剂按SSP S P1“溶剂清理”清除干净。

5.3 喷射用磨料要清洁干燥,不能对涂料性能有不利影响。不能使用河砂,因为它对工人健康有严重不利影响,并且在钢材表面夹砂严重不利于涂层质量。

5.4 磨料的大小要能产生涂料系统规定的表面粗糙度,表面粗糙度按GB/T 13288-2008执行。

5.5 喷射清理时,要防止油或水对喷射清理后的表面的污染。空压机须安装油水分离器。

5.6 磨料不能循环使用,除非得到业主代表或PPG公司现场技术人员的书面认可。

5.7 钢材表面要求喷射清理到GB 8923-88 Sa 2 ?(ISO 8501-1:1988),或SSPC SP10,即钢材表面在不放大的情况下进行观察时,表面应无可见的油脂和污垢,并且没有氧化皮、铁锈、油漆涂层和异物,任何残留的痕迹应仅是点状或条纹状的轻微色斑。

5.8 粗糙度达到Rz 40-70微米或ISO 8503-2中规定的“中等(G)”级别。

5.9 喷射清理后准备涂漆的钢材表面要清洁、干燥,无油脂,保持粗糙度和

清洁程度直到第一道漆的喷涂。

5.10 涂漆前钢材表面灰尘量小于GB/T 18570.3(ISO 8502-3)中规定的3级。

5.11 表面处理后4个小时内,钢材在返黄前就须涂漆。如果钢材表面有可见返锈现现象、变湿或被污染,要求重新处理到前面规定的级别。

5.12 镀锌件、铝件、喷锌或喷铝表面等非碳钢表面的表面处理,应遵循各自的施工要求。

6 环境控制

6.1 表面处理和涂漆施工过程中,要进行环境控制,以获得最佳的涂装质量。环境控制主要包括温度、相对湿度和露点。

6.2 表面处理和涂漆施工,要求在良好通风的室内施工。

6.3 在最终喷砂处理和涂漆过程,以及涂膜固化过程中,空气相对湿度要低于85%,底材须高于露点温度至少3℃。

6.4 无机硅酸锌涂料在固化过程中要求湿度至少70%以上,如果相对湿度过低,可以对涂膜表面洒清水以加速固化。

6.5 通常施工中环境温度必须大于10℃,钢材表面温度不得超过45℃,最好在15℃~30℃。钢材表面温度如果高于30℃,应特别小心避免成膜不良和过度干喷。

7 涂装施工

7.1 推荐采用高压无气喷涂,刷涂和辊涂仅限于小面积施工或预涂与局部修补。

7.2 涂料的调配:对于双组分涂料先应加入固化剂调配好后,再加入稀释剂

进行稀释。加入稀释剂的量符合各涂料的产品说明书所规定的范围,以达到要求的施工黏度。

7.3 正确的喷涂气压与涂料的种类、稀释剂的种类和稀释后黏度有关。空气喷涂时,一般调节气压0.30—0.60Mpa,并进行试喷而定。高压无气喷涂时,一般调节气压15—20Mpa,并进行试喷而定。

7.4 喷枪与工件表面必须保持垂直,绝对不可由手腕或手肘作弧形的摆动,见下图。

7.5 空气喷涂时,正常的喷涂距离应与喷枪的气压、喷枪的扇面调整大小以及涂料的种类相配合,一般喷涂距离为20cm左右;高压无气喷涂时,一般喷涂距离为50cm左右。

7.6 喷枪的移动速度与涂料干燥速度、环境温度、涂料的黏度有关,约以30cm/s的速度匀速移动。

7.7 喷涂方法有纵行重叠法、横行重叠法、纵横交替喷涂法、喷涂路线应从高到低、从左到右、从上到下、从里后外顺序进行。在行程终点关闭喷枪,喷枪第二次单方向移动的行程与第一次相反,喷嘴与第一次行程的边缘平齐,雾型的上半部与第一次雾型的下半部重叠,重叠幅度应第二次与第一次重叠1/3或1/2。

7.8 在正式喷涂前,针对边、角以及喷涂难以接近的部位等,要进行预涂,以确保这些部位达到规定的干膜厚度。预涂主要采用刷涂的方法进行。

8 质量控制

8.1 湿膜厚度控制

施工人员在喷漆过程中要要不断检测调节每道油漆的湿膜厚度,以控制干膜厚度,从而控制涂层的总干膜厚度。使用梳齿状湿膜仪在喷漆后应立即进行检测。

湿膜厚度与干膜厚度之间的关系如下:

体积固体分干膜厚度湿膜厚度

如果涂料稀释后进行喷涂,湿膜厚度与干膜厚度间的关系如下:

体积固体分稀释量干膜厚度稀释后的湿膜厚度) % (1

8.2 干膜厚度控制

每道涂层及最终涂层须用电子式干膜测厚仪进行干膜厚度的检测。膜厚不足时须按要求进行补涂到规定的干膜厚度。干膜厚度的检查按ISO 2808 或ISO19840 进行。

8.3 附着力检测

8.3.1 附着力检测可按划格法GB/T 9286 或拉开法GB/T 5210 进行。

8.3.2 划格法可以采用多刃刀具或单刃刀具。附着力小于等于2 级认定为合格。划格法测试程序和方法如下:

(1)测量漆膜,以确定适当的切割间距。干膜厚度在61~120 时,切割间距为2mm;干膜厚度在12-250 微米时,切割间距为3mm。

(2)以稳定的压力,适当的间距,匀速地切割漆膜,直透底材表面

(3)重复以上操作,以90°角再次平行等数切割漆膜,形成井字格

(4)用软刷轻扫表面。以稳定状态卷开胶带,切下75mm 的长度

(5)从胶带中间与划线呈平行放在格子上,至少留有20mm 长度在格子外以用手抓着,用手指摩平胶带

(6)抓着胶带一头,在0.5~ 1.0s 内,以接近60°角撕开胶带。保留胶带作为参考,检查切割部位的状态。

8.3.3 拉开法采用气动或液压型拉力仪进行,不推荐采用机械式拉力仪。涂层系统要求达到5Mpa 认为合格。测试方法和程序如下:

(1)铝合金圆柱用240-400 目细度的砂纸砂毛,使用前用溶剂擦洗除油(2)测试部位用溶剂除油除灰

(3)按正确比例混合双组份无溶剂环氧胶粘剂,再涂抹上铝合金圆柱,压在测试涂层表面,转向360°,确保所有部位都有胶黏剂附着

(4)用胶带把铝合金圆柱固定在涂层表面,双组份环氧胶粘剂在室温下要固化24 小时;氰基丙烯酸胶粘剂按说明书的要求(15 分钟后达到强

度,最好在2小时测试)

(5)测试前,用刀具围着铝合金圆柱切割涂层到底材,干膜厚度150微米以下只要各方同意,也可以不用刀具切割

(6)用拉力仪套上铝合金圆柱,进行测试,记录下破坏强度(MPa),以及破坏状态。用百分比表示出涂层与底材、涂层之间、涂层与胶水以及胶水与圆柱间的附着力强度及状态

划格法附着力图示

级别描述图示0 完全光滑:无任何方格分层---------

1

交叉处有小块的剥离,影响面积为5%

2

交叉点沿边缘剥落,影响面积为5-15%

3 沿边缘整条剥落,和/或部分或全部不同的格子,影响面积15-35%

4 沿边缘整条剥落,有些格子部分或全部剥落,影响面积35-65%

5 任何大于根据4来进行分级的剥落级别

4 防腐涂料配套组合方案

4.1 塔筒筒体和门防腐涂料配套组合方案

4.1.1 重度腐蚀环境

针对近海及滩涂沿海湿热、含盐份气候条件下重度腐蚀环境。防腐材料采用海虹老人牌(HEMPEL)产品。涂料配套组合为:

外表面:

涂漆材料(产品)干膜厚度

底漆老人牌环氧富锌底漆 17360-19830(灰红色)60μm

内表面:

塔筒被海浪淹没和冲刷及以上2 米的区域按照下防腐方案执行;海水具体淹没高度须由业主提供并经海装公司确认。

外表面:

内表面:

4.1.2 气候干燥地区

针对内陆地区气候干燥,有沙尘爆的气候。涂料配套组合为:

外表面:

内表面:

4.2 塔筒基础段防腐方案

4.2.1 基础环上法兰面至以下1000mm 的范围内(包括上法兰面)。按

GB/T9793-1988火焰喷锌或热镀锌,锌层厚度160±50μm。

4.2.2 基础环上法兰面至以下1100mm 的范围内(不包括上法兰面)。防腐材料采用海虹老人牌(HEMPEL)产品。针对近海及滩涂沿海湿热、含盐份气候条件下重度腐蚀环境按4.1.1 条技术要求进行防腐处理;内陆地区按

4.1.2 条技术要求进行防腐处理。

4.2.3 塔筒基础段距上法兰面1100mm 以下的其余所有面积喷涂无机富锌底漆40~50μm,确保运输过程中不锈蚀。

4.3 塔筒附件防腐方案

4.3.1 塔架平台、直爬梯,吊梁支架及入口梯子采用热浸锌防腐,锌层厚度

大于60μm。组装的平台应拆开分别防腐;其余可拆缷附件(梯架支撑、门挂钩、接地板等)采用热浸锌处理,与塔架焊接在一起的附件允许与筒体一起进行涂漆防腐。焊接避雷螺柱也须热喷锌,锌层厚度120±20μm;表面不允许有涂层。

4.3.2 塔筒上、中、下法兰对接接触面以及防雷接地耳板喷砂后,按GB/T9793 火焰喷锌或热镀锌,锌层厚度不小于200μm,表面不喷油漆涂层。

4.1防腐质量检测

4.4.1 面漆质量检测

4.4.2 锌层厚度测量按GB/T9793 中7.1 条检验。

4.4.3 锌层结合强度试验按GB/T9793中8.3条检验。

4.4.4 漆涂层厚度测量按GB/T13452.2 方法5 检验。

4.4.5 漆涂层结合强度试验按GB/T9286,达到“1”级及以上。

4.4.6 颜色:按需方提供的色标执行,并要求所有防腐产品颜色一致。

4.4.7 涂层外观应无流挂、漏刷、针孔、气泡等缺陷,颜色一致、平整光亮。

4.4.8 防腐竣工验收后,施工方提供完整的检验资料,随机交业主备查。

XXX风电安装施工方案

. XX风电场风力发电机组安装工程施工方案 编制单位: 编制人: 编制日期:

施工方案审批页

目录 1 工程概况 (1) 2 吊装平台规划 (3) 3 机组吊装的施工方法 (4) 4 施工网络进度计划 (23) 5 施工设备、机具及量具计划 (25) 6 项目管理组织机构及施工劳动力资源计划 (26) 7 施工质量保证措施 (28) 8 施工安全保证措施 (32) 9 文明施工及环境保护措施 (37) 10 冬雨季施工预防措施 (40)

1工程概况 1.1工程名称:XX风电场风机安装工程 1.2工程地址:云南省安宁市 1.3工程简述 XX风电场主要分为东、西两部分,西部区域主要位于安宁市与楚雄彝族自治州交界的山脊上,还有一部分位于安宁市青龙镇与禄脿镇交界的山脊,地理坐标介于北纬24°7′6″~25°7′6″,东经102°10′10″~102°14′17″之间,高程介于2100m~2600m之间;东部区域主要位于安宁市青龙镇与温泉镇交界的山脊上,地理坐标介于北纬25°0′2″~25°3′10″,东经102°20′41″~102°26′14″之间,高程介于2000m~2500m之间,本工程共布置43台2000kW风力机组,总装机86MW。 项目业主: 设计单位: 项目监理: 施工单位: 1.4工程量及机组参数 实物量安装43台单机容量为2000kW的风电机组。

1.5工程特点 ?高、大、重是风力发电机组的施工特点,设备吊装是施工的重点和难点; ?场区处于高山,多风、强阵风对机组吊装施工会产生不利的影响。 ?安装分两个区域进行。距离跨度较大,设备和机械需要二次转场。 1.6编制依据 ?招标方提供的招标文件及技术资料; ?《厂家提供的2.0MW风电机组现场安装手册》; ?《工业安装工程施工质量验收统一标准》GB50252-2010 ?《机械设备安装工程施工及验收通用规范》GB50231-2009 ?《工程测量规范》GB50026-2007 ?《建筑电气安装工程质量验收规范》GB50303-2002 ?《电气装置安装工程电力变流设备施工及验收规范》GB50255-96 ?《电气装置安装工程接地装置施工及验收规范》GB50169-2006 ?《电气装置安装工程电缆线路施工及验收规范》GB50168-2006 ?《电气装置安装工程高压电器施工及验收规范》GB50147-2010 ?《风力发电场项目建设工程验收规程》DLT5191-2004; ?《建筑机械使用安全技术规程》(JGJ33-2012); ?《起重机械安全规程》GB6067.1-2010 ; ?《起重工操作规程》SYB4112-80; ?《电力建设安全施工管理规定》和《补充规定》; ?《建设工程项目管理规范》GB/T50326-2006; ?《大型设备吊装工程施工工艺标准》SH 3515-2003 ?《风力发电场安全规程》DL796-2001 ?《中华人民共和国环境保护法》 ?《中华人民共和国水土保持法》 ?同类型工程施工经验、施工管理文件、资料及施工方案和工程技术总结

风电场施工组织设计

龙源巴里坤三塘湖风电场二期项目 施工组织总设计 ?、编制依据 1、新疆风电工程设计咨询有限责任公司做出的设计文件及施工蓝图 2、电力建设工程(建筑及安装工程)施工及验收规范,质量验评标准(SDJ69-87) 1) 建筑地基与基础工程施工质量验收规范 (GB50202-2002 2) 电力工程地基处理技术规范(DZ5024-2005 3) 砼结构工程施工质量验收规范(GB50204-2002 4) 钢结构工程施工质量及验收规范(GB50204-2001) \ 5) 建筑地面工程施工质量验收规范(GB50209-2002 6) 建筑装饰工程质量验收规范(GB50210-2001 7) 建筑电气安装工程质量验收规范(GBJ303-88 8) 建筑给排水,采暖安装工程质量验收规范 (GB50242-2002 9) 砌体工程质量验收规范(GB50203-2002 10) 建筑屋面工程质量验收规范(GB50345-2004

11) 电缆线路施工及验收规程(GB50168-92 12)电力建设施工及验收技术规定(BL147-90) 13)风力发电运行规程(DL/T666) 14)工程建设标准强制性条文(电力工程部分,房屋建设部 分(建表【2002】219号【2002】120号) 15)国家及电力行业的现行规程,规范标准及有关实施细 贝聽 二、工程概况 龙源巴里坤三塘湖风电二期场区位于新疆哈密地区巴里坤县三塘湖乡境内。该乡地处巴里坤县城以北88KM处,东径93° 5T ---94 17',北纬43° 48’ ---44 18’ .海拔高度900-990M,地势 南高北低,地形坡度1%-4%东靠伊吾县,西邻萨尔乔克乡,南连八墙子乡,北与蒙古人民共和国接壤,属典型的大陆干旱气候,光照资源丰富,昼夜温差大,全年无霜期170天,有效积温3440C,年均 温度7C,极端最高温度40C,蒸发量是降水量的110倍。由于具有充足的光热资源,加之土壤以砂土壤为主,适合种植经济类植物。是新疆风能资源最丰富的地区之一。全年风速起伏不大,风况较好,主导风向稳定。该区地质构造稳定性好,场址区及附近无活动断裂,无火上及岩浆活动,无大的地震发生,无滑坡、泥石流等不良地质活动,在20m深度范围内无饱和沙土及粉土。基础持力层为角砾层,地基承载力较好。

风电工程专用标准清单

2.风电工程专用标准 2.1 风电场工程可行性研究报告设计概算编制办法及计算标准 FD001—2007 2.2 风电场工程等级划分及安全标准(试行) FD002—2007 2.3 风电机组地基基础设计规定(试行) FD003—2007 2.4 风电场工程概算定额 FD004—2007 2.5 风力发电厂设计技术规范 DL/T 5383—2007 2.6 风力发电工程施工组织设计规范 DL/T 5384—2007 2.7 风力发电场项目建设工程验收规程 DL /T 5191—2004 2.8 风力发电机组验收规范 GB/T 20319—2006 2.9风力发电场运行规程 DL/T 666-2012 2.10风力发电场安全规程 DL 796-2012 2.11风力发电场检修规程 DL/T 797-2012 2.12风力发电场项目可行性研究报告编制规程 DL/T 5067-1996 2.13风力发电机组设计要求GB/T18451.1 2.15风电场风能资源测量方法 GB/T 18709-2002 2.16风电场风能资源评估方法 GB/T 18710-2002 2.17风力发电机组装配和安装规范 GB/T 19568-2004 2.18风电场场址工程地质勘察技术规定发改能源[2003]1403号 2.19风电特许权项目前期工作管理办法发改能源[2003]1403号 2.20风电场工程前期工作管理暂行办法发改办能源[2005]899号 2.21风电场工程建设用地和环境保护管理暂行办法发改能源[2005]1511号 2.22风电工程安全设施竣工验收办法水电规办[2008]001号 2.23风力发电机组第1部分:通用技术条件 GB/T 19960.1-2005 2.24风力发电机组第2部分:通用试验方法 GB/T 19960.2-2005 2.25风力发电机组电能质量测量和评估方法 GB/T 20320-2014 2.26风力发电机组异步发电机第1部分:技术条件 GB/T 19071.1-2003 2.27风力发电机组异步发电机第2部分:试验方法 GB/T 19071.2-2003 2.28风力发电机组塔架 GB/T 19072-2010 2.29风力发电机组功率特性试验 GB/T 18451.2-2012 2.30风力发电机组电工术语 GB/T 2900.53-2001 2.31风力发电机组控制器技术条件 GB/T 19069-2003 2.32风力发电机组控制器试验方法 GB/T 19070-2003 2.33风力发电机组齿轮箱 GB/T 19073-2008 2.34风力发电机组风轮叶片 JB/T 10194-2000

风电安装施工组织设计

辉腾锡勒风电场100MW世行项目工程( B1标段:风机安装) 施工组织设计

目录 第一章编制说明、依据、范围及工程概况 (4) 第二章施工部署 (8) 一、部署原则 二、工程建设目标 第三章现场总平面布置 (9) 第四章主要机械设备配置及进场计划 (10) 一、主要施工机械装备一览表及进场计划 第五章劳动力计划 (12) 第六章施工管理 (14) 一、项目管理机构 二、施工各岗位职责及管理制度 三、施工技术准备及管理 四、物资管理 五、建立收发文和资料管理制度 六、施工现场周边关系协调 第七章施工方法 (23) 一、施工机械的选择 二、施工顺序 三、施工条件准备 四、卸车和掏箱 第八章分部分项工程及工程重点、难点的施工方法 (25) 一、设备吊装吊车的选择 二、变频柜安装过程 三、底部塔筒的吊装 四、第二节塔筒的吊装

五、第三、第四节塔筒的吊装 六、机舱安装 七、转子的安装 八、其它工作 第九章设备的存放 (32) 第十章施工进度网络计划及工期进度保证措施 (33) 一、开竣工日期及进度网络计划 二、工期进度保证措施 1、组织保证措施 2、劳动力保证措施 3、机械设备保证措施 4、周转工具保证措施 5、进度计划动态控制措施 第十一章保证工程质量管理措施 (37) 一、质量保证体系 二、质量管理制度 第十二章安全生产保护措施 (41) 一、安全生产方针及目标 二、组织管理 三、安全教育 四、安全生产技术措施 1、安全防护技术措施 2、施工机械安全技术措施 3、吊装作业安全技术措施 第十三章冬雨季施工措施 (46) 第十四章环境保护、降低环境污染及噪音措施 (48) 第十五章文明施工措施 (51)

风电工程施工组织总设计

XXX风电场工程 施工组织设计 XXX公司 XXX年XXX月XXX日

目录 第一章工程概况及特点 (1) 1.1编制依据 (1) 1.2工程概述: (1) 1.3工程技术说明: (2) 第二章施工现场组织机构 (5) 2.1 施工现场组织机构设想 (5) 2.2项目部施工组织机构图 (7) 2.3施工现场管理职责 (7) 2.4 特种工人员配备 (10) 第三章施工现场平面布置 (12) 3.1施工现场总平面布置 (12) 3.2工地使用权及出入权 (15) 3.3工地管理方案与制度 (15) 第四章施工机具配置 (16) 4.1施工机具配置 (16) 第五章劳动力配备计划 (19) 5.1 施工力量配置 (19) 5.2劳动力计划 (20) 5.3作业队伍的准备计划 (22) 第六章施工方案 (23) 6.1工程准备阶段 (23) 6.2集电线路主要施工方法 (25) 6.3升压站建筑工程施工方法 (43) 6.4 风机基础施工方案 (60) 第七章工期及施工进度计划 (85) 7.1 工期规划及要求 (85)

7.2施工进度计划(进度计划横道图、网络图见附图2、3) (85) 7.3图纸交付计划 (86) 7.4进度计划风险分析及控制措施 (86) 第八章物资供应管理 (89) 8.1物资保管 (89) 8.2主要材料供应计划表 (90) 第九章施工质量管理 (91) 9.1 质量管理总目标 (91) 9.2 质量管理总方针:................................................................................................................................... - 60 - 9.3质量管理机构............................................................................................................................................ - 60 - 9.4主要质量职责............................................................................................................................................ - 60 - 9.5施工质量管理保证措施............................................................................................................................ - 62 - 9.6施工中应用的技术规范标准如下: ........................................................................................................ - 63 -第十章施工安全管理. (98) 10.1安全管理目标.......................................................................................................................................... - 64 - 10.2安全管理责任.......................................................................................................................................... - 64 - 10.3安全管理组织机构................................................................................................................................ - 67 -1第十一章环境保护及文明施工管理 . (111) 11.1 环境保护的目标、指标及措施 (111) 11.2 文明施工的目标、组织机构和实施 (112) 第十二章计划、统计和信息管理 (115) 12.1 计划、统计报表的编制与传递 (115) 12.2 信息管理目标及措施 (116) 12.3 工程档案管理 (116) 12.4信息管理 (117)

风电项目升压站施工组织设计

神华虞城风电项目升压站施工总承包 工程 施工组织设计 批准人: 审核人: 编制人: 山东泰开送变电有限公司 2020年4月

目录 第一章工程概况 (6) 1.1工程概况 (6) 1.1.1工程规模................................................................................ 错误!未定义书签。 1.1.2工程承包范围 (6) 1.1.3交通情况 (6) 1.2工程特点 (6) 1.2.1设计特点 (6) 1.2.2自然环境 (6) 1.3 项目管理特点及总体要求 (6) 第二章主要施工方案及技术措施 (9) 2.1 施工准备 (9) 2.2 施工工序总体安排 (11) 2.3主要工序和特殊工序的施工方法 (11) 2.3.1一般技术要求 (11) 2.3.2变压器安装及场试验 (13) 2.3.3母线安装 (14) 2.3.4隔离开关安装 (15) 2.3.5互感器、避雷器安装 (16) 2.3.6二次设备安装 (16) 2.3.7电缆敷设及井室 (17) 2.3.8 调试、试验 (20) 2.3.8 .1.电气一次设备调试、试验 (20) 2.3.8 .2.电气二次设备调试、试验 (20) 2.3.8 .3.现场试验 (21) 2.3.8 .3.1 GIS现场试验 (21) 2.3.8 .3.2避雷器试验 (22) 2.3.8 .3.3无功补偿装置的试验 (22) 2.3.8.3.4 中压开关柜试验 (22) 2.3.8 .3.5接地兼站用变的试验 (23) 2.3.8 .3.6 低压开关柜试验 (23) 2.3.8 .3.7母线、电力金具调试 (24) 2.3.8.3.8 接地调试 (24) 2.3.8 .3.9 二次结线的检验与试验 (24) 2.3.8 .3.10综合自动化系统设备及保护控制设备调试 (25) 2.3.8 .3.11直流及逆变电源 (26) 2.3.9系统调试 (27) 2.3.10资源配置 (27)

风电施工组织设计方案

第一部分总体策划 第1章编制依据及执行标准和规 1.1 编制依据 《电力建设工程施工技术管理导则》 国投吐番小草湖一期49.5MW风电场工程招标文件 国投吐番小草湖一期49.5MW风电场工程招标文件公告及招标编号中能建西北电力建设第四工程公司施工技术管理标准 我司对国投吐番小草湖一期49.5MW风电场施工现场实际情况的调查1.2 执行标准和规程规 《建筑地基基础工程施工质量验收规》GB50202-2002 《混凝土结构工程施工质量验收规》GB50204-2002 《混凝土结构设计规》GB50010-2002 《混凝土质量控制标准》GB50164-1992 《硅酸盐水泥、普通硅酸盐水泥》GB175-1999 《混凝土外加剂》GB8076-1997 《混凝土外加剂应用技术规》GB50119-2003 《普通混凝土用碎或卵质量标准及检验法》JGJ53-1992 《普通混凝土用砂质量标准及检验法》JGJ52-1992 《混凝土拌合用水标准》JGJ63-1989 《普通混凝土配合比设计规程》JGJ55-2000 《钢筋焊接及验收规程》JGJ18-2003 《钢筋混凝土用热轧带肋钢筋》GB1499-1998

《电气装置安装工程接地装置施工及验收规》GB50169-92 《接地装置工频特性参数的测量导则》DL475-92 《电气装置安装工程电缆线路施工及验收规》GB50168-92 以上标准若有新的版本则执行新标准,替代原有标准。 第2章工程概况 2.1 工程建设规模 2.1.1 工程名称 国投吐番小草湖一期49.5MW风电场工程 2.1.2 投资单位 国投电力控股股份有限公司 2.1.3 工程建设规模 国投吐番小草湖一期49.5MW风电场工程规划33台1500kW风力发电机组。每台风力发电机组均配置一台箱式变压器。 本标段工程包括如下容:风机基础地基处理,风机基础施工,箱式变电站基础施工,场检修道路施工。 2.2 工程自然条件 2.2.1工程地址 国投吐番小草湖风电场一期49.5MW项目位于新疆维吾尔自治区吐番地区,与乌木齐市公路里程约133km,与吐番市公路里程约72km,与大河沿镇公路里程约48km。风电场位于新疆吐番小草湖规划风区中的小草风电场,场地开阔,交通条件较好。 2.2.2 工程地质情况

风电风机及箱变基础建筑安装工程施工方案

目录 第一章前 言 (2) 第二章施工优 势 (2) 第三章工程概况及特 点 (3) 第四章主要工程 量 (5) 第五章工程难点特点分析及采取的措 施 (6) 第六章施工部 署 (7) 第七章施工总平面布置及管理措 施 (13) 第八章主要施工方案及措 施 (20) 第九章工程进度计划及管 理 (33) 第十章质量管理及技术管

理 (38) 第十一章职业安全健康保证体 系 (45) 第十二章环境保护及文明施 工 (51) 第十三章特殊条件下的施工措 施 (54) 第十四章计划、统计和信息管 理 (55) 第一章前言 编制说明 本工程施工组织设计是按《》、安装工程招标文件国华乾安一、二期项目风机及箱变基础建筑、国家现行技术法规及施工规范、规程、标准编制的。依据的主要技术标准与规范见下: 风电机组地基基础设计规定(2007) FD003-2007 GB 50009-2001 年版)建筑结构荷载规范(2006GB 50010-2002 混凝土结构设计规范GB 50007-2002 建筑地基基础设计规范 GB 50011-2001 年版)建筑抗震设计规范(2008GB50108—地下工程防水技术规范 2001 GB/T 50105-2001 建筑结构制图标准GB/T 50001-2001 房屋建筑制图统一标准GB 50068-2001 建筑结构可靠度设计统一标准《电力建设施工质量及评定规程》(第1部分:土建工程) 建筑工程施工质量验收统一标准 GB50300-2001 GB50204-2002 混凝土结构工程施工质量验收规范其它有关的现行规程、规范第二章施工优势 一、真诚的感谢业主对我公司的信任,能够给予我公司参与本工程投标机会!我

80MW风电项目升压站土建施工工程施工组织设计

80MW风电项目升压站土建施工工程施工组织设计(80MW风电项目升压站土建施工工程施工组织设计日期:2012年10 月31 日目录一、工程概况及特点1.1 工程概况1.2 工程特点二、施工方案 2.1 施工准备2.2 、施工工序总体安排2.3 、主要工序和特殊工序的施工方法 2.4 、工程成本的控制措施三、工期及施工进度计划 3.1 工程投入的主要施工机械设备情况、主要施工机械进场计划3.2 劳动力安排计划及主要材料设备的供应3.3 确保工期的技术组织措施四、质量目标、质量保证体系及技术组织措施 4.1 质量目标4.2 质量管理组织机构及主要职责4.3 质量管理的措施4.4 质量管理及检验的标准五、安全目标、安全保证体系及技术组织措施 5.1 安全保证体系 5.2 安全管理目标5.3 安全管理组织机构及主要主要职责5.4 保证安全的主要措施5.5 重要施工方案和特殊施工工序的安全过程控制六、环境保护及文明施工 6.1 环境保护6.2 加强施工管理、严格保护环境6.3 文明施工的目标、组织机构和实施方案6.4 文明施工保证措施七、季节性施工措施 7.1 、现场部署: 7.2 、雨施材料的储存和堆放7.3 、施工现场雨季防护措施7.4 、主要项目雨季施工方法附件一: 质量保证体系框图附件二文明施工保证体系框图附件四工期保证体系框图附安全保证体系框图附件 件五临时用地表附件六施工总平面布置图附件七施工进度横道图附件八拟投入工程主要施工机械设备表附件九劳动力计划表附件十拟配备本工程的试验和检测仪器设备表一、工程概况及特点1.1 工程概况1.1.1 工程简述本工程为江苏大丰二期(80MW风电项目升压站土建施工工程,位于江苏大丰港风电场。升压站建设规模:电压等级220kV;容量80MVA 1.1.2 工程承包范围1、主变基础、SVG室、电缆沟改造(总面积约80平米,实际面积以招标图纸为准)2、附属设备、构架基础1.1.3 自然地理大丰港地处北亚热带向南暖温带过渡地带,属季风性湿润气候区。季风盛行,四季分明,热量丰富,降水丰沛。年平均气温和降水量分别为14.2?

风电吊装方案

目录 一工程概况 二施工组织管理 三主要施工方法及技术措施 四主要施工机具配制计划 五质量保证措施 六安全文明施工保证措施及HSE

1.工程概况 1.1项目简介 华电徐闻黄塘风电场位于徐闻县城区东偏北约49.5km 的下洋镇及前山镇,地理坐标为东经110o29′~110o33′,北纬20o46′~20o30′之间。湛江市徐闻县地处中国大陆最南端,地处东经109°52′~110°35′,北纬20°13′~20°43′。三面环海,距离湛江市区149.5 多公里,距离海口市只有18 海里,是大陆通往海南的咽喉之地。徐闻交通四通八达,207国道和粤海铁路贯穿南北,南部有中国最大的汽车轮渡港口(海安港)和亚洲第二大火车轮渡码头(粤海铁路轮渡码头)。 本期工程建设方案拟安装24台2000kW风电机组和1台1500kW 风电机组,总装机容量为49.5MW,110kV升压站已在一期工程中建设完成,升压站内已建设完成综合楼、设备楼以及泵房、仓库、车库、事故油池,总占地面积6396m2。升压变电站工程使用类别在建筑设计中属于工程的等级3等,主要建筑物等级为2等。 1.2设备结构与交货状态 1)设备结构主体由四大件组成:2MW风力发电机组,①塔架②机舱③发电机④叶轮 2)设备交货状态①控制柜②塔架分三段,现场组装③机舱分机舱与发电机,现场组装④叶轮分轮毂与叶片,现场组装

1.3风电机组主要设备部件实物量参数 2MW风电机组主要设备部件实物量参。 序号设备(部件) 名称 数量 件(套) 单件重量 (t) 单件垂直 高度 (mm) 备注 1 塔筒(下段)25 64.1 20000 2 塔筒(中段)25 60.1 27500 3 塔筒(上段)25 41.6 30000 4 机舱2 5 19.5 5 发电机25 66 6 轮毂25 21.5 7 叶片75 9 46500 1.4风力发电机组安装(吊装)采用的主要施工方法 1)设备进场运输,大型吊机进场移动转移,设置临时施工道路。 2)风电机组的周围各设置一个施工平台,进行吊机设备的转场放置。机组与吊机定位吊装的场所,施工平台与施工临时道路相接。 3)小件设备卸车与吊装选用TR-250M(25t)液压汽车式起重机。(包括配合其他吊机)。 4)大件设备吊装选用QAY800(800t)液压汽车式起重机。 5)大件设备吊装抬吊选用QAY260(260t)液压汽车式起重机(包括其他吊装)。 1.5重要工期节点要求 风电机组安装于2014年9月16日开始施工,2014年11月30日前全部吊装完毕。 1.6方案编制依据 1)《安装手册(适用于XE96-2000风力发电机组)》。

风电平台风电道路施工组织设计

目录

表1 编制依据 本施工组织设计是我们详细阅读业主招标文件的基础上,通过施工现场实地踏勘,结合我公司近几年公路施工经验及人员、技术、装备、管理等综合水平编制而成的。如能中标,我们将按施工图设计资料和技术规范要求,进一步细化、优化施工方案,提供一套更详细、更科学、更有效的实施性施工组织设计,以指导工程的顺利实施。 一、工程技术规范 1、依据设计施工图纸和技术文件要求,本工程项目的材料、设备、施工必须达到以下现行中华人民共和国及省、市、行业的一切有关法规、规范的要求,如下述标准及规范要求有出入则以较严格者为准。 2、执行国家、省市现行的建设工程施工及验收规范、施工技术标准、程序,建设工程施工操作规程、“建设工程质量管理条例”、“工程建设强制性标准”、“工程建设标准强制性条文”、“建筑施工安全检查标准”以及有关建筑质量、安全施工等有关文件、规定、施工图纸、技术交底、地质勘察等有关技术说明和“建筑工程质量检验评定标准”,“建筑安装工程质量检验评定统一标准”等。 1.《建筑结构可靠度设计统一标准》 2.《建筑结构制图标准》 3.《中国地震动参数区划图》 4.《建筑抗震设防分类标准》 5.《混凝土结构设计规范》(GB50010-2002) 6.《建筑抗震设计规范》 7.《建筑结构荷载规范》 8.《建筑地基基础设计规范》(GB50007-2002) 9.《钢筋焊接及验收规程》 11.《钢筋机械连接通用技术规程》 12.《地下工程防水技术规范》 13.《混凝土外加剂应用技术规范》 14. 其他见图纸要求。

表2 工程概况 一、项目情况: 国华康保二期300MW风电项目位于河北省康保县境内,地处内蒙古高原南缘,东、西、北紧靠内蒙,南与张家口市张北、尚义、沽源三县毗邻,距张家口市135km,北京市315km。康保二期规划容量300MW,安装120台远景能源2500kW风电机组,轮毂高度80米,叶轮直径110米。 二、招标范围: 本项目吊装道路(检修道路)全长约为150公里,拟修路宽6米(含路肩),施工结构为:清表、道路压实、泥结碎石300mm、磨耗层40mm,道路转弯半径按35m进行控制。140个风机吊装平台(其中:40m×50m 140个),吊装平台施工结构为:就地平整、压实,满足风机基础施 三、项目名称: 国华康保二期300MW风电项目风电场道路(检修道路)、吊装平台施工 工程 招标编号: CSIEZB170100166 资金来源: 企业自筹。 工期要求: 计划2017年4月10日开工(或以甲方通知为准),总工期为70

风电基础施工组织设计

一、施工组织设计 1、工程概况 现场自然条件 铜川市位于陕西省中部,黄土高原南缘,处于关中平原向陕北黄土高原的过渡地带,是关中经济带的重要组成部分,介于东经108°34′-109°29′、北纬34°50′-35“34′之间,是陕西省省辖市。交通便利,是通往人文初祖黄帝陵及革命圣地延安的必经之地,距西安市区68km、距西安咸阳国际机场72km。全市下辖宜君县、王益区、印台区、耀州区和省级经济技术开发区--新区。国华铜川阿庄一期49.5MW风电场工程位于陕西省铜川市印台区东北约20km处的丘陵上,东经109o13′5″~109o18′55″,北纬35o13′35″~35o16′40″,场址高程1200m~1500m,占地约19km2。场址西侧距离包茂高速约20km,南侧距离S305 约10km,其间有县乡级道路相连,交通较为便利。 国华铜川阿庄风电场地理位置见图1.1-1。

图1.1-1 国华铜川阿庄风电场地位置图1.2 区域地质概况 1.2.1 自然地理 1.2.1.1 地形地貌特征及不良地质作用

风场位于铜川市印台区阿庄镇北部,地貌单元主要为低中山、黄土梁峁,高程在1400~1560m,地势总体上北高南低,地表为多为耕地及林地,其中林地植被发育。未见有其他不良地质作用。 1.2.1.2 地层结构及地基土分布特征 根据目前的勘探成果,拟建风场场地地层属第四系上更新统(Q3)风积沉积物,下伏第三系(N)砂岩,各地层简述如下: ①层黄土状粉质粘土(Q3eol):黄褐色,稍湿~湿,可塑,针状孔隙发育,局部可见大孔隙,见虫、根孔,含有腐殖质及植物根须,干强度高。层厚 1.0~4.0m,平均厚度为1.5m。 ②层砂岩(N):浅灰色,岩石主要成分石英,长石,碎屑结构,层状构造,节理裂隙发育,节理面见铁锰质,风化后呈碎屑状或碎块状,强风化厚度一般 1.2.2地质构造与地震 场地地震效应,根据《中国地震动参数区划图》GB18306-2001,拟建场地50 年超越概率10%的地震动峰值加速度0.10g,地震动反应谱特征周期值 0.45s,对应的地震烈度为7 度。 1.2.3 水文气象 铜川地区属于暖温带大陆性季风气候,四季分明,冬长夏短。冬季受来自西伯利亚和蒙古极地大陆气候的控制,干燥寒冷,雨雪稀少;夏季受来自太平洋的暖湿气团影响,炎热湿润,雨水较多;春秋两季气候多变,夏秋易涝,冬春易旱。 1.3 工程基本情况

风电机组安装施工方案

表号:A-1 工程名称:中电投张北大囫囵风电场二期工程编号:

正式方案交监理工程师2份(存档1份、专业监理工程师1份),送建设单位1份。 中电投张北大囫囵风电场二期工程 中电投张北大囫囵风电场二期2#标段风力发电工程 风机安装工程施工方案(作业指导书) 编制单位:山西电建二公司中电投审定单位:黑龙江润华电力工程管理公司张北风电场工程项目部中电投张北风电场项目监理部 批准:年月日总监理师:年月日 审核:年月日专业监理师:年月日 编制:年月日建设单位:年月日 目录

10、成品保护 (18) 11、施工进度计划 (19) 中电投张北大囫囵风电场二期2#标段风力发电工程 风机安装工程施工作业指导书 1.工程概述及工作范围 工程简况 中电投张北大囫囵风电场位于河北省张北县大囫囵镇境内。本工程由中国电力投资有限公司投资,中国电力建设工程咨询公司设计,黑龙江润华电力工程监理有限公司进行监督管理,山西电建二公司承建,风机生产厂家是华锐。 建设规模 本期工程安装33台1500kW的风力发电机组,装机容量为。风机叶轮直径为77m,轮毂高度为70m,机舱重量约58t。

气象、水文 ? 张北县地处坝上高寒区,属中温带亚干旱季风气候,年降水量400毫米左右,年平均气温℃。年平均7级以上大风日数30天左右。全年无霜期90-110天,光照充足,昼夜温差大,干旱、多风、少雨、无霜期短是主要的气候特征。 交通情况 风电场变电站位于河北省张家口市张北县大囫囵镇境内,距离万宝庄村约2km,距张北县城约75km,距张家口市约120km,交通较为便利。 工程特点 单件吊装重(机舱重58t),吊装高度高达70m,组合体吊装受风的影响很大。本工程施工环境地处山区比较偏僻,道路崎岖弯多坡陡,地势高差较大,材料、设备运输困难,施工用电、水比较困难,气候比较寒冷。 工程范围 10台1500KW风机吊装: 风力发电机的吊装、以及配合系统调试、风机的清理等。 包括但不限于塔筒、机舱、发电机、叶轮以及配套的设备部件的到货卸车、保管;吊装设备运输、进出场、机械设备站位、场内拆卸及转移;叶轮的现场组装;塔筒、机舱、发电机、叶轮等的吊装、风机内部电气线缆及设备安装等。 主要设备参数 主要部件参数一览表

风电基础施工组织设计

. 目录 第一章前 言 (2) 第二章施工优 势 (2) 第三章工程概况及特 点 (3) 第四章主要工程 量 (5) 第五章工程难点特点分析及采取的措 施 (6) 第六章施工部 署 (8) 第七章施工总平面布置及管理措 施 (14) 第八章主要施工方案及措 施 (20) 第九章工程进度计划及管

理 (33) 第十章质量管理及技术管 理 (38) 第十一章职业安全健康保证体 系 (45) 第十二章环境保护及文明施 工 (51) 第十三章特殊条件下的施工措 施 (54) 第十四章计划、统计和信息管 理 (55) 专业资料 . 第一章前言 编制说明 本工程施工组织设计是按《》、安装工程招标文件国华乾安一、二期项目风机及箱变基础建筑、国家现行技术法规及施工规范、规程、标准编制的。依据的主要技术标准与规范见下: 风电机组地基基础设计规定(2007) FD003-2007 GB 50009-2001 2006年版)建筑结构荷载规范(GB 50010-2002 混凝土结构设计规范GB 50007-2002 建筑地基基础设计规范 GB 50011-2001 2008年版)建筑抗震设计规范(GB50108—地下工程防水技术规范 2001 GB/T 50105-2001 建筑结构制图标准GB/T 50001-2001 房屋建筑制图统一标准GB 50068-2001 建筑结构可靠度设计统一标准 《电力建设施工质量及评定规程》(第1部分:土建工程)

建筑工程施工质量验收统一标准 GB50300-2001 GB50204-2002 混凝土结构工程施工质量验收规范 其它有关的现行规程、规范 第二章施工优势 一、真诚的感谢业主对我公司的信任,能够给予我公司参与本工程投标机会!我们深知本工程的特殊性与重要性,我公司从上到下表现出了高度的重视程度,我们将会十分珍惜此次机遇。 二、接到招标文件和设计图纸后,我公司多次组织工程技术管理人员对招标文件和图纸进行了仔细认真的研究,并组织了各个专题会对该项工程的特点、重点、难点进行反复的研究和方案论证比较,并认真的准备了该工程投标预备会的答疑文件,其目的是使施工组织设计科学、合理、详尽,具有很强的可操作性和针对性。 三、我公司通过认真研究招标文件和图纸后对本工程的“桩基础施工方案”、“混凝土专业资料 . 施工方案”、“安装工程施工方案”、“工程测量和检验试验方案”、“工程进度计划安排和进度计划保证措施”、“工程质量保证创优方案”、“对各专业承包商的工程总承包管理和协调,与业主、设计、监理和政府部门的配合协作措施”等工程的重点和难点,进行了认真的方案设计论证和方案研究比选,这将是本工程施工组织设计的重点内容。 四、我公司承建过许多类似工程,在上述工程的重点和难点方面积累了较为丰富的施工经验,积累了一套成熟先进的施工技术和管理经验,为工程的圆满完成奠定坚实的基础,我们将结合本工程的特点,针对上述重点和难点制定专项的施工方案和保证措施。 五、我公司为本工程所选派的项目经理部的管理人员已经全部拟定,其中项目经理和技术负责人,均承担过类似的工程,本项目经理部的管理人员综合素质高、业务能力强、作风过硬、具有类似工程和类似工程的关键技术的实践经验和技术管理水平,这将是我公司最为优秀的项目管理班子之一。 六、在工程上,我公司会积极、主动、高效为业主服务,秉承“急业主所急、想业主所想”的指导思想,努力拓展并延伸为业主、设计、监理等有关各方的服务范围和内涵,处理好与业主、监理、设计、各专业分包及相关政府部门的关系,与业主、设计、监理密切配合,诚心诚意接受业主工程师、监理工程师和设计人员在施工全过程中的指导、监督和热忱帮助,使工程各方形成一个团结、协作、高效、和谐、健康的有机整体,形成合力共同促进项目综合目标的实现。 第三章工程概况及特点 1.1工程概况

风电基础施工组织设计概述(doc 63页)

风电基础施工组织设计概述(doc 63页)

工程施工组织设计 华润唐河九龙250MW风电场一期70MW工程 风机基础工程 施工组织设计 - 0 -

工程施工组织设计 施工单位(章) ________年____月____日 河南省金鹰电力勘测设计有限公司 华润唐河九龙250MW风电场一期70MW工程 风机基础工程

工程施工组织设计审批:____________ ________年____月____日 审核:____________ ________年____月____日 编制:____________ ________年____月____日 施工单位(章) ________年____月____日 河南省金鹰电力勘测设计有限公司 目录 第一章、工程概况 (6) 1.1工程基本情况 ..................................... . (6) 1.2区域地质概况 (6) 1.3水文、气象条件 (8) 1.4交通、通讯条件 (8) 第二章、施工组织管理机构 (9)

工程施工组织设计 2.1 施工组织机构关系图 (9) 2.2 施工布置及任务划分 (9) 2.2.1 施工布置 (9) 2.2.2 任务划分 (11) 第三章、施工方案及工期安排 (12) 3.1 施工方案 (12) 3.2 工期安排 (12) 第四章、各分部分项工程的主要施工方法 (13) 4.1 基础施工 (13) 4.1.1 风电机组布置 (13) 4.1.2 地基与基础 (13) 4.2 风机基础施工方案 (14) 4.2.1基坑开挖施工方案和措施 (14) 4.2.2施工方法及技术控制措施 (14) 4.2.2.1测量放线 (14) 4.2.2.2基坑开挖 (15) 4.2.2.3基底检验 (15) 4.3 风机基础施工 (15) 4.3.1垫层施工 (15) 4.3.2基础混凝土施工 (16) 4.3.3基础支模 (17) 4.3.4钢筋施工 (18) 4.3.5预埋管及预埋件施工 (18) 4.3.6基础环止水 (20) 4.3.7土方回填 (20) 4.3.8接地网及预埋管线施工 (21) 4.3.9钢筋工程施工 (22) 4.3.10混凝土施工 (22) 4.3.11混凝土搅拌及运输 (25) 4.3.12风机基础沉降观测 (27) 第五章、工程投入的主要施工机械设备情况、主要施工机械进场计划 (27) 5.1 工程投入的主要施工机械设备情况 (27) 5.2 主要施工机械进场计划 (27) 第六章、劳动力安排计划及主要材料设备的供应 (28) 6.1 劳动力安排计划....................................... . .28 6.2 主要材料设备的供应 (29) 6.3 确保材料质量的措施..................................... .31 第七章、确保工程质量的技术组织措施 (31) 7.1 质量保证体系 (31) 7.2 保证工程质量的技术保证措施 (32) 第八章、确保安全生产的技术组织措施 (33)

风电基础混凝土施工方案正式样本

文件编号:TP-AR-L7684 In Terms Of Organization Management, It Is Necessary To Form A Certain Guiding And Planning Executable Plan, So As To Help Decision-Makers To Carry Out Better Production And Management From Multiple Perspectives. (示范文本) 编制:_______________ 审核:_______________ 单位:_______________ 风电基础混凝土施工方 案正式样本

风电基础混凝土施工方案正式样本 使用注意:该解决方案资料可用在组织/机构/单位管理上,形成一定的具有指导性,规划性的可执行计划,从而实现多角度地帮助决策人员进行更好的生产与管理。材料内容可根据实际情况作相应修改,请在使用时认真阅读。 一、编制依据 1、《风机基础施工图》(F0805S-T0107) 2、图纸会审及变更文件 3、施工合同及招标文件 4、《混凝土工程施工质量验收规范》 (GB50204-2002) 5、施工手册(第四版) 6、风力发电场项目建设工程验收规程 (DL/T5191-2004) 二、工程概况 本工程浇筑的单个风机基础混凝土总浇筑量大约

为540m3,拟采用搅拌站集中搅拌,以混凝土罐车进行水平运输,混凝土泵车入仓,插入式振捣器振捣。整个基础一次连续浇注完成,不留施工缝。 三、施工用工器具及人员组织 采用2台(30kW柴油发电机和15kW柴油发电机)作为施工电源及备用电源。 水准仪1台测温仪器 1台 30m钢卷尺1副 5m钢卷尺1副坍落度桶1个试块模具 6套施工管理人员2人混凝土工7人电工 1人木工 3人试验人员1人照明器具 4个 四、施工方案及工艺流程 1、混凝土浇筑 1.1混凝土由本工程搅拌站负责供应。浇筑混凝土时,现场分两班,每班混凝土工7人、技术人员1人,质检员1人,协调员1人,浇筑过程连续不间

1.风电项目管理总目标

1. 风电项目管理总目标 项目管理总目标 1 范围 1.1 本管理目标规定了项目部存续期间对工程项目进行管理的标准、要求和目标。 1.2 本管理目标适用于公司风电分公司所有承建工程的项目管理。 1.3 因为某具体工程特点、市场状况等外部条件变化,某些内容可能修改,其原则为本项目管理目标框架不变,确需变化内容可在本项目的《施工组织设计》及《内部经济责任承包考核协议》中作出明确规定。 2 引用标准 2.1 《电力建设工程质量监督检查典型大纲(风力发电部分)2019 版》 2.2 《风力发电厂项目建设工程验收规范》DL/T 5191-200 2.3 《风力发电机组验收规范》GB/T20319-2019 2.4 《湖南省火电建设公司“十五”计划及2019 年远景规划》 2.5 《湖南省火电建设公司内部经济责任制考核办法》 3 术语 3.1 项目部 指公司根据承接的工程项目,为确保完成合同要求成立的组织,受公司委派对该项工程进行管理,对工程项目的安全文明施工、质量、工期和成本等负全面责任。 4 管理职能 4.1 项目经理受公司委派对工程项目管理目标负全面责任。 4.2 项目执行经理全面负责工程项目的现场管理,对工程现场管理目标负直接领导责任。 4.3 项目部所属管理部室各自对其分管专业(业务)的管理目标(或分解目标)负直接责任。5 管理内容与要求 5.1 精神文明管理目标 5.1.1 培育遵纪守法、勇于任事、敢为人先、诚实守信、文明礼貌,优质服务、追求卓越的队伍。 5.1.2 项目部综合治理违纪人员每年度不超过0.1%。

5.1.3 加强班组建设:全年合格班组率达90%以上,其中优秀班组率》20%先进班组 率》30% 1 5.2 安全、环境管理:整个工程自始至终保持良好的安全局面。 目标:实现“五无二控一创建”。 即:无人身死亡及重伤事故; 无群伤事故和重大责任事故; 无重大施工机械损坏和重大设备损坏事故; 无重大火灾和重大交通事故; 无重大环境污染事故; 杜绝职业病发生; 年度人身重伤率控制在0.5 %。以下; 年度人身轻伤率控制在3%o以下; 创建全国一流的安全文明施工现场。 5.3 质量管理 5.3.1 质量目标 5.3.1.1 全面执行国家和电力行业颁布的有关规范、标准,使工程范围内的建筑、安 装、调试项目的合格率达到100%;单位工程优良率达96%以上。 5.3.1.2 杜绝重大质量事故及造成永久性缺陷的事故。 5.3.1.3 工艺规范美观,消除质量通病,实现“零”缺陷进入250小时试运。试运期 间平均设备可利用率不低于95%。 5.3.1.4 250 小时测试运行期间,单机同一故障停机次数不超过6次,累计故障时间不超过12h 。 5.3.1.5 严格遵守国家环保法律、法规,确保厂区绿化、风场环保指标达到合同要求。 5.3.1.6 提供优质服务,兑现“用户满意”的服务承诺,不发生业主投拆事件。